(The Developers ask their Product Owner to re-order the Product Backlog. The team is waiting for an external supplier to deliver a component. Without that component, there will not be enough work in the next Sprint to occupy the full team. As the Scrum Master, what advice would you give the Product Owner?
Choose the best answer.)
Who is responsible for the sizing of Product Backlog items?
(choose the best answer)
What are two responsibilities of testers in a Development Team? (Choose two.)
Which of the following is an example of an Increment? (Choose the best answer.)
(Several Sprints into a project, the Product Owner tells the Scrum Master that a key stakeholder has just started using the product. The stakeholder is unhappy with the quality of the product, and the Product Owner agrees with the stakeholder’s assessment that the quality is low. How should the Scrum Master respond to the Product Owner?
Choose the best two answers.)
Who should know the most about the progress toward a business objective or a release?
As the Development Team starts work during the Sprint, it realizes it has selected too much work to finish in the Sprint. What should it do?
User documentation is part of your Definition of Done. However, there are not enough technical writers for all teams. Your Scrum Team does not have a technical writer. What should the Scrum Team do?
(choose the best answer)
(What should the Scrum Team do during the first Sprint?
Choose the best answer.)
Which of the following are true about the length of the Sprint? (Choose two.)
The Sprint Review is mainly an inspect and adapt opportunity for which group?
What are two effective ways for the Scrum Team to make non-functional requirements visible?
(choose the best two answers)
A Scrum Master is keeping a list of open impediments, but it is growing and they have been able to resolve only a small portion of the impediments. Which two techniques would be most helpful in this situation?
(Choose two.)
(When does a Developer become accountable for an item in the Sprint Backlog?
Choose the best answer.)
A Scrum Master is working with a Development Team that has members in different physical locations. The Development Team meets in a variety of meeting rooms and has much to do logistically (for example, set up conference calls) before the Daily Scrum. What action should the Scrum Master take?
Which of the following are roles on a Scrum Team? (Choose all that apply.)
A Product Owner wants advice from the Scrum Master about estimating work in Scrum. Which of these is the guideline that a Scrum Master should give?
Who is responsible for collaboration with stakeholders?
(choose the best answer)
Which three of the following are time-boxed events in Scrum? (Choose the best three answers.)
(The Definition of Done serves which three purposes?
Choose the best three answers.)
Which are appropriate topics for discussion in a Sprint Retrospective? (Choose the best three answers.)
(What are two effective ways for a Scrum Team to ensure security concerns are satisfied?
Choose the best two answers.)
A new developer is having continuing conflicts with existing Development Team members and creating the hostile environment. If necessary, who is responsible for removing the team member?
The CEO asks the Developers to add a " very important " item to a Sprint that is in progress.
What should the Developers do?
(choose the best answer)
The CEO asks the Development Team to add a “very important” item to a Sprint that is in progress. What should the Development Team do?
How much of the Sprint Backlog must be defined during the Sprint Planning event?
The Product Owner makes sure the team selects enough from the Product Backlog for a Sprint to satisfy the stakeholders.
Who is accountable for managing the progress ot work during a Sprint?
(choose the best answer)
During Sprint Planning the Product Owner and the Developers are unable to reach an
understanding about the highest order Product Backlog items. Because of this, the Developers
are unable to determine how many Product Backlog items they can forecast for the upcoming
Sprint However, the Product Owner and the Developers are able to agree on a Sprint Goal.
Which of the following actions should the Scrum Master support?
(choose the best two answers)
The IT manager asks a Development Team for a status report describing the progress throughout the Sprint.
The Development Team asks the Scrum Master for advice. The Scrum Master should:
(Choose the best answer.)
Marian is the Product Owner envisioning a project for a new release of her product. She made a projection of a release date based upon a sustained velocity of 17 completed units of work per Sprint. Over the first 3 Sprints, the average velocity was 13 for work that the Development Team estimated as 90% done. The Development Teams, feeling the need to meet the plan, figured that a velocity of 17 was within their reach.
A good way to continue is:
During a Sprint Retrospective, the Development Team proposes moving the Daily Scrum to only occur on Tuesdays and Thursdays. Which two are the most appropriate responses for the Scrum Master? (Choose two.)
Which two activities will a Product Owner engage in during a Sprint? (Choose two.)
Which two things should the Development Team do during the first Sprint? (Choose two.)
When must the Product Owner participate in the Dairy Scrum? (choose the best answer)
Who is accountable for clearly expressing Product Backlog items? (Choose the best answer.)
When a Development Team determines that it will not be able to finish the complete forecast, who has to be
present when reviewing and adjusting the Sprint work selected? (Choose the best answer.)
The Scrum Team should have all the skills needed to:
(choose the best answer)
As the Sprint Planning progresses, the Developers realize that the workload may be greater
than their capacity to complete the work. Which two are valid actions?
(choose the best two answers)
Currently, your Development Teams are organized to address a single layer only (for example, front end, middle tier, back end, and interfaces). What are three things to consider when deciding to move away from such component teams toward feature teams? (Choose three.)
Which two of the following are true about the Scrum Master role? (Choose two.)
Who should make sure everyone on the scrum Team does their tasks for the sprint? (choose the best answer)
What does n mean tor a scrum Team to be cross-function at? (choose the best answer)
How should a Scrum Team deal with non-functional requirements?
(choose the best answer)
Which Scrum Values are exhibited by not building Product Backlog items that have low business value? (Choose three.)
How do you know that a Scrum Team is cross-functional? (Choose the best answer.)
At the end of a Sprint Product Backlog item worked on during the Sprint does not meet the definition of “Done”. What two things should happen with the undone Product Backlog item? (Choose two.)
Which two things are appropriate for a Scrum Master to do if the Development Team doesn’t have the engineering tools and infrastructure to completely finish each selected Product Backlog item? (Choose two.)
The Scrum Master observes the Product Owner struggling with ordering the Product Backlog. What is an appropriate action for the Scrum Master to take?
Which two of the following are appropriate topics for discussion during a Sprint Retrospective? (Choose two.)
If two Scrum Teams are added to the development of a product that previously had only one Scrum Team, what will be the immediate impact on the productivity of the original Scrum Team?
Which of these may a Scrum Team deliver at the end of a Sprint?
(choose the best answer)
What happens if the Development Team cannot complete its work by the end of the Sprint?
(A new Developer is having continuing conflicts with existing members of the Scrum Team, which is impacting the delivery of the Increment. If necessary, who is responsible for removing the Developer from the Scrum Team?
Choose the best answer.)
True or False: The purpose of a Sprint Is lo produce a valuable useful Inclement.
Several Sprints into a project, the Product Owner tells the Scrum Master that a key stakeholder just started using the product. The stakeholder is unhappy with the quality of the product, and the Product Owner agrees with the stakeholder’s assessment that the quality is low. How should the Scrum Master respond to the Product Owner?
(choose the best two answers)
Which two ways of creating Scrum Teams are consistent with Scrum ' s values?
(choose the best two answers)
What is the best suited structure for Development Teams in order to produce integrated Increments?
For the purpose of transparency, when does Scrum say a new increment of working software must be available?
Who does the work to make sure Product Backlog items conform to the Definition of Done?
(choose the Best answer)
What is the key concern when multiple Development Teams are working from the same Product Backlog?
(Which outcome is expected as a Scrum Team matures?
Choose the best answer.)
When many Development Teams are working on a single product, what best describes the definition of “Done”? (Choose the best answer.)
What are two good ways for the Development Team to make non-functional requirements visible? (Choose two.)