Spring Sale - Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70dumps

PSM-I Questions and Answers

Question # 6

(The Developers ask their Product Owner to re-order the Product Backlog. The team is waiting for an external supplier to deliver a component. Without that component, there will not be enough work in the next Sprint to occupy the full team. As the Scrum Master, what advice would you give the Product Owner?

Choose the best answer.)

A.

Remind the Product Owner that their primary concern is the flow of value reflected in the ordering of the Product Backlog.

B.

Tell the Product Owner to re-order the Product Backlog so the work involving the external component can be planned in a separate Sprint.

C.

Tell the Product Owner that the Product Backlog should be ordered to maximize utilization of the Developers.

Full Access
Question # 7

Who is responsible for the sizing of Product Backlog items?

(choose the best answer)

A.

The Developers after clarifying requirements with the Product Owner

B.

The Scrum Master.

C.

The Product Owner with input from the Developers.

D.

The Developers, alone.

E.

The most senior people in the organization, including architects and subject matter experts.

Full Access
Question # 8

What are two responsibilities of testers in a Development Team? (Choose two.)

A.

Verifying the work of programmers.

B.

Everyone in the Development Team is responsible for quality.

C.

Tracking quality metrics.

D.

Finding bugs.

E.

Scrum has no “tester” role.

Full Access
Question # 9

Which of the following is an example of an Increment? (Choose the best answer.)

A.

A plan for the overall product release.

B.

A mock-up of the product marketing materials.

C.

A design for the product.

D.

A product roll-out plan.

E.

A valuable, useful set of products featured.

F.

All of the above.

Full Access
Question # 10

(Several Sprints into a project, the Product Owner tells the Scrum Master that a key stakeholder has just started using the product. The stakeholder is unhappy with the quality of the product, and the Product Owner agrees with the stakeholder’s assessment that the quality is low. How should the Scrum Master respond to the Product Owner?

Choose the best two answers.)

A.

Explain to the Product Owner that it is up to the Developers to decide on acceptable quality standards.

B.

Encourage the Product Owner to include quality specifications in the Product Backlog and to communicate the stakeholders ' concerns to the Developers.

C.

Work with the Product Owner to understand their desired resolution and help formulate an approach for raising the concern with the Developers.

D.

Bring the concern to the testers to improve how the product is verified.

E.

Tell the Product Owner they have noted the concern and will raise this issue at the Sprint Retrospective.

Full Access
Question # 11

Who should know the most about the progress toward a business objective or a release?

A.

The Project Manager.

B.

The Scrum Master.

C.

The Development Team.

D.

The Product Owner.

Full Access
Question # 12

Sprint burndown charts are an efficient tracking tool, because they show:

A.

An estimate of the total work remaining for the Sprint.

B.

How much effort has gone into a Sprint.

C.

How many hours have been worked by each Development Team member.

D.

How many Product Backlog items remain.

Full Access
Question # 13

As the Development Team starts work during the Sprint, it realizes it has selected too much work to finish in the Sprint. What should it do?

A.

Inform the Product Owner at the Sprint Review, but prior to the demonstration.

B.

Find another Scrum Team to give the excess work to.

C.

As soon as possible in the Sprint, work with the Product Owner to remove some work or Product Backlog items.

D.

Reduce the definition of “Done” and get all of the Product Backlog items “Done” by the new definition.

Full Access
Question # 14

The time-box for a Daily Scrum?

A.

Two minutes per person.

B.

15 minutes.

C.

15 minutes for a 4 week sprint. For shorter Sprints it is usually shorter.

D.

4 hours.

E.

The same time of day every day.

Full Access
Question # 15

User documentation is part of your Definition of Done. However, there are not enough technical writers for all teams. Your Scrum Team does not have a technical writer. What should the Scrum Team do?

(choose the best answer)

A.

Let the user documentation remain undone and accumulate until after the last development Sprint. It will then be done by any available technical writers.

B.

The Developers on the Scrum Team should write the user documentation.

C.

Wait until you have a technical writer on your Scrum Team to take care of this.

D.

Form a separate team of technical writers that will work on an on-demand basis for the various Product Owners. Work order will be first in, first out.

Full Access
Question # 16

(What should the Scrum Team do during the first Sprint?

Choose the best answer.)

A.

Analyze, describe, and document the requirements for the subsequent Sprints.

B.

Define the major product features and a release plan architecture.

C.

Make up a plan for the rest of the project.

D.

Create at least one valuable and useful Increment.

Full Access
Question # 17

Which of the following are true about the length of the Sprint? (Choose two.)

A.

The length of the Sprint should be proportional to the work that is done in between Sprints.

B.

It is best to have Sprints of consistent length throughout a development effort.

C.

Sprint length is determined during Sprint Planning, and should hold the time it will take to code the planned features in the upcoming Sprint, but does not include time for any testing.

D.

Sprint length is determined during Sprint Planning, and should be long enough to make sure the Development Team can deliver what is to be accomplished in the upcoming Sprint.

E.

All Sprints must be 1 month or less.

Full Access
Question # 18

The Sprint Review is mainly an inspect and adapt opportunity for which group?

A.

The Development Team and stakeholders.

B.

The Product Owner and Development Team.

C.

The Scrum Team and stakeholders.

D.

The Product Owner and management.

E.

The Development Team and management.

F.

The Product Owner and stakeholders.

Full Access
Question # 19

What are two effective ways for the Scrum Team to make non-functional requirements visible?

(choose the best two answers)

A.

Run the integration and regression tests before the end of the Sprint, and

capture the open work for the Sprint Backlog of the next Sprint.

B.

Put them on a separate list on the Scrum board, available for all to see.

C.

Add them to the Definition of Done so the work is taken care of every Sprint.

D.

Add them to the Product Backlog to ensure transparency.

Full Access
Question # 20

What is the role of management in Scrum?

A.

To facilitate the Scrum Teams with insights and resources that help them improve.

B.

To monitor the Development Team’s productivity.

C.

To identify and remove people that aren’t working hard enough.

D.

To continually monitor staffing levels of the Development Team.

Full Access
Question # 21

A Scrum Master is keeping a list of open impediments, but it is growing and they have been able to resolve only a small portion of the impediments. Which two techniques would be most helpful in this situation?

(Choose two.)

A.

Discuss the impediments with the Development Team.

B.

Prioritize the list and work on them in order.

C.

Arrange a triage meeting with all project managers.

D.

Add each open impediment to the Product Backlog.

Full Access
Question # 22

(When does a Developer become accountable for an item in the Sprint Backlog?

Choose the best answer.)

A.

During the Daily Scrum.

B.

Never. All Developers on the Scrum Team share accountability for items in the Sprint Backlog.

C.

As soon as a Developer on the Scrum Team can accommodate more work.

D.

At Sprint Planning when all of the Sprint Backlog items are split evenly across the Developers.

Full Access
Question # 23

A Scrum Master is working with a Development Team that has members in different physical locations. The Development Team meets in a variety of meeting rooms and has much to do logistically (for example, set up conference calls) before the Daily Scrum. What action should the Scrum Master take?

A.

Allow the Development Team to self-manage and determine for itself what to do.

B.

Set up the meeting and tell the Development Team that is how it will be done.

C.

Ask the Development Team members to alternate who is responsible for meeting setup.

D.

Inform management and ask them to solve it.

Full Access
Question # 24

Which of the following are roles on a Scrum Team? (Choose all that apply.)

A.

Users

B.

Scrum Master

C.

Product Owner

D.

Development Team

E.

Customers

Full Access
Question # 25

A Product Owner wants advice from the Scrum Master about estimating work in Scrum. Which of these is the guideline that a Scrum Master should give?

A.

Product Backlog items must be estimated in story points.

B.

Estimates are made by the Development Team.

C.

Estimates must be in relative units.

D.

Scrum forbids estimating.

E.

Estimates are made by the Product Owner, but are best checked with the Development Team.

Full Access
Question # 26

Who is responsible for collaboration with stakeholders?

(choose the best answer)

A.

The Business Analyst.

B.

The Scrum Team.

C.

The Team Manager.

D.

The Project Manager.

E.

The Developers.

Full Access
Question # 27

Which three of the following are time-boxed events in Scrum? (Choose the best three answers.)

A.

Release Planning.

B.

Release Retrospective.

C.

Sprint Retrospective.

D.

Sprint Planning.

E.

Sprint Testing.

F.

Sprint 0.

G.

Daily Scrum.

Full Access
Question # 28

(The Definition of Done serves which three purposes?

Choose the best three answers.)

A.

Guide the Developers on how many Product Backlog items to select for the Sprint.

B.

Describe the work that must be mostly done before the Sprint is allowed to end.

C.

Increase transparency.

D.

Describe the purpose, objective, and timebox of each Scrum event.

E.

Create a shared understanding of when work is complete.

Full Access
Question # 29

Which are appropriate topics for discussion in a Sprint Retrospective? (Choose the best three answers.)

A.

Arranging the Sprint Backlog for the next Sprint.

B.

The value of work currently represented in the Product Backlog.

C.

Team relations

D.

Definition of Done.

E.

How the Scrum Team does its work.

Full Access
Question # 30

(What are two effective ways for a Scrum Team to ensure security concerns are satisfied?

Choose the best two answers.)

A.

Delegate the work to the security department.

B.

Have the Scrum Team create Product Backlog items for each concern.

C.

Add security concerns to the Definition of Done.

D.

Postpone the work until a specialist can perform a security audit and create a list of security-related Product Backlog items.

E.

Add a Sprint to specifically resolve all security concerns.

Full Access
Question # 31

A new developer is having continuing conflicts with existing Development Team members and creating the hostile environment. If necessary, who is responsible for removing the team member?

A.

The hiring manager is responsible, because he/she hired the developer.

B.

The Scrum Manager is responsible, because he/she removes Impediments.

C.

The Development Team is responsible, and may need help from the Scrum Master.

D.

The Product Owner is responsible, because he/she controls the return on investment (ROI).

Full Access
Question # 32

Who must attend the Daily Scrum?

A.

The Scrum Master and Product Owner.

B.

The Development Team.

C.

The Development Team and Product Owner.

D.

The Scrum Team.

E.

The Development Team and Scrum Master.

Full Access
Question # 33

Who can cancel a Sprint?

(choose the best answer)

A.

The Scrum Master

B.

The Scrum Team.

C.

The Stakeholders.

D.

The Product Owner.

Full Access
Question # 34

Who is responsible for managing the progress of work during a Sprint?

A.

The Scrum Master.

B.

The Development Team.

C.

The Product Owner.

D.

The most junior member of the Team.

Full Access
Question # 35

The Development Team should have all the skills needed to:

A.

Turn Product Backlog items into an Increment of potentially releasable product functionality.

B.

Do all of the development work, except for specialized testing that requires additional tools and environments.

C.

Complete the project within the date and cost as calculated by the Product Owner.

Full Access
Question # 36

The CEO asks the Developers to add a " very important " item to a Sprint that is in progress.

What should the Developers do?

(choose the best answer)

A.

Add the item to the top of the Product Backlog.

B.

Add the item to the current Sprint Backlog and begin work immediately since the

request came from the CEO.

C.

Add the item to the Sprint Backlog for the next Sprint.

D.

Discuss the item with the other members of the Scrum Team so the team can

decide what to do.

E.

Add the item to the current Sprint and drop an item of equal size.

Full Access
Question # 37

During a Sprint Retrospective, for what is the Scrum Master responsible?

A.

Prioritizing the resulting action items.

B.

Participating as a Scrum team member and facilitating as requested or needed.

C.

Acting as a scribe to capture the Development Team’s answers.

D.

Summarizing and reporting the discussions to management.

Full Access
Question # 38

When does the next Sprint begin?

A.

When the Product Owner is ready.

B.

Immediately after the conclusion of the previous Sprint.

C.

The Monday following the Sprint Review.

D.

Immediately following the next Sprint Planning.

Full Access
Question # 39

The CEO asks the Development Team to add a “very important” item to a Sprint that is in progress. What should the Development Team do?

A.

Add the item to the current Sprint and drop an item of equal size.

B.

Add the item to the current Sprint without any adjustments.

C.

Inform the Product Owner so he/she can work with the CEO.

D.

Add the item to the next Sprint.

Full Access
Question # 40

How much of the Sprint Backlog must be defined during the Sprint Planning event?

A.

Just enough tasks for the Scrum Master to be confident in the Development Team’s understanding of the Sprint.

B.

The entire Sprint Backlog must be identified and estimated by the end of the Sprint Planning meeting.

C.

Enough so the Development Team can create its best forecast of what is can do, and to start the first several days of the Sprint.

D.

Just enough to understand design and architectural implications.

Full Access
Question # 41

Every Development Team should have:

A.

At least one representative from each major software engineering discipline (like QA, Dev, UX).

B.

The competencies and skills needed to deliver a Done Increment in a Sprint.

C.

One Lead Developer and no more than 8 other members.

Full Access
Question # 42

Who has the final say on the order of the Product Backlog?

A.

The Development Team.

B.

The Product Owner.

C.

The Scrum Master.

D.

The Stakeholders.

E.

The CEO.

Full Access
Question # 43

The Product Owner makes sure the team selects enough from the Product Backlog for a Sprint to satisfy the stakeholders.

A.

True

B.

False

Full Access
Question # 44

Who is accountable for managing the progress ot work during a Sprint?

(choose the best answer)

A.

The Product Owner.

B.

The Developers.

C.

The Scrum Master.

D.

The most junior member ot the team.

Full Access
Question # 45

During Sprint Planning the Product Owner and the Developers are unable to reach an

understanding about the highest order Product Backlog items. Because of this, the Developers

are unable to determine how many Product Backlog items they can forecast for the upcoming

Sprint However, the Product Owner and the Developers are able to agree on a Sprint Goal.

Which of the following actions should the Scrum Master support?

(choose the best two answers)

A.

Cancel the Sprint Send the entire team to an advanced Scrum training and then

start a new Sprint

B.

During the next Sprint Retrospective discuss why this happened and what

changes will make it less likely to recur.

C.

Continue the Sprint Planning event past its timebox until an adequate number ot

Product Backlog items are well enough understood for the Developers to make a

complete forecast Then start the Sprint

D.

Forecast the Product Backlog items that are most likely to meet the Sprint Goal

and create the Sprint Backlog. Conclude Sprint Planning and start the

development work. Continue to analyze, decompose, and create additional

functionality during the Sprint

E.

Ask everyone to take as much time as needed to analyze the Product Backlog

first, and then reconvene another Sprint Planning meeting.

Full Access
Question # 46

What is included in the Sprint Backlog?

A.

User Stories.

B.

Tasks.

C.

Use Cases.

D.

Tests.

E.

Any of the above (or others) which are a decomposition of the selected Product Backlog items.

Full Access
Question # 47

The IT manager asks a Development Team for a status report describing the progress throughout the Sprint.

The Development Team asks the Scrum Master for advice. The Scrum Master should:

(Choose the best answer.)

A.

Talk to the IT manager and explain that progress in Scrum comes from inspecting an Increment at the Sprint Review.

B.

Tell the Development Team to figure it out themselves.

C.

Tell the Development Team to fit the report into the Sprint Backlog.

D.

Create and deliver the report to the manager herself.

E.

Ask the Product Owner to send the manager the report.

Full Access
Question # 48

Marian is the Product Owner envisioning a project for a new release of her product. She made a projection of a release date based upon a sustained velocity of 17 completed units of work per Sprint. Over the first 3 Sprints, the average velocity was 13 for work that the Development Team estimated as 90% done. The Development Teams, feeling the need to meet the plan, figured that a velocity of 17 was within their reach.

A good way to continue is:

A.

The Development Team makes sure that all of the selected scope per Sprint is as “Done” as possible. The undone work is estimated and added to the Sprint Backlog of the next Sprint, so it doesn’t mess up the Product Backlog.

B.

Add enough people to the Development Team for the deadline to be made.

C.

The opportunity to inspect and adapt is lost. Opaqueness has replaced transparency. Predictability has dropped below zero. The produced software is not usable. As the rules of Scrum have not been respected, it is the Scrum Master’s duty to assess whether repair is possible, or a restart with a more reliable team. If not, the Scrum Master should cancel the project.

D.

The Development Team should remind Marian to find funding for enough Release Sprints in which the remaining work can be done.

Full Access
Question # 49

During a Sprint Retrospective, the Development Team proposes moving the Daily Scrum to only occur on Tuesdays and Thursdays. Which two are the most appropriate responses for the Scrum Master? (Choose two.)

A.

Consider the request and decide on which days the Daily Scrum should occur.

B.

Coach the team on why the Daily Scrum is important as an opportunity to update the plan.

C.

Have the developers vote.

D.

Learn why the Development Team wants this and work with them to improve the outcome of the Daily Scrum.

E.

Acknowledge and support the self-organizing team’s decision.

Full Access
Question # 50

Which two activities will a Product Owner engage in during a Sprint? (Choose two.)

A.

Run the Daily Scrum.

B.

Prioritize the Development Team’s work on the Sprint Backlog.

C.

Update the Sprint burndown chart.

D.

Answer questions from the Development Team about items in the current Sprint.

E.

Work with the stakeholders.

Full Access
Question # 51

Which two things should the Development Team do during the first Sprint? (Choose two.)

A.

Make up a plan for the rest of the project.

B.

Analyze, describe, and document the requirements for the subsequent Sprints.

C.

Develop at least one piece of functionality.

D.

Analyze, design, and describe the complete architecture and infrastructure.

E.

Create an increment of potentially releasable software.

Full Access
Question # 52

When must the Product Owner participate in the Dairy Scrum? (choose the best answer)

A.

When the Product Owner is actively working on items on the Sprint Backlog; however, they participate as a Developer

B.

When the Product Owner needs to represent the stakeholders point of view to the Developers

C.

When there are impediments to discuss

D.

When the Scrum Master asks the Product Owner to attend

Full Access
Question # 53

Who is accountable for clearly expressing Product Backlog items? (Choose the best answer.)

A.

The business analyst who represents the Product Owner.

B.

The Product Owner.

C.

The Scrum Master, or the Scrum Master may have the Developers do it.

D.

The Scrum Master.

Full Access
Question # 54

When a Development Team determines that it will not be able to finish the complete forecast, who has to be

present when reviewing and adjusting the Sprint work selected? (Choose the best answer.)

A.

The Development Team.

B.

The Product Owner and all stakeholders.

C.

The Product Owner and the Development Team.

D.

The Scrum Master, project manager and Development Team.

Full Access
Question # 55

When can a Development Team cancel a Sprint?

A.

It can’t. Only Product Owners can cancel Sprints.

B.

When functional expectations are not well understood.

C.

When the Product Owner is absent too often.

D.

When the selected Product Backlog items for the Sprint become unachievable.

E.

When a technical dependency cannot be resolved.

Full Access
Question # 56

During a Sprint Retrospective, for what is the Product Owner responsible?

A.

Participating as a Scrum Team member.

B.

Summarizing and reporting the discussions to the stakeholders that he/she represents in the Scrum Team.

C.

Capturing requirements for the Product Backlog.

D.

The Product Owner should not take part in Sprint Retrospectives.

Full Access
Question # 57

The Scrum Team should have all the skills needed to:

(choose the best answer)

A.

Turn Product Backlog items into a valuable, useful Increment.

B.

Do all of the development work, except for specialized testing that requires additional

tools and environments.

C.

Complete the project within the date and cost as calculated by the Product Owner.

Full Access
Question # 58

As the Sprint Planning progresses, the Developers realize that the workload may be greater

than their capacity to complete the work. Which two are valid actions?

(choose the best two answers)

A.

Recruit additional Developers before the work can begim

B.

The Developers ensure that the Scrum Team is aware, start the Sprint, and

monitor progress.

C.

The Developers work overtime during this Sprint

D.

Cancel the Sprint

E.

Remove or change selected Product Backlog items.

Full Access
Question # 59

Currently, your Development Teams are organized to address a single layer only (for example, front end, middle tier, back end, and interfaces). What are three things to consider when deciding to move away from such component teams toward feature teams? (Choose three.)

A.

You cannot do Scrum without feature teams.

B.

Productivity may suffer when making this kind of move.

C.

Getting support from the business side first helps.

D.

Feature teams have less communication overhead.

E.

With feature teams, it is easier to calculate the productivity per team.

Full Access
Question # 60

Which two of the following are true about the Scrum Master role? (Choose two.)

A.

At the Sprint Review, the Scrum Master identifies what has been “done” and what has not been “done”.

B.

The Scrum Master teaches the Development Team to keep the Scrum meetings to their time-box.

C.

The Scrum Master helps those outside the team interact with the Scrum Team.

D.

The Scrum Master assigns tasks to Development Team members when they need work.

E.

The Scrum Master is responsible for updating the Sprint Burndown.

Full Access
Question # 61

Who should make sure everyone on the scrum Team does their tasks for the sprint? (choose the best answer)

A.

The Project Manager

B.

The Product Owner

C.

The Scrum Master

D.

The Scrum Team

E.

All of the above

Full Access
Question # 62

What does n mean tor a scrum Team to be cross-function at? (choose the best answer)

A.

The Scrum Team includes skilled individuals who together have all the skins necessary to create value each sprint

B.

Developers on the Scrum Team work closely with business analysis architects developers, and testers who are not on the team

C.

The Scrum Team includes not only developers but also business analysts, architects, and testers

D.

The Scrum Team is a virtual team drawing from separate teams of business analysts, architects, developers, and testers

Full Access
Question # 63

How should a Scrum Team deal with non-functional requirements?

(choose the best answer)

A.

Manage them during the Integration Sprint prior to the Release Sprint.

B.

Assign them to the lead developers on the team.

C.

Ensure every Increment meets them.

D.

Make sure the release department understands these requirements, but it is not the

Scrum Team ' s responsibility.

Full Access
Question # 64

Which Scrum Values are exhibited by not building Product Backlog items that have low business value? (Choose three.)

A.

Economic Value Added.

B.

Respect.

C.

Focus.

D.

Earned Value.

E.

Courage.

Full Access
Question # 65

How do you know that a Scrum Team is cross-functional? (Choose the best answer.)

A.

Scrum Team has all the skills to create an increment by the end of every Sprint.

B.

A few of the Development Team members pair program and do Test Driven Development.

C.

There are no conflicts within the Scrum Team.

D.

Every member of the Scrum Team is able to perform every task.

Full Access
Question # 66

At the end of a Sprint Product Backlog item worked on during the Sprint does not meet the definition of “Done”. What two things should happen with the undone Product Backlog item? (Choose two.)

A.

If the stakeholders agree, the Product Owner can accept it and release it to the users.

B.

Put it on the Product Backlog for the Product Owner to decide what to do with it.

C.

Review the item, add the “Done” part of the estimate to the velocity and create a Story for the remaining work.

D.

Do not include the item in the Increment this Sprint.

Full Access
Question # 67

Which two things are appropriate for a Scrum Master to do if the Development Team doesn’t have the engineering tools and infrastructure to completely finish each selected Product Backlog item? (Choose two.)

A.

Coach the Development Team to improve its skills, tools, and infrastructure over time and adjust the Definition of “Done” accordingly.

B.

Encourage the Product Owner to accept partially “Done” increments until the situation improves.

C.

Refocus the current Sprint on establishing the Development Team’s infrastructure instead of delivering an increment.

D.

Declare the Development Team not ready for Scrum.

E.

Have the Development Team establish a Definition of “Done” that is actually possible to achieve given current circumstances.

Full Access
Question # 68

The Scrum Master observes the Product Owner struggling with ordering the Product Backlog. What is an appropriate action for the Scrum Master to take?

A.

Suggest the Product Owner extend the Sprint, so he can have more time to order the Product Backlog.

B.

Suggest that the Development Team does the ordering to be sure that it is a feasible ordering of work.

C.

Offer the Product Owner help in understanding that the goal of ordering the Product Backlog is to maximize value.

D.

Present the Product Owner with an ordered Product Backlog to use.

E.

Encourage the Product Owner to work with the Development Team to see which items technically are fastest to implement.

Full Access
Question # 69

Which two of the following are appropriate topics for discussion during a Sprint Retrospective? (Choose two.)

A.

Identifying high priority process improvements for the next Sprint.

B.

The order of items in the Product Backlog.

C.

How the team collaborates.

D.

Documenting acceptance criteria for items in the next Sprint.

Full Access
Question # 70

If two Scrum Teams are added to the development of a product that previously had only one Scrum Team, what will be the immediate impact on the productivity of the original Scrum Team?

A.

Its productivity is likely to decrease.

B.

Its productivity is likely to stay the same.

C.

Its productivity is likely to increase.

Full Access
Question # 71

What are three ways Scrum promotes self-organization? (Choose three.)

A.

By not allowing documentation.

B.

By the Development Team deciding what work to do in a Sprint.

C.

By preventing stakeholders from entering the development room.

D.

By removing titles for Development Team members.

E.

By being a lightweight framework.

Full Access
Question # 72

Which of these may a Scrum Team deliver at the end of a Sprint?

(choose the best answer)

A.

A single document, if that is what management asked for.

B.

A valuable, useful Increment that meets the Definition of Done.

C.

Failing unit tests, to identify acceptance tests for the next Sprint.

D.

An Increment of software with minor known bugs in it.

Full Access
Question # 73

What happens if the Development Team cannot complete its work by the end of the Sprint?

A.

The Sprint is extended and future Sprints use this new duration.

B.

The Sprint length holds and the Development Team continuously learns what is actually possible to do within a Sprint of this length.

C.

The Sprint is extended temporarily. Lessons are taken to ensure it doesn’t happen again.

Full Access
Question # 74

(A new Developer is having continuing conflicts with existing members of the Scrum Team, which is impacting the delivery of the Increment. If necessary, who is responsible for removing the Developer from the Scrum Team?

Choose the best answer.)

A.

The Scrum Master is responsible, they remove impediments.

B.

The Product Owner is responsible, they control the return on investment (ROI).

C.

The hiring manager is responsible, they hired the Developer.

D.

The Scrum Team is responsible.

Full Access
Question # 75

True or False: The purpose of a Sprint Is lo produce a valuable useful Inclement.

A.

True

B.

False

Full Access
Question # 76

Several Sprints into a project, the Product Owner tells the Scrum Master that a key stakeholder just started using the product. The stakeholder is unhappy with the quality of the product, and the Product Owner agrees with the stakeholder’s assessment that the quality is low. How should the Scrum Master respond to the Product Owner?

(choose the best two answers)

A.

Encourage the Product Owner to include quality specifications in the Product Backlog and to communicate the stakeholders ' concerns to the Developers.

B.

Bring the concern to the testers to improve how the Product is verified.

C.

Work with the Product Owner to understand their desired resolution and help formulate an approach for raising the concern with the Developers.

D.

Tell the Product Owner they have noted the concern and will raise this issue at the Sprint Retrospective.

E.

Explain to the Product Owner that it is up to the Developers to decide on acceptable quality standards.

Full Access
Question # 77

Which two ways of creating Scrum Teams are consistent with Scrum ' s values?

(choose the best two answers)

A.

Bring all the people together and let them organize into Scrum Teams

B.

Managers personally re-assign current subordinates to new teams.

C.

Existing teams propose how they would like to go about organizing into the new

structure.

D.

Managers collaborate to assign individuals to specific teams.

E.

The Chief Product Owner determines the new team structures and assignments.

Full Access
Question # 78

For which is the Scrum Master responsible?

A.

Managing the performance of the Scrum Team.

B.

The meetings and the objectives that a Scrum Team sets for itself.

C.

The Scrum framework being adopted and used properly.

D.

Keeping track of resource allocation.

Full Access
Question # 79

What is the best suited structure for Development Teams in order to produce integrated Increments?

A.

Each Development Team works only one technical layer of the system (e.g. GUI, database, middle tier, interfaces).

B.

Each Development Team develops functionality from beginning to end throughout all technical layers.

Full Access
Question # 80

What is the typical size for a Scrum Team?

(choose the best answer)

A.

7 plus or minus 3.

B.

At least 7.

C.

9

D.

10 or fewer.

Full Access
Question # 81

For the purpose of transparency, when does Scrum say a new increment of working software must be available?

A.

After the acceptance testing phase.

B.

Before the release Sprint.

C.

Every 3 Sprints.

D.

At the end of every Sprint.

E.

When the Product Owner asks to create one.

Full Access
Question # 82

Who does the work to make sure Product Backlog items conform to the Definition of Done?

(choose the Best answer)

A.

The Quality Assurance Team

B.

The Scrum Team

C.

The Product Owner

D.

The Scrum Master

E.

The Developers

Full Access
Question # 83

The length of a Sprint should be:

A.

Short enough to keep the business risk acceptable to the Product Owner.

B.

Short enough to be able to synchronize the development work with other business events.

C.

No more than one calendar month.

D.

All of these answers are correct.

Full Access
Question # 84

What is the key concern when multiple Development Teams are working from the same Product Backlog?

A.

Minimizing dependencies between teams.

B.

Clear definition of requirements.

C.

Meeting original scope projections.

D.

Making sure there’s enough work for everyone on every team.

E.

Maximizing velocity.

Full Access
Question # 85

(Which outcome is expected as a Scrum Team matures?

Choose the best answer.)

A.

The Sprint Retrospectives will grow to be longer than 4 hours.

B.

They will improve their Definition of Done to include more stringent criteria.

C.

A Scrum Master is no longer needed since they are a mature team now.

D.

There will be no need for a timeboxed Sprint.

E.

Sprint Reviews will no longer be needed.

Full Access
Question # 86

When many Development Teams are working on a single product, what best describes the definition of “Done”? (Choose the best answer.)

A.

Each Development Team defines and uses its own. The differences are discussed and reconciled during a hardening Sprint.

B.

It depends.

C.

Each Development Team uses its own but must make their definition clear to all other teams so the differences are known.

D.

All Development Teams must have a definition of “Done” that makes their combined work potentially releasable.

Full Access
Question # 87

What it the main reason for the Scrum Master to be at the Daily Scrum?

A.

To gather status and progress information to report to management.

B.

To write down any changes to the Sprint Backlog, including adding new items, and tracking progress on the burn-down.

C.

He or she does not have to be there; he or she only has to ensure the Development Team has a Daily Scrum.

D.

To make sure every team member answers the three questions.

Full Access
Question # 88

When is the Sprint Backlog created?

A.

At the beginning of the project.

B.

During the Sprint Planning meeting.

C.

Prior to the Sprint Planning meeting.

D.

During the Sprint.

Full Access
Question # 89

What are two good ways for the Development Team to make non-functional requirements visible? (Choose two.)

A.

Put them on a separate list on the Scrum board, available for all to see.

B.

Add them to the Product Backlog and keep the Product Owner posted on the expected effort.

C.

Run the integration and regression tests before the end of the Sprint, and capture the open work for the Sprint Backlog of the next Sprint.

D.

Add them to the definition of “Done” so the work is taken care of every Sprint.

Full Access