March Sale - Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70dumps

 PMI-SP Dumps with Practice Exam Questions Answers

Questions: 323 questions

Last Update: Mar 29, 2024

PMI Certification Exam PMI-SP has been designed to measure your skills in handling the technical tasks mentioned in the certification syllabus

PMI-SP Exam Last Week Results!

20

Customers Passed
PMI PMI-SP

85%

Average Score In Real
Exam At Testing Centre

95%

Questions came word by
word from this dump

An Innovative Pathway to Ensure Success in PMI-SP

DumpsTool Practice Questions provide you with the ultimate pathway to achieve your targeted PMI Exam PMI-SP IT certification. The innovative questions with their interactive and to the point content make your learning of the syllabus far easier than you could ever imagine.

Intensive Individual support and Guidance for PMI-SP

DumpsTool Practice Questions are information-packed and prove to be the best supportive study material for all exam candidates. They have been designed especially keeping in view your actual exam requirements. Hence they prove to be the best individual support and guidance to ace exam in first go!

PMI-SP Downloadable on All Devices and Systems

PMI PMI Certification PMI-SP PDF file of Practice Questions is easily downloadable on all devices and systems. This you can continue your studies as per your convenience and preferred schedule. Where as testing engine can be downloaded and install to any windows based machine.

PMI-SP Exam Success with Money Back Guarantee

DumpsTool Practice Questions ensure your exam success with 100% money back guarantee. There virtually no possibility of losing PMI PMI Certification PMI-SP Exam, if you grasp the information contained in the questions.

24/7 Customer Support

DumpsTool professional guidance is always available to its worthy clients on all issues related to exam and DumpsTool products. Feel free to contact us at your own preferred time. Your queries will be responded with prompt response.

PMI PMI-SP Exam Materials with Affordable Price!

DumpsTool tires its level best to entertain its clients with the most affordable products. They are never a burden on your budget. The prices are far less than the vendor tutorials, online coaching and study material. With their lower price, the advantage of DumpsTool PMI-SP PMI Scheduling Professional Practice Questions is enormous and unmatched!

PMI PMI-SP Practice Exam FAQs

1. To what extent DumpsTool PMI-SP products are relevant to the Real Exam format?

DumpsTool products focus each and every aspect of the PMI-SP certification exam. You’ll find them absolutely relevant to your needs.

2. To what extent DumpsTool’s products are relevant to the exam format?

DumpsTool’s products are absolutely exam-oriented. They contain PMI-SP study material that is Q&As based and comprises only the information that can be asked in actual exam. The information is abridged and up to the task, devoid of all irrelevant and unnecessary detail. This outstanding content is easy to learn and memorize.

3. What different products DumpsTool offers?

DumpsTool offers a variety of products to its clients to cater to their individual needs. DumpsTool Study Guides, PMI-SP Exam Dumps, Practice Questions answers in pdf and Testing Engine are the products that have been created by the best industry professionals.

4. What is money back guarantee and how is it applicable on my failure?

The money back guarantee is the best proof of our most relevant and rewarding products. DumpsTool’s claim is the 100% success of its clients. If they don’t succeed, they can take back their money.

5. What is DumpsTool’s Testing Engine? How does it benefit the exam takers?

DumpsTool PMI-SP Testing Engine delivers you practice tests that have been made to introduce you to the real exam format. Taking these tests also helps you to revise the syllabus and maximize your success prospects.

6. Does DumpsTool offer discount on its prices?

Yes. DumpsTool’s concentration is to provide you with the state of the art products at affordable prices. Round the year, special packages and discounted prices are also introduced.

PMI-SP Questions and Answers

Question # 1

Wendy is the project manager for the NHQ project. She is working with her project to begin creating the project duration estimate. Her organization is in weak matrix and several of the project team members are scheduled to complete work on other projects. What input will most likely be of the biggest assistance as Wendy and the project team begin creating the duration estimate for this project?

A.

Project charter

B.

Project scope statement

C.

Project communications management plan

D.

Resource calendar

Question # 2

You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned and they'd like to know what is your schedule performance index. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450, what is the SPI for this project?

A.

$227,140

B.

0.75

C.

0.95

D.

-$56,789

Question # 3

Ned is the project manager for his organization. Ned is using a standard tool to capture, store, and distribute information to the stakeholders about the project costs, schedule, and performance. What term is assigned to this communication tool?

A.

Project management information system

B.

Table reporting

C.

Reporting system

D.

Communications management system

Question # 4

You have 83 project stakeholders from all across your organization. Some of the stakeholders, such as functional management, require weekly communication from you, while other stakeholders, such as the end users, only need quarterly progress updates. Where can you record this communication requirements based on your stakeholder analysis?

A.

Project communications management plan

B.

Project reporting structure

C.

Project schedule

D.

Project scope management plan

Question # 5

You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned and they'd like to know what your schedule variance is. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450. What is the schedule variance for this project?

A.

-$45,789

B.

-$56,790

C.

There is not enough information to know.

D.

-$30,268