Labour Day - Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70dumps

C_TS422_2022 Questions and Answers

Question # 6

What is the work center hierarchy in capacity planning?

A.

A group of work center in a parallel sequence that is used to split production quantities and work on them in parallel

B.

A group of alternative work centers providing a cumulative available capacity for production

C.

A group of work centers in a production line being used in sequence for production

D.

A group of alternative work centers for production, structured in hierarchy levels by priorities

Full Access
Question # 7

Which standard item categories can you select inside a bill of material (BOM)?

Note: There are 2 correct answers to this question

A.

Work item

B.

Variable-size item

C.

Non-stock item

D.

WBS item

Full Access
Question # 8

where does the system check master data selection settings during the creation of planned orders and production orders?

Note: There are 3 Correct answers to this question.

A.

in the bill of material (BOM)

B.

in the work centers

C.

in the MRP controller

D.

In the routing

E.

in the production version

Full Access
Question # 9

What does a line hierarchy in repetitive manufacturing represent?

A.

A production line with more than one work center

B.

A production line with prioritized work centers

C.

A production line with a parallel sequence in the routing

D.

A production line with an alternative sequence in the routing

Full Access
Question # 10

You are trying to create a production order and NO valid production version can be selected. What could be the reasons?

Note: There are 2 correct answers to this question.

A.

NO bills of material (BOMs) are assigned to the production versions.

B.

All production versions for the material are locked.

C.

The order lot size is NOT within the validity range of a production version.

D.

NO production lines are assigned to the production versions..

Full Access
Question # 11

Your company manufactures materials whose specifications differ for each manufacturing process. Which application do you have to use in SAP S/4HANA to be able to track and use this information in all areas of logistics?

A.

Engineering change management

B.

Quality management

C.

Process order management

D.

Batch management

Full Access
Question # 12

What are the consequences when you assign a planned order to a production line manually, using the planning table in repetitive manufacturing?

A.

The planned order is converted to a production order.

B.

The planned order's component availability is checked.

C.

The planned order generates capacity requirements

D.

The planned order's components are copied to the picking list.

Full Access
Question # 13

When you create a sales order

When can consumption of planned independent requirements take place for planning strategy 40 (Planning with final assembly?

A.

When MRP creates a dependent requirement

B.

When MRP creates a planned order

C.

When you create a sales order

D.

When MRP creates a planned order

Full Access
Question # 14

What does forecasting in the demand planning cycle include?

Note: There are 3 correct answers to this question

A.

One-off events

B.

Past quotation quantities

C.

Past sales order quantities

D.

Market intelligence

E.

Past production planning quantities

Full Access
Question # 15

which of the following automation options can you use for production orders? Note: There are 2 Correct answers to this question?

A.

you can use mass processing to set production orders to technically complete

B.

you can use the production scheduling profile to automatically set orders toI technically complete

C.

You can use trigger points to automatically create rework orders via confirmation.

D.

You can use mass processing to read PP master data for production orders

Full Access
Question # 16

Which of the following processes lead to an entry in the MRP planning file?

Note: There are 3 correct answers to this question.

A.

Changing the storage bin in warehouse management

B.

Changing the procurement type in the product master

C.

Changing the operation times in the production data structure

D.

Changing the stock in inventory management

E.

Changing the purchasing contract in materials management

Full Access
Question # 17

which actions does the system perform by default when you save a confirmation for a finished

product in repetitive manufacturing?

Note: There are 3 Correct answers to this question.

A.

Posting of production costs to the production cost collector

B.

posting of goods receipt for the product

C.

Reduction of associated capacity requirements

D.

Archiving of document for assembly scrap

E.

Material staging for next order in sequence

Full Access
Question # 18

Advanced Planning uses master data and transaction data from SAP S/4HANA In which data objects can you set the Advanced Planning flag?

Note: There are 2 correct answers to this question.

A.

Work Center

B.

Production Version

C.

Material

D.

plant

Full Access
Question # 19

What are the possible results of a production planning run in Advanced Planning (PP/DS)? Note: There are 2 correct answers to this question.

A.

Scheduling agreement schedule line

B.

Purchase Order

C.

Planned Order

D.

Production Order

Full Access
Question # 20

You can you use capacity availability checks for production orders, which settings have to be made for this?

Note: There are 2 Correct answers to this question?

A.

The relevant for finite scheduling indicator must be set.

B.

A checking rule must be assigned to the work centers

C.

An overall profile must be assigned in the checking control

D.

The scope of check must be defined in customizing.

Full Access
Question # 21

In the Capacity Scheduling Table, which settings can you select for the planning strategy?

Note: There are 3 correct answers to this question.

A.

Finiteness level

B.

Fixed pegging

C.

Scheduling control

D.

Planning mode

E.

Direction

Full Access
Question # 22

What do you need to consider when working with material master numbering in SAP S/4HANA?

Note: There are 2 correct answers to this question.

A.

Material numbering is defined cross-client.

B.

Material numbering is defined at client level.

C.

The maximum material number length is 18 for external numbers and 18 for internalnumbers.

D.

The maximum material number length is 40 for external numbers and 18 for internal numbers

Full Access
Question # 23

You have maintained the parameters for simple discontinuation in the material master of a component. Which business process will be affected if the available stock is zero and the discontinuation date is in the past?

A.

Kanban

B.

Material requirements planning

C.

Backflushing

D.

Production order release

Full Access
Question # 24

For a production version to be valid and consistent, what requirements must be fulfilled? Note:There are 3 correct answers to this question.

A.

The deletion flag must NOT be set for the bill of material (BOM) or the routing

B.

The lot size range must be within the lot size range of the assigned routing.

C.

The assigned routing and bill of material (BOM) must be valid in the entirevalidity period.

D.

The assigned routing must be a rate routing.

E.

The assigned routing must NOT have alternative sequences

Full Access