A risk manager notices that a risk owner is facing challenges implementing their response strategy and the costs are significantly exceeding expectations. What is the first thing the risk manager should do?
A project team identifies that there is a probability of missing a key milestone in a project. The team wants to move forward with the risk response planning.
What should the risk manager complete first?
The risk manager for an IT project developing a software application has a major stakeholder concerned that the project will not conclude within the available funding. The risk manager found delays in the iterations and increments in the project ' s budget, potentially increasing the duration by two weeks.
What tools should the risk manager use to properly decide the risk of not finishing the project within the budget?
The project risk manager on a large firm fixed priced (FFP) contract has an up-to-date risk register with accurate and detailed information. What should the project risk manager do next?
A risk manager recently had to take an unexpected leave of absence. An interim risk manager has been tasked with completing risk planning for a new project. The interim risk manager has been provided with a strength, weaknesses, opportunities, and threats (SWOT) analysis that was completed during a project kickoff meeting several weeks ago.
What should the interim risk manager do to derive actionable risk responses from the SWOT analysis?
During the early planning stages of an AI-based software development project, the project team begins outlining the risk management activities. The risk manager notices that key stakeholders, such as data scientists, product owners, and external data vendors, lack a shared understanding of risk management principles.
What should the risk manager do to educate stakeholders?
An external vendor needs to be contracted to provide additional capacity and expertise to a project team to reduce the probability of delays in a project. The contracts department is raising a concern about confidentiality risks not addressed in the proposed contract and missing from the risk register.
What should the risk manager do next?
A project manager is working on a complex construction project. During the risk identification process, hundreds of risks were identified. The team seems to be confused regarding on which risks to focus. The project manager advises the team to go ahead and start assessing the likelihood and impact of each risk.
What process is this part of?
An organization with a portfolio of unique business functions kicks-off a performance improvement project across the entire organization. There are a large number of stakeholders the project team will need to consider during risk identification.
What three actions should the risk manager ensure the project team performs during risk identification? (Choose 3)
A budget change request was initiated by a functional manager in an organization due to a shortage in the functional manager ' s department budget. The functional manager asks the CEO to approve utilization of a contingency budget reserved for one of the projects in its closing phase.
What should the risk manager of the related project have done to prevent this situation from happening?
During a complex infrastructure project, the team successfully mitigated a risk related to equipment failure. However, the mitigation strategy resulted in a secondary issue due to the use of alternative machinery.
What should the risk manager do?
In a large mobile network deployment project, there is delay risk due to insufficient staffing. The risk manager is considering executing a response plan, which involves allowing staff members to work overtime. However, this action may lead to excessive additional cost.
What should the risk manager do?
A project team is concerned about a risk which, if occurs, might add additional complexity to their work. The team will need help from an external vendor, but the contracting process is long.
What should the risk manager do in this case?
During the execution phase of a construction project, a risk response strategy is implemented to mitigate the risk of supply chain disruptions. However, this leads to a secondary risk of increased logistics costs.
What should the risk manager do to address the new risk of increased logistics costs?
As per the risk analysis process carried out for a project, two risks are registered. The probability risk A will occur is 40% and its monetary impact to the project is US$100,000. The probability risk B will occur is 60% and its monetary impact to the project is US$20,000.
What is the total contingency budget that should be created?
After the initial assessment of a new project, a project manager found that in order to complete the expected results, detailed and exhaustive planning will be required to ensure the product ' s characteristics and quality. What should the risk manager propose to the project manager what to do?
An agriculture government agency faces different challenges with farmers and landlords In implementing its ambitious growth strategy. The agency decided to establish an enterprise risk management unit to identify risks, analyze risks, and provide a handbook showing how to handle the surrounding uncertainty.
What should the risk management expert recommend the agency do first to identify risks and develop the handbook?
The risk manager for a large-scale software development project with a tight deadline and multiple stakeholders highlights concerns about potential delays, communication gaps, and vendor reliability. During the early stages of the project, the project sponsor requests that the risk manager identify and address any potential risks that could disrupt project delivery.
What should the risk manager do?
A risk manager of a major project facilitates a meeting to develop the risk management plan. What two factors does the risk manager need to consider to ensure an effective risk management plan is developed? (Choose two.)
A risk manager completed risk response planning for a project that is currently in the execution phase. During a periodic review of the risk register, the project manager recognizes that some key secondary risks have not been considered.
Who should the project manager hold accountable for missing the risks?
A new risk manager is assigned to an ongoing project, what should the new risk manager do first to assess the project environment?
The project risk manager is in the process of identifying risks. The project sponsor has communicated that there is an influential stakeholder who has a senior management position. The other stakeholders do not feel comfortable speaking in front of this stakeholder.
What should the project risk manager do next to identify risks?
A project manager of an IT company is assigned to a project whose schedule may be delayed due to a lack of resources to conclude the backlog activities. The project manager decides to hire additional developers to reduce the project ' s technical debt and meet the project deadline.
What should the risk manager advise the project manager to do to address this situation?
In the middle of a construction project, the primary construction materials provider canceled the contract and moved to a competitor offering a higher price. The risk manager considers
this a low-impact issue because many construction materials providers can fulfill the project demands. However, after informing the stakeholders of this issue, the major investor is about
to drop their intention to continue executing the project. The risk manager does not understand their decision.
What should the risk manager do next to understand the major stakeholder ' s decision regarding the project?
When processing freight invoices for a project, the project manager notices the shipping costs exceeded the budget due to increased fuel costs. The risk manager included this risk in the project ' s contingency allowance. When reviewing the project budget execution reports, the project manager notices unused budget remaining in other closed tasks of the project that could cover the additional shipping costs.
What should the project manager do?
A project team has just initiated a large project to move an organization ' s headquarters to another location. The risk manager has scheduled a risk identification session but notices that the project charter, work breakdown structure (WBS). and scope statement are not available.
What should the risk manager consider?
Stakeholder holiday schedules and availability of raw materials were two risks initially identified in a manufacturing project. The risk manager now notices that both risks are not quite as originally described and might require a plan change.
What should the risk manager do next?
An organization faces immense competition in the market and decides to accelerate a key project. What is the first action for the project risk manager to take?
A project manager for a predictive project just received a scope change request where additional development is required. What should the risk manager do to support the project manager with this scope change request?
A project is underway to implement a new customer support software. During testing, the risk manager discovers that the integration with the existing customer relationship management system is more complex than initially planned, potentially delaying the project. The risk manager needs to update project documents to reflect this new information.
Which steps should the risk manager consider when updating relevant project documents?
In a large enablement project with strict time lines, risks need to be closely monitored. The risk manager publishes reports comparing planned enablement sessions with actual enablement sessions, which help identify potential risks to be addressed.
Which technique is the risk manager using?
An organization performs an annual strategies and initiatives workshop during which a strengths, weaknesses, opportunities, and threats (SWOT) analysis is being conducted. As part of this process the functional managers identify the opportunities and threats.
What should the risk manager do next?
A new project is about to start, and the risk manager wants to review some documents that could be relevant for risk identification. Which document will help the risk manager in this process?
A risk manager is integrated into a team overseeing a crucial software development project. During the information gathering phase, the risk manager notices significant weaknesses in the maturity of the risk management process. The team needs to establish a more structured approach to managing risks, including the documentation of strategies, ownership structures, and details about the organization ' s project risk baseline.
What should the risk manager do?
Multiple new risks have come up on a project that were not included on the risk register. The project manager met with the team to explain that risk management is critical for the success of the project, and risk identification is key.
What should the project manager do next?
During the design phase the project team is exploring various architecture options. After reviewing the results of design pilot, two conflicting infrastructure pieces were identified.
What action should the project manager take?
Three months into a program, multiple workstreams are showing issues. At this point, the program manager requires that a risk impact assessment be conducted.
What will help calculate the impact?
An IT project is 40% complete. During the initial analysis, risks A and B were identified for the project. Risk A has a probability of 0.6 and an impact of US$50.000. Risk B has a probability of 0.7 and an impact of USS60.000. After implementing the planned risk response for risk B. the probability of risk B has been reduced is 0.3.
What is the current project risk exposure?
Which statement describes the risk portrayed on the risk matrix heat map below?
During a risk identification session, the risk manager notices that subject matter experts (SMEs) are reluctant to participate because some risks could expose the poor maturity of processes in other business units. Which risk analysis technique should the risk manager use?
The project director and project manager have met with the board and determined that the project has depleted the entire contingency reserve and has started eroding the profit margin.
The project manager would like the risk manager to take full advantage of opportunities.
Which response should the risk manager take?
A risk manager for a cross-functional project is initiating the risk identification process. The risk manager conducted some meetings for stakeholders to express their concerns, but some stakeholders are complaining that their opinions were not considered.
How should the risk manager address these concerns?
A critical piece of equipment broke during a project execution phase. The risk manager notices this risk in the risk register, and the response is to rent equipment until the critical piece is repaired.
What type of risk response is this?
A project is evaluating a new software to streamline the current purchase order process. The current process is labor-intensive and involves printing, ink signatures, scanning, and emailing. Several team members gathered cycle time data to gauge the current process and evaluate the new process.
What should the risk manager do next with the data set?
A web page for weather reports will be online next quarter. During the retrospective, discrepancies were discovered with the customer’s requests and the user experience (UX). There is a disagreement between the product owner and the development team about what may have gone wrong and led to this.
What should the Extreme Programming (XP) coach do to keep the project on track and deliver on time?
A risk management professional is in the process of categorizing risks when a subject matter expert (SME) suggests categorizing the risks by their impact to the project objectives. Why should the risk management professional use this approach?
A risk manager has been assigned to a project in a company that is undergoing a significant cultural and organizational change. The risk manager will start planning risk management. activities with stakeholders but is unsure with whom to engage.
What should the risk manager do?
A new risk manager has been assigned to a delayed strategic project. The risk manager presented a new plan to get the project back on track using lessons learned and applying risk response strategies. Senior management wants to remove contingency reserves because they want to finish the project earlier.
What should the risk manager do in this scenario?
A project manager has just been assigned to a new project. The project manager has been tasked by the project sponsor to ensure the project risks are closely managed. The project manager starts with developing the risk management plan.
What is the expected outcome of developing the risk management plan?
A home solar panel project has many internal and external stakeholders including households, businesses, community groups, electric utility companies, local government officials, landlords, and investors. What should the project manager do when engaging stakeholders?
A list of risks was identified that could occur during the design phase. Now, the team finished the design phase and those risks did not materialize.
What should the project manager do next?
A key hardware component failed during a large software implementation project, with significant organizational impact. The risk owner was on vacation and no one responded to this incident, thereby causing project delays.
What should have been done to prevent this situation?
There is a debate within the organization on whether projects need to be agile or waterfall. Some agile terms and principles are understood differently by the key stakeholders, and this delays the decision-making process.
A company manages confidential customer information, and a data breach exposing sensitive information was discovered. What should the risk manager do?
During the weekly project meeting a risk manager identified new risks in the last sprint, which might impact the project cost by implementing mitigation plans. The sponsor and some project team members do not agree that those risks can impact the project cost.
What should the risk manager do to resolve the sponsor and project team members ' concerns about risk identification?
A project team has failed to complete an important project milestone on time. The team was counting on an external provider to deliver key equipment on a specific date but the provider was delayed.
What should the risk manager have done to prevent missing the milestone?
The project manager leading a company ' s digital signature initiative for engineering drawings has identified threats and opportunities using a strengths, weaknesses, opportunities, and threats (SWOT) analysis.
What are two potential threats or opportunities under the SWOT analysis? (Choose two.)
A project has a S0S4 chance of a US$100 000 profit and a 40% chance of a US$100,000 loss. What is the expected monetary value for this project?
A project with impending risks has 12 deliverables as subprojects, which will be executed in three different locations involving multiple stakeholders. What should the risk manager do to organize the prevailing risks?
A project team is leading a software development project. During the project kickoff meeting, the risk manager discovers that a vendor has not finalized the timeline for delivering an essential component. This creates uncertainty in the overall project schedule.
What should the risk manager do to address the risk?
In a complex project, individual risks have been identified with the stakeholders. The project sponsor asks the risk manager about the likelihood of project success. Which risk analysis tool(s) should the risk manager use as a basis for their response?
A risk manager reviews a Monte Carlo schedule risk analysis model before sharing the results with the project manager. The risk manager notices that activity correlations were not included in the model.
What is an effect of adding the correlation to the model?
An experienced and the only developer on a software implementation project will be on leave for several weeks. The risk of this critical resource ' s availability was added to the risk register. Contingencies were made for a support developer to job shadow this resource, depending on how things go prior to their leave. The project team was pleased with the backup plan and the new resource was able to shadow for a few weeks.
What should the risk manager do next?
An organization is executing two projects — Project A and Project B — simultaneously. A previously identified risk will impact the schedule for Project A. While executing the mitigation plan, a number of residual risks are identified that could provide cost savings for Project B.
Which action should the risk manager for Project A take?
During a project ' s initial planning session, the project team identifies a possible risk. The team is under the impression that a critical vendor might delay delivery. This could impact both the project schedule and budget. The team shares insights on the risk ' s likelihood and impact with the risk manager.
What should the risk manager do?
A new risk manager has been assigned to a project experiencing delays, quality issues, low performance, and client complaints. The work is being completed with the
client ' s vendor, which apparently has been causing all of the issues.
What should the risk manager do first?
After starting a new pipeline project, a risk manager schedules an initial meeting with the project sponsor. For the meeting, the project sponsor requests a presentation of the risks that have the most impact on achieving the project objectives.
What should the risk manager do to facilitate the sponsor ' s ask?
Members of a project team are not taking their risk management responsibilities seriously. They do not consider risk management as primary to the project’s success and do not believe that the benefits are significant.
What should the risk manager do?
As part of standard procedure to monitor and control a project, a risk manager should constantly update the risk register. The risk register updates should include information on risk reassessment, risk audits, and periodic risk reviews.
What additional information should the risk manager prioritize in the risk register updates?
A project team is overseeing the construction of a new office building. The project is complex, involving multiple contractors, regulatory requirements, and a tight schedule. During a team meeting, the risk manager realizes that a formal risk identification exercise has not yet been conducted.
Given the project ' s complexity, what should the risk manager do?
A risk manager administered a pre-workshop risk survey in preparation for the upcoming workshop. The workshop invitees participated in the survey and submitted many risks encompassing all project phases and risk areas. The risk manager sorts risks by similarities and categories for the workshop.
What should the risk manager do next to visually organize the risks?
The project manager performed ' a variance analysis on the project during the execution phase. The variances were shown as increasing
What does this result imply?
A highly complex project is about to start Considering that many changes and new information will arise as the work moves forward, key stakeholders are anxious about not addressing risks on time
What should the risk manager do in this situation?
A project is at the final development stage. The test lead informs the risk manager that a key feature may not be testable due to changes in the environment
What should the risk manager do?
A risk manager for a new product development project has worked diligently with stakeholders and the project team to identify and document risks. These project risks vary widely in probability and impact.
Which three actions should the risk manager take to inform the identification of resource requirements for individual risk responses? (Choose 3).
A project team identified some risks in a project. Team members became interested in predicting the outcomes of their potential choices following their probability of occurrence.
Which technique should the risk manager use?
A project manager for a large product development project assigned a risk manager to perform the risk management. The project sponsor questions why this project requires a risk manager as it is similar to a previous project with a developed risk strategy.
How should the risk manager explain the need for a risk strategy specific to this project?
it typically takes 5 hours to perform a complete home inspection. If there are unforeseen risk factors, it can take up to 7 hours to finish the inspection. The earliest the project team has ever finished an inspection is in 3 hours.
Using the project evaluation and review technique (PERT) to estimate duration how many hours should the project manager plan to schedule the task taking into account all the positive and negative risk factors?
A stakeholder is asking a project team to hire an external vendor with more expertise and capacity to accelerate a delivery plan. The team has some concerns about this request. What should the risk manager do first?
Several key stakeholders approach the project manager with concerns. The stakeholders have received feedback from local businesses that have reported a reduction in customers because of construction activities at the worksite, and they plan to submit a claim to the municipality to fine the project manager ' s company.
How should the project manager address this concern?