C_TPLM22_67 Questions and Answers

Question # 6

Your customer uses Progress Tracking for network components and maintains dates of events manually. They need to implement scheduling of events. What is the prerequisite for scheduling of events? *

A.

Priority of Events must be set

B.

Event Scenarios must be defined

C.

Scheduling Paramaters for Material Scheduling must be set

D.

Events must be released manually

Full Access
Question # 7

Can you specify in the application which status profile should be used the first time you set a user status where a status profile has not yet been defined in the project profile?

Please choose the correct answer.

Response:

A.

Yes

B.

No

C.

Yes using operative status

D.

Yes using status modes

Full Access
Question # 8

In bottom-up time scheduling scenario the differences between the earliest and latest dates of an activity are referred to as?

Please choose the correct answer.

Response:

A.

Deviations

B.

Time gaps

C.

Floats

D.

High priority

Full Access
Question # 9

In which type of settlement the costs of all the periods up to the one you specify in settlement are settled?

Please choose the correct answer.

Response:

A.

Periodic settlement

B.

Full settlement

C.

Profile settlement

D.

Overview settlement

Full Access
Question # 10

Consider a scenario in easy cost planning where you plan dates and resources in network activities and the system automatically determines the corresponding planned costs as part of network costing.

In this scenario planned costs are determined for which of the following?

There are 3 correct answers to this question.

Response:

A.

Primary costs for general costs activities

B.

Primary costs for material components

C.

Primary costs for service activities

D.

Activity inputs for internally-processed activities

Full Access
Question # 11

How can you distinguish between service activities and external activities while accessing the detailed information for service activities on the external tab page?

There are 2 correct answers to this question.

Response:

A.

Control key

B.

Service exits indicator

C.

Order unit

D.

Cost element

Full Access
Question # 12

How can you update the degree of processing for an activity?

A.

By charging the activity

B.

By confirming the activity

C.

By using results analysis

D.

By scheduling the activity

Full Access
Question # 13

Your customer wants to use milestone billing. Billing elements are implemented. What do you have to do in addition to enable milestone billing?

There are 2 correct answers to this question.

Response:

A.

Activate milestone functions.

B.

Activate indicator sales document date for milestones.

C.

Create a billing plan assigned to a sales order item.

D.

Set up percentage of completion for milestones.

E.

Create a billing plan assigned to a WBS element.

Full Access
Question # 14

Among the various functions provided by progress tracking that simplify data entry and analysis which function allows you to go the master data display for objects that are underlined?

Please choose the correct answer.

Response:

A.

Mass change of scenarios

B.

Copying dates

C.

Subitems

D.

Hotspots

Full Access
Question # 15

Which of the following information regarding cost activity is not relevant for the calculation of planned costs?

Please choose the correct answer.

Response:

A.

Control key

B.

The cost element is defaulted for cost activities based on the network profile

C.

A unit costing that enables detailed planning with multiple cost elements, or an invoicing plan

D.

Cost activities based on external services

Full Access
Question # 16

Which of the following prerequisites need to be met in order to analyze the capacity requirements of an activity?

There are 3 correct answers to this question.

Response:

A.

Scheduling must have been carried

B.

A distribution key must be maintained in the work center

C.

A work center must be maintained in the activity

D.

The capacity requirements indicator must not be set in the network header

Full Access
Question # 17

You have implemented automatic requirements grouping for projects. Once you check the materials turbine and fittings you realize that the requirements are grouped for turbine but not for fittings. What might be the reason?

Please choose the correct answer.

Response:

A.

The grouping indicator of the top WBS element is set to a single MRP Group.

B.

The network is set to no grouping for specific MRP Groups.

C.

The MRP Group for fittings is deactivated for grouping.

D.

The project definition is set to no project stock.

Full Access
Question # 18

Which type of order is created at BOM level to cover requirements when a material shortage occurs in material planning?

Please choose the correct answer.

Response:

A.

Scheduled orders

B.

Procurement orders

C.

Planned orders

D.

Stock orders

Full Access
Question # 19

You have created a network with successive activities. After scheduling the network, the Gantt chart shows that every activity has the same earliest start and earliest finish date as the network header. What could be the reason?

Please choose the correct answer.

Response:

A.

The control key is set to no scheduling.

B.

The scheduling type is set to capacity requirements only.

C.

The normal duration of each activity is missing.

D.

There is a loop in the network.

Full Access
Question # 20

What should you call up to view all the information on an active or completed job that was scheduled in the scheduler in schedule manager?

Please choose the correct answer.

Response:

A.

Task list

B.

Job list

C.

Memory joggers

D.

Monitor

Full Access
Question # 21

What are the various elements that are included in checking rules?

There are 3 correct answers to this question.

Response:

A.

Checking group

B.

Checking rule

C.

Scope of check

D.

Check types

Full Access
Question # 22

In Structure Information System which transactions allow you to analyze and edit the entire hierarchical structure of a project including documents, PS texts, networks, other orders, investment programs, and SD documents?

There are 2 correct answers to this question.

Response:

A.

Network overview

B.

Order overview

C.

Structure overview

D.

Project structure overview

Full Access
Question # 23

Which technique is one of the ways to measure the earned value where each milestone corresponds to a percentage of work completed in an activity or a WBS element in progress analysis?

Please choose the correct answer.

Response:

A.

Trend technique

B.

Project technique

C.

Milestone technique

D.

Period indicator technique

Full Access
Question # 24

Your projects consist of WBS elements, several networks, and subnetworks.What are the advantages of new overall network scheduling (CN24N) instead of the old overall network scheduling (CN24)?

There are 3 correct answers to this question.

Response:

A.

Scheduling of subnetworks and subordinate internal orders

B.

Introduction of a configurable level concept for the targeted selection of

C.

Scheduling that takes available capacities and material availability into

D.

Improve performance through the targeted selection of subnetworks to be

E.

Detailed subnetwork monitor

Full Access