Which activity from the Smart Meter Programme should be delivered using a continual improvement approach?
In delivering the capability, which role is responsible for aligning projects with programme objectives?
The programme is in Tranche 2 and has been progressing according to plan. However, there have been difficulties transitioning to the new ways of working at the end of Tranche 1 and UU has had some customer complaints as a result. Therefore, the SRO asked the programme manager to replan the programme so that all remaining capabilities are transitioned at the end of the programme, instead of at the end of the tranche.
Is this an appropriate application of the 'structure' theme, and why?
It has been agreed with the sponsoring group that a risk review should be held before any of the new customer processes and web-based portal services are used by call centre staff to consider any risks before transition. This risk review needs to be documented appropriately.
Which role should approve the inclusion of this risk review in the relevant programme control document?
Who has the responsibility for monitoring the progress of benefits realization against the plan?
The programme is in the ‘evaluate new information' process at the end of Tranche 2. A new supplier has been identified that may be able to develop the next generation smart meters. This would be an alternative to developing them internally as part of the Research and Development Project and it could be faster and cheaper.
Which role should be responsible for evaluating this new information?
The programme is in the middle of Tranche 2. A new SRO has been appointed. To understand the current status of the programme, the SRO has asked for a health check to be carried out. The programme office lead has recruited an external consultant to carry out the health check.
Which assurance success factor does this demonstrate?
Which one of below options is the delivery mechanism for 'stakeholder engagement'?
Halfway through Tranche 2, North City local government announced a new incentive programme to support green initiatives that help residents reduce their carbon footprint. UU is applying for this funding, claiming that its water smart meters and leak detection systems qualify as eco-friendly mechanisms aligned to the new government scheme. The cost of the application process will be more than paid for if UU is approved as part of the incentive programme.
Is this an appropriate application of the justification' theme, and why?
Which of the following is Not one of MSP defined levels of stakeholder engagement?
The programme has just started. One outcome will be that fewer staff need to work as meter readers. The CEO of UU is keen to make the redundancy process as smooth as possible for the affected staff. As a result, the CEngO is attending a meeting with the meter readers to discuss UU’s plans for the future, as well as the different redundancy and early retirement packages.
Is this an appropriate application of the 'lead with purpose' principle?
UU has partnered with a supplier who has expertise in training and change management. The supplier will provide a virtual change office function, helping staff in the business prepare for the significant transformation ahead and ensuring that the benefits will be realized. However, these change management services are very costly.
Is this an appropriate application of the ‘justification’ theme, and why?
The programme is in the ‘plan progressive delivery' process for the first time and the business case has been confirmed. The programme manager is now attempting to get commitment from the Call Centre Manager that they will provide the staff needed in Tranche 1.
Is this an appropriate application of the ‘plan progressive delivery' process, and why?
For a business transformation programme, which of scenarios will lead to high probability of success?
When it is found that an acceptable Business Case is not emerging, which of the following is NOT one of the normal options?
The Smart Meter Programme is in Tranche 2 and the Customer Processes Project is delivering ahead of schedule. This means that fewer resources are required to complete the project. The Training Project, which was due to start in Tranche 3, has now become a higher priority and needs to be started early. The programme manager has recommended starting the Training Project now although Tranche 2 and Tranche 3 will then overlap.
Is this an appropriate application of the structure' theme, and why?
Three items of information have been recorded in the documents to support the 'decisions' theme. In which document should they be recorded?

During the 'identify the programme’ process, the SRO identified that the utility regulator may be considering a fair pricing policy to protect vulnerable customers. The introduction of this policy would have a significant impact on the benefits expected by UU. The programme manager included this information in the programme brief.
How well does this apply the 'deal with ambiguity’ principle, and why?