A project manager has recently taken over a project and notices that a client team member often halts progress due to a lack of understanding of some project elements. The former project manager gave the
new project manager a complete list of people to communicate with, and this client team member is not on it.
What should the project manager do?
A project manager is asked to negotiate between two team members who frequently have misunderstandings in order to reach an agreement that will advance the project. What should the project manager to?
A project manager has been managing a project for several months when an issue that had not been registered as a risk appeared. This issue may have a big impact on the
project.
What should the project manager do?
A project manager held a meeting and framed the project schedule. A critical stakeholder, who was not consulted at the time of theschedule discussion, complained that the published dates are not agreeable due to a prescheduled task for another assignment.
What should the project manager do first?
After the merger of two large companies, a project manager is assigned to a project. The company hires a consultant to ensure best practices are being used in information security. During an iteration, the consultant requests changes to a software component, claiming that it is not meeting market requirements.
What should the project manager do?
A project manager acquired information from the market that would reduce the business value being delivered by an ongoing project. Based on that information, the project manager believes the project shouldbe stopped.
How should the project manager handle the situation?
In a weekly status meeting with the client, the project manager asks each team member to present how their deliverables are impacting the
customer's final product requirements. Which leadership skill is the project manager applying?
A project team is having difficulties understanding technical details regarding requirements. The information was not initially provided by the customer, butthe information is critical in the current iteration for clarification on how tasks need to be accomplished.
How should the project manager approach this situation?
A project manager who takes over halfway through a project determines that the cost performance index (CPI) is 0.65. A detailed audit identifies that the project cost was analogously estimated, and the auditteam thinks that something was missing in the way the estimates were done.
What should have been done to avoid this problem?
A team has been working on a project for several months, but the completion date is unclear because the scope is changing frequently as new knowledge is gained. Some
deliverables have already been completed, but when new stakeholders join the team, they complain that project outcomes are not meeting business goals.
How can the project manager prevent this situation from happening in the future?
A project manager is assigned midway through a project. The team members are in different locations across the country and they are unable to meet in-person often. During a status review meeting, one of
the stakeholders highlighted that they were unaware of the status for the project deliverables.
What should the project manager do first?
A customer support team has planned short, iterative cycles for working on customer-reported issues. Recently, there was a surge of high-priority issues that disrupted the original plan, and the team's manageris finding it difficult to manage the progress.
Which approach should the project manager suggest using?
A project is nearing completion. The contingency time has been consumed. To ensure that the final deliverables are achieved on time and within budget, the
project manager has asked the team to follow a rigorous process. This is causing some resistance among the team members.
What should the project manager do to address the growing resistance?
A project to implement a new online landing platform has started. After the first sprint, the project sponsor requested a change.
What should the project manager do next?
A project manager is leading a small project with a low budget and a short, tight schedule. Many of the stakeholders are within the
organization and have varying levels of interest.
Which approach should the project manager use with the stakeholders?
Drag the interpersonal skill on the left to the correct scenario on the right.
A project manager is assigned to work on a large global project. The resources for the project are dispersed among different organizations and countries. After the projectkick-off meeting, the project manager learns that many virtual team members are unable to join the regular project update meetings. Their absence will impact the overallproject schedule.
What immediate corrective action should the project manager take?
Aretail chain is evaluating a project to replace payment systems across all its stores in multiple locations. The project does not pass the financial threshold but is alsoexpected to increase marketshare, improve customer services, and retain more customers. The project is planned as a phased implementation, building on learningfromthe retrospectives during each phase.
How should the business increase the value of the project?
A project manager has been assigned to an education project with the objective of training a workforce in application development. One ofthe deliverables is to provideinternships to the best students in the customer's active projects. However, the customer does not have enough projects in progress right now. The project manager decidesto create several internal projects in order to ensure the internships.
Which three actions should the project manager take to fulfill this scenario without adding costs for the customer? (Choose 3)
An experienced project manager is working on a complex hybrid project that has several dependencies with other projects. How should the project manager reduce the risk related to those external
dependencies?
A company has been following a predictive approach and always waits for the preceding phase to be completed before evaluating the quality of their products. A new project
manager with experience in hybrid approaches has been assigned to help increase the efficiency of the company's quality management process.
What should the new project manager do to address the process improvements?
How can agile measurements improve upon predictive measurements in cases where the final 10% of a project takes longer than planned?
A project is being planned to deliver a proof of concept to evaluate technology compatibilities. The business and project stakeholders are having difficulty agreeing on what should be included in the final
product.
What should the project manager do?
A project manager has been hired to lead a governance consulting project that is in the initial phase. The project manager has been assigned to evaluate the supplier search activity. There are many interested
candidates, including former suppliers and suppliers recommended by the sponsor.
What should the project manager do in this situation?
project is currently in the execution phase. Because of the complexity of the project and the large number of regulatory requirements involved,theproject manager decides to hold a management review with senior executives to ensure the successful implementation of project deliverables.
What should the project manager review during the management review to ensure the meeting is effective?
A project manager assigned team members to work in pairs on a large amount of technical reports. At times, the project manager noticed that important information was not shared properly among the team.
This has caused delivery delays and, ultimately, the failure to complete the project.
What is the root cause of this issue?
A project manager is executing a commercial building project. The project manager discovers that the required building permits have not been obtained. Obtaining the permits will delay the project by 1 month and will cost the project US$35,000. The fine associated with continuing to build without the permits is US$1,000 per day.
What should the project manager do first?
A project manager in an automotive company is scheduling activities for a complex project Some of the project requirements are fixed and some are flexible Match the items on the left with the methodology on the right that the project manager is using.
A supplier, who was tasked with providing an important component for a project, is unable to deliver the materials due to a large-scale labor problem. What document should the project manager use toupdatethe details and communicate to relevant stakeholders?
A project team delivered a critical deliverable to the customer. The customer complained that the maintenance manual was not included.
What should the project manager do next?
A project interfaces with other projects that are in the same portfolio but are being developed in international locations. One ofthe international projects hassuggested a tactical change that needs to be implemented in this project.
What should the project manager do next?
During a project's closing phase, the project manager identified that the client did not use one particular service. The client then asks the project manager to informally extend the service beyond the contract
end date. The contract is clear about the expiration of the service.
How should the project manager address this situation in order to close the project?
As part of a company’s planning effort for team capacity building, the project manager was asked to provide management with a list ofrequired trainings for the project team. What should the project manager do?
A project manager is meeting with the project sponsor regarding a new project. The project manager tells the sponsor that, as part of the communications management plan, a weekly email will be sent with thestatus of the project, so the sponsor can be informed of the progress. The sponsor indicates that the email is not necessary because they will ask for a status update whenever it is needed.
What should the project manager do next?
A project manager implementing a hybrid project is dealing with multiple stakeholders in a rapidly changing business environment. How should the project manager ensure that the needs of stakeholders are consistently met?
A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous
project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely
finished in 8 months.
What should the new project manager do?
A verbal announcement is made that the new team member joining the Scrum team has limited mobility. The scrummaster is aware that some teammembers are unsure how the dynamics of the team will change.
What should the scrum master do?
A project manager is leading a hybrid project. The only available resources that have experience with agile are not at the project manager's location. The project has a strict schedule
and budget, and the project manager is concerned about their ability to deliver it.
What should the project manager do?
A new development project is about to start, and the project manager knows that a high-profile customer makes very specific and frequent requests in all sprints. This projectwill demand contract coordination with third parties, and the project manager must find a better way to manage customer and partner expectations.
What strategy should the project manager use?
A project presently in the testing stage is nearing the closing phase, which will transition the completed project to the company’s operations support team. However, many new members have just been added
to the operations support team who are not familiar with the project and the project's acceptance is now at risk.
What should the project manager do to mitigate this transition risk?
An agile project has a documented list of requirements prioritized in high, medium, and low categories. The project team has expressed that it is difficult toknow what to work on next as so many items are listed as high priority.
What should the project manager recommend?
A project manager is managing a project with team members who are working all over the globe. The project manager notices that each team member'sdeliverables do not meet the requirements.
What should the project manager do first?
A project manager is leading a project in an organization that has a functional structure. The project manager has been informed by the team that the tasks related to the
purchase of services are taking too long, as the purchasing department has other priorities.
What should the project manager do?
Team members of a new scrum team are skilled and excited about the project, despite never having worked together before. The project leader requested an offsite team building activity to talk about the project and get familiar with each other, but the activity was not approved by the sponsor who is trying to save money. The project leader believes it is important to hold a team building activity to bring the team together.
What should the project leader do?
vendor informed the project manager that a critical resource will be on a long leave of absence. The project team reviewed the pending vendor deliverables and identified
an alternative solution, but the solution will incur an additional cost. The project is currently on schedule and slightly under budget.
What should the project manager do next?
A new building project is in the middle of its life cycle. The municipality informs the project manager that due to new regulations, the parking lot around theproject has to accommodate twice the number of cars than was initially planned.
What should the project manager do next?
An agile project team is creating an enterprise workflow system for a company. One of the project team members, who is the system design architect, keeps receiving telephone calls from the users who are
asking questions about the system. The calls are impacting the architect's daily work schedule.
What should the project manager do?
A project scope was developed with numerous assumptions. During the execution phase, the assumptions changed, which has jeopardized the planned business value of the project.
What should the project manager do next?
A system migration project is in its closing stage. The project manager is being pressured to close the project. The project manager communicated to allstakeholders; however, the last department to migrate indicated that they have not received the notification.
What should the project manager do?
A project manager who is new to an organization observes that an approaching deadline is likely to be missed because there have been some delays on theproject due to a lack of resources. What should the project manager do next?
A project is behind schedule because of a delayed equipment installation. This is affecting many other activities. The manager responsible for the equipment delivery notified
the project manager that there is a capacity issue for the team doing the installation.
What should the project manager have done to prevent this situation from happening?
Some of the team members who are working on a new software tool are in a public space, arguing over a new feature being coded instead of completingthe coding. How should the project manager handle this situation and get the team to complete the task?
A member of a testing team in an agile project works well with the project team. However, in the previous two iterations, this team member's performance was poor, and the
team had difficulty meeting the iteration goals.
How should the project manager handle this situation?
A project manager is working on a major construction project. Part of the agreed-upon plan was to use a cloud-based system with a server that runs on high-speed internet
service since most of the team members work virtually. The company needs to reduce operating costs as much as possible and management insists that the project will now
use a system running on a conventional dial-up service.
What should the project manager do next?
A hybrid project has just deployed, and the project manager is planning project closure with lessons learned workshops. A key stakeholder informs the project manager that
having the Scrum team in the workshops is a waste of time because the project was delivered successfully.
What should the project manager do?
During the daily standup meeting that is assessing progress against the current sprint, ateam member reports some delayscomponent managed by an external vendor. How should the project manager address the team member's concern?
Due to organizational changes, several key stakeholders are replaced by new ones in the middle of a project. As a result, numerous new requirements are raised.
What should the project manager do to ensure success of the project?
A project manager is working as a servant leader for a pilot project to adopt agile practices. After three sprints, the teamdemos the product to the mainstakeholders but receives negative feedback about the product's features. The team feels that all the features met the acceptance criteria defined by the
product owner and does not understand what went wrong.
How should the project manager mitigate the product rejection?
A project manager received the project charter for a new product. The project is expected to have two main deliveries: the hardware part that has detailed specifications already defined,
including a sample machine, and the user interface software that has only a basic specification and a requirement for a user experience design approach.
Which project management approach should the project manager use?
A team realizes that there is no access to data that the project depends on to complete the current iteration. This dependency was known; however, theteam is unsure of the available options to remove this obstacle.
What should the project manager do next?
A project sponsor is promoting the use of a new technology that has not yet been approved. The technology guarantees cost savings and a delivery ahead of schedule. However, the operational support atproject completion is uncertain as the service organization expressed an inability to provide support without approval of the new technology.
What should the project manager do to resolve the conflict?
A project manager is using an agile approach. During the sprint planning meeting, the product owner flagged a backlog item as high business value and easy to implement.
However, the other team members identified a high dependency between this item and another item that is flagged as low business value and high complexity.
What should the project manager do to support the backlog prioritization?
One of the team members is always late to the daily standup meeting. What should the project manager do?
An external project manager is managing the construction of new corporate offices for a large company. The project management plan states that it is
necessary to contract a highly trained external resource to revise and validate an important project component. The client has rejected hiring the external
resource because of the high cost, even though it is within the project budget.
What should the project manager do to resolve this issue?
A project team is in the planning stage and has prepared a list of activities and completed sequencing the activities. During a review, theteam noted that there is a dependency missing between:
* Test the product
* Release to customer
According to the quality management plan, the product must be tested before being released.
How should the project manager enter this dependency?
A project that has to be delivered by the targeted date has been delayed due to an unforeseen risk occurrence. How should the project manager compress the project to ensure the completion date is not
affected?
An agile project is running its second iteration out of six. A marketing director, who is a key stakeholder, contacts the project lead for a highlevel report of the project.
What should the project lead do?
According to this burnup chart for the last 7-day sprint, what should the project lead address with the product owner and team?
During the execution phase of a project, one of the customer's stakeholders keeps requesting changes to the scope every week. Which three actions should the project manager take to resolve this issue?
(Choose three)
During the final stage of the launch for a new design, team members are having a conflict about some features of the design. What should the project manager do?
A project manager just completed the planning phase when a new stakeholder was assigned to the project. The deliverables were discussed with the customer, but the new
stakeholder is still concerned about the benefits of two of the deliverables.
What should the project manager do next to address this stakeholder’s concerns?
A compliance strategy was created during the planning phase of a project. During execution, the project manager left the organization and another project manager was assigned to the team.
What should the project manager do first to ensure the project is compliant?
A project manager has noticed that a critical team member is consistently arguing with a client. This has started to have a negative effect on the meetings.
How should the project manager address this?
A project manager is struggling to figure out the performance of the project teams in an agile environment. For the same scope of work, team A has calculated 100 story
points and team B has calculated 125 story points.
Which team is performing better?
A project manager was recently assigned to a banking IT project. The project team has been developing products using a predictive approach for more than 10 years, butmanagement wants the team to change to an agile approach. The project manager met with the team to introduce the agile approach.Most of the team memberscomplained about changing approaches because the performance of this team has always been above average among the IT teams in the bank.
Which two actions should the project manager take? (Choose 2)
A project manager for an IT company starts a project with members distributed across five different countries and four different time zones. In the first meetings with the sponsor and some stakeholders, theproject manager notices that people do not join the meetings on time, have internet connection issues, or experience language barriers during some conversations.
What should the project manager do to improve communication among the team?
A highly skilled team resource received a job offer and is leaving the project soon. What should the project manager do to maintain project performancewhile a new team member is being onboarded?
A project manager has been managing a highly complex project. The project manager has ensured that all of the required tasks have been completed.
During a recent external audit, the project manager was informed of a heavy penalty being levied on the project for the latest module that was implemented.
What should the project manager have done to ensure that there were no liabilities arising from the recent implementation?
A project manager has recently been asked to take over an existing project. The project manager would like to determine how the project has been progressing by tracking features that are in progress,
completed, or scheduled to be worked on.
Which of the following can help the project manager assess the state of the project?
A supplier informs the project manager that producing the quantity of a key component for the project will require an additional month. Theproject manager has to meet animportant milestone in a week.
What should the project manager do next?
During project execution, the client requires several changes that will impact the project's duration. The project manager needs to apply fast-tracking techniques to accelerate the schedule, but the team is
concerned about working overtime.
What should the project manager do to motivate the team?
A project team consists of eight resources working on a complex project. The chief technical designer prefers to work alone and seldom talks in meetings, but produces good designs. The technical lead is always energetic, has lots of opinions about the project, and constantly clarifies their thoughts in discussions.
What should the project manager do to improve overall team performance?
A project manager is in the middle of a project when one of the key project team members needs to take an unexpected and prolonged leave of absence. The project isahead of schedule and running under budget.
Which two actions should the project manager take initially to resolve this problem? (Choose two)
A project team has finished its first iteration out of six. The iteration's delivery performance (velocity) was 50%. During the iteration retrospective, the team realizes that the
complexity of the work was underestimated.
What should the project manager do?
A project delivers every 2 weeks. The customer raises a complaint because they do not perceive business value in the products delivered even though deliveries have been completed in a timely manner.
Which activity should the project manager undertake?
During the execution of a project within an operations function, the project manager encounters scope changes and a delay in the delivery ofcritical tasks. How should the project manager address this situation?
A project manager is assigned to a project with a long time line and complex scope. The client requires a high-level, long-termplan as well as something thatwill work immediately, adding features to the product as the project progresses.
How should the project manager plan and deliver this project?
At a project status meeting, different activities were agreed upon for the following weeks. At the end of the first week, the project team
realizes that the activities were executed in the wrong way because each team member had a different understanding. These
misunderstandings have caused a delay in the project.
Which of the following actions should the project manager take to avoid this situation in the future?
During an agile team retrospective, a project team member mentions that the code quality is degrading, which might result in future rework that could becomeunmanageable with time. What should the project manager do?
By the end of the first sprint, a project lead notices that one of the team members is not performing very well. Which form of communication should the
project lead use to handle the situation?
During the early phase of a project, the requirements documentation was not approved. It was identified that the leader of a user partywas not included in any of therequirements collection communications.
Which of the documents was likely missed or outdated?
A project manager is transitioning from a predictive life cycle project to a new agile project. How should the project manager manage and control the scope for the new project?
A project manager realizes that the team members are new to the hybrid approach and do not value standup meetings. Team members often arrive late, digress into solutioning, or skip the meetings altogether.
How should the project manager improve this situation with the project team?
In an iteration-based marketing project, a product is scheduled to be launched at the sixth iteration. In the third iteration demo, the marketing team expressed that they need
five iterations to launch the product and they have not started yet.
What should the project team have done to avoid this issue?
An agile project manager notices that one of the team members is developing extensive knowledge in a specific matter. Other team members are likely to require this
knowledge in the future.
What should the agile project manager do?
In a complex project with several subcontractors, one subcontractor reports a likely delay in the schedule. This could affect the other subcontractors and impact their ability to deliver on time.
What should the project manager do first?
A project manager is assigned to a major construction project. The project is critical to the city's population, and especially to the local government official who committed to
delivering the project on time as an election promise. A new project sponsor has been assigned and wants to include aspects that the previous project sponsor did not
support,
What should the project manager do next?
An agile project team received an assignment to develop an industrial system that interfaces with robots. The project team does not have any previous experience performing this type of work. Team members are interested in acquiring such expertise but it may result in a project delay.
How should this situation be handled?
A network transformation project to increase efficiency and return on investment (ROI) is in the implementation stage. A conflict between the head of the network and the
transformation manager arises.
What should the project manager do to manage this?
During the implementation of a project, the project team discovered a new opportunity. After an internal review, the project team agreed that the opportunity is outside of theproject scope. The project manager decided to update the risk register and escalate the opportunity to a higher level.
What should the project manager do next with this opportunity?
An organization is embarking on the deployment of a new digital solution that will revolutionize purchasing services. The project manager has created all the necessary plans and activities to ensure a successful integration and solution launch. There is a risk of a partner's system being unavailable which could impact the project negatively.
What key activity is needed to ensure the project's success?