Pre-Summer Sale - Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70dumps

PMI-ACP Questions and Answers

Question # 6

During a backlog refinement meeting, the new developer on the team asks the product owner to discuss a new performance threshold requirement and how it impacts the stories in the backlog.

What should the team do?

A.

Add this threshold requirement request as acceptance criteria in all impacted stories

B.

Create a spike story to analyze the impact of the threshold requirement on current stories

C.

Conduct design planning session to review the performance threshold requirement

D.

Identify the tasks for the new performance threshold requirement

Full Access
Question # 7

How can an agile team working on a new product ensure alignment with external stakeholders?

A.

Ask the product owner to provide a detailed product specification document

B.

Conduct story-mapping exercises to clarify deliverables and release priorities

C.

Hold a kick-off meeting to assign roles and responsibilities

D.

Work with the scrum master and stakeholders to ensure agile principles are followed

Full Access
Question # 8

A large, corporate organization is forced to hire new team members in a geographically remote location from the current team. The manager of the department is concerned about the team not being colocated.

What behavior would indicate the team is not working well together?

A.

Team members are sending more emails to the team.

B.

The duration of feedback cycles has increased.

C.

The velocity has increased by having the new team work on items.

D.

New team members requested to move meetings due to time differences.

Full Access
Question # 9

During planning, a project team and sponsor created a visual representation of the high-level specifications of the features and user stories to be implemented in a product. Consensus was achieved on this high-level depiction of the product characteristics, but the sponsor is having difficulty understanding what to develop and when.

How should the project manager explain this to the customer and save time in the meeting?

A.

Team performance and velocity can be determined only after the project has started

B.

Point out the Walking Skeleton and highlight the basic features that provide value.

C.

Create a kanban board for visualizing the work in process (WIP) and future development.

D.

High-level release planning is part of iteration 0 and works as a proof of concept

Full Access
Question # 10

A project manager is leading a large agile project with multiple deliverables at each phase of completion. The project team has informed the project manager that the deliverables are completed per the team agreement.

Which agile practice should the project manager advise their team use to ensure deliverables are completed and ready for release?

A.

Requirements backlog and ready for release

B.

Acceptance criteria and release

C.

Definition of ready (DoR) and review

D.

Definition of done (DoD) and demonstrate

Full Access
Question # 11

A new stakeholder has recently joined a project. During a meeting with the Scrum Master, the new stakeholder tries to understand the status of the project and the remaining tasks for completion.

How should the Scrum Master inform the new stakeholder?

A.

Show the stakeholder the latest release breakdown for the project.

B.

Invite the stakeholder to attend the next sprint review meeting.

C.

Show the stakeholder the progress radiators for the project.

D.

Invite the stakeholder to attend the next sprint planning meeting.

Full Access
Question # 12

A manufacturing shop is using Kanban to plan, visualize workflow, and limit work in process (WIP). Which productivity key performance indicator (KPI) should the team lead be monitoring on a regular basis?

A.

Lead time

B.

Team velocity

C.

Burndown rate

D.

Earned value (EV)

Full Access
Question # 13

Unable to meet a sprint ' s committed velocity, an agile team approaches the agile coach to define the next sprint ' s velocity. What should the agile coach advise?

A.

Split each story into multiple stories to meet the desired velocity.

B.

Set the velocity to the delivered story points of the last sprint.

C.

Use different estimation methods for stories and defects to meet the desired velocity.

D.

Re-estimate by assigning more story points to smaller stories to increase the velocity.

Full Access
Question # 14

What should the team do?

A.

Re-estimate the sprint ' s completed stories to increase and adjust the sprint ' s velocity.

B.

Increase the duration of the next sprint to accommodate the incomplete user stories and maintain velocity.

C.

Work with the product owner to create a spike with another agile team.

D.

Re-estimate the incomplete stories for the next sprint because its relative size has changed.

Full Access
Question # 15

What should the agile coach do?

A.

Work with the team to determine points at which to celebrate its work.

B.

Provide the team with a break by scheduling a team event.

C.

Have the team increase work in progress (WIP) levels to more quickly complete the flow.

D.

Rejuvenate the team by temporarily reducing WIP levels.

Full Access
Question # 16

A technical problem arises that will likely impact the stories planned for delivery in the current sprint.

What should the Scrum Master do?

A.

Consider adding a story to the next sprint to seek resolution

B.

Immediately solve the problem on behalf of the team

C.

Ask the team to collaboratively work out a solution

D.

Engage a technical manager to assist with finding a solution

Full Access
Question # 17

During backlog refinement, the team uses an online planning poker tool for estimation. The junior developers change their number of story points after they see the estimations provided by the developers. The junior developers state that the reason for this is that they do not have enough experience and do not want to be blamed for sizing it wrong.

What should the scrum master do?

A.

Ask the developers to keep their estimation so that the team is transparent with their level of understanding of work.

B.

Agree with the team to keep their estimation as the final number of story points will be the average of all team members.

C.

Propose to consider the estimations of only senior developers and have the junior developers learn from them.

D.

Encourage the team to keep their estimation as this will help surface different constraints and assumptions that others might have missed.

Full Access
Question # 18

Two similar stories A and B are estimated at 3 story points. Story C is estimated at 8 points. After an iteration in which A and C were completed, it is found that story A took much longer than story C.

What should the agile practitioner do?

A.

Assign story B more than 8 story points to provide a better estimate

B.

Add points to story B’s iteration to account for the error but keep story B at 3 points

C.

Assign more resources to story B to bring it in line with the estimate

D.

Reestimate all stories including values for A, B, and C

Full Access
Question # 19

Which option describes how risk should be managed in an agile project?

A.

Since using an agile methodology minimizes risk in project management, the project team can focus on delivering business value over managing risk.

B.

Project team members would each be responsible for identifying and managing risks for the individual user stories they have been assigned.

C.

All stakeholders are responsible for identifying risks during standups, retrospectives, and other team meetings.

D.

The product owner is responsible for identifying risks and entering them into the backlog so that their mitigation can be prioritized.

Full Access
Question # 20

A project team for a local government is transitioning from a predictive development life cycle to an iterative development life cycle. The project sponsor has informed the team lead that the subject matter expert (SME) for the financial functions of the solution is overallocated, so the team needs to convert the previously gathered requirements into user stories.

What should the agile lead do?

A.

Explain that the testable acceptance criteria are included in each story and it is necessary for the expert to collaborate with the developers, testers, and product owner for common understanding of the solution.

B.

Agree, and ask the developers to explain to the testers how the solution should perform for quality assurance. The testers will demonstrate to the stakeholders how the system should perform to gain acceptance.

C.

Agree, because the developers can copy and paste the requirements and include the technical specifications and performance criteria while writing the stories to save time.

D.

Explain to the project sponsor that the user stories should be assigned to the analysts, because they helped write the requirements and better understand them.

Full Access
Question # 21

A company president is concerned about the impact of a natural disaster on the company. How should management identify areas to apply its resources and mitigate potential impacts?

A.

Establish and keep an active risk register that includes mitigation strategies and a cost-benefit analysis.

B.

Establish and keep an active risk register based on qualitative risk analysis and expected losses.

C.

Have each development team post the highest risk development items on the information radiator.

D.

Avoid risk by splitting development teams into two locations to ensure knowledge continuity.

Full Access
Question # 22

An agile team is in their 2nd iteration planning session. During the session, they are debating on whether regression and integration testing should be part of every iteration or part of the hardening iteration.

What should the agile lead recommend?

A.

Integration testing with other upstream or downstream applications and all bug fixes should be done as part of the hardening iteration.

B.

Integration testing with other upstream or downstream applications should be done by the team as part of every iteration.

C.

Continuous integration and regression testing should be done by the team as part of every iteration.

D.

Regression testing should not be done by the team as part of every iteration but only as part of the hardening iteration.

Full Access
Question # 23

The risk profile of a project has increased beyond the upper threshold of tolerance. The product owner and project leader meet to discuss an approach for dealing with this. What should the team do next?

A.

Add risk mitigation tasks to the backlog, then prioritize in current and upcoming sprints

B.

Add risk mitigation time to each requirement

C.

Apply the 80/20 rule, reserving 20 percent of each sprint’s capacity for risk mitigation

D.

Hold all risks until they become issues, then add issue resolution tasks to the product backlog

Full Access
Question # 24

A food company seeks additional business-to-business (B2B) revenues from some customers by

implementing purchase order (PO) functionality. To achieve this, the agile project team is exploring PO integration options (see item #3 in Exhibit A), as the product increment (PI) planning process is underway.

What should the project team do next?

A.

Use agile estimation techniques like planning poker or relative sizing for collaborative assessment.

B.

Break down the feature into smaller tasks or user stories for better assessment and incremental delivery.

C.

Analyze current system requirements and dependencies, including integration levels and regulatory compliance.

D.

Refer to past performance and historical data from similar projects to identity potential risks and challenges.

Full Access
Question # 25

Daily coordination meeting attendance has been declining recently. Those who attend have little to contribute outside of what they are currently working on. The project manager met with the team to remind them of the importance of regular, face-to-face communication. The project team feels the daily coordination meetings are not adding value.

What should the project manager do?

A.

Keep the meetings because some find them valuable and assume that those not attending are working steadily and have no blockers.

B.

Change the meeting to the end of the day ensure it lasts only 15 minutes and require all team members to attend.

C.

Work with team members to create a wiki where they can record their current accomplishments.

D.

Reduce the occurrence of meetings because team members regularly communicate with the another and the customer

Full Access
Question # 26

What should the agile practitioner do?

A.

Regularly circulate an updated, detailed version of the project plan

B.

Frequently update the online project management office (PMO) repository site

C.

Invite the stakeholders to daily stand-ups

D.

Post a project board in an area where all can view it

Full Access
Question # 27

An agile coach has been hired to improve the performance and quality of developed software. The coach performed an analysis of the software and discovered an excessive number of escaped defects, leading to external failures.

How can the agile coach effectively address and correct defects in the software development process while maintaining predictability and keeping workloads within capacity?

A.

Work with the team to create explicit rules such as coding and quality standards and testing policies.

B.

Discipline the team members and institute status meetings with penalties for any future escaped defects.

C.

Hire more generalized specialists because the current team members cannot keep up with the pace.

D.

Apply work in process (WIP) limits so the developers are not pressured to release code that is problematic.

Full Access
Question # 28

Stakeholders are unhappy because they have not been consulted on a user interface (UI) for a project that will have a significant impact on end users once it is launched.

How should this situation be handled?

A.

The Agile team should engage stakeholders regarding the proposed designs and ensure that sufficient engagement occurs throughout the project in an adaptive way.

B.

The Agile practitioner should inform the stakeholders that the UI has already been approved by the project team and sponsor, so the team is committed to staying the course.

C.

All stakeholders should go through the approved project charter and business requirements document to reduce the number of late changes or requests.

D.

The stakeholders should contact the project sponsor to get the project halted until new requirements are agreed upon.

Full Access
Question # 29

A project team identifies a number of technical challenges with features in the next sprint.

What should they do?

A.

Request direction from the technical manager

B.

Encourage the Product Owner to reallocate the features to another sprint

C.

Determine who is best qualified to address the challenges

D.

Ask the Product Owner to assign the tasks to the most appropriately skilled resources

Full Access
Question # 30
A.

Document the problem, escalate to the project manager, and develop a solution for the team

B.

Add the problem to the backlog and assign resolution to a future iteration

C.

Instruct the team to try to solve the problem within the team

D.

Perform root cause analysis and report the problem to the product owner

Full Access
Question # 31

An agile team had unexpected technical problems in a project and was not able to complete the deliverables on time. During the retrospective meeting, the team openly discussed the causes for these issues and what can be done to avoid similar situations in the future.

What agile values and principles did the team demonstrate?

A.

The team is being proactive by discussing how to better balance demands and capacity and make sure they have the right competencies.

B.

The team shows respect for one another by listening to everyone ' s opinions and valuing human interaction during face-to-face meetings.

C.

The team is providing one another with fast feedback to find those responsible for any mistakes so they can be avoided in the future.

D.

The team eliminates potential waste by discussing who should be responsible for future risk management by actively applying the pi an-do-check-act (PDCA) method.

Full Access
Question # 32

A product roadmap should contain which of these primary components?

A.

Detailed design plan, business objectives, timeframes

B.

Project management plan, communications management plan, stakeholder engagement plan

C.

Project release timeframes detailed design plan

D.

Product vision, business objectives, timeframes

Full Access
Question # 33

Toward the end of a project, the product owner discovers that the project has a high probability of failure due to a critical feature not functioning as expected.

What should the product owner do?

A.

Terminate the project to cut losses

B.

Review possible options and make an informed decision to cut losses based on delivered business value

C.

Bring in experts to increase the probability of success

D.

Continue the project, release the product without the failing feature, and fix the feature in a subsequent release

Full Access
Question # 34

A project team meets to estimate user stories for a sprint. While an important non-functional requirement must be delivered in the sprint, the estimate exceeds sprint capacity.

What should the team do?

A.

Estimate only functional requirements that will impact product quality

B.

Add team resources

C.

Refer the issue to the product owner

D.

Break non-functional requirements into those that can be delivered in the given sprint

Full Access
Question # 35

After completing the release plan, the team realizes that the project is very likely to have a negative ROI.

What should the team do?

A.

Prioritize the backlog, and remove low-priority stories from the release plan to ensure a positive ROI

B.

Replace some team members to reduce the release costs and minimize a negative ROI

C.

Perform a root-cause analysis to remove waste from the delivery process and increase the ROI

D.

Communicate the risk of a negative ROI to the stakeholders, and update the release plan

Full Access
Question # 36

Project stakeholders are finding it difficult to know the real-time status of who has been assigned to various stories and the status of each work item.

What should the agile project manager do?

A.

Use an information radiator to help increase the transparency of work for key stakeholders.

B.

Send status updates whenever the stakeholders request them.

C.

Hold Scrum meetings more frequently to ensure stakeholders are well informed.

D.

Instruct the team to focus on their own assignments rather than the work of others.

Full Access
Question # 37

Over the last two sprints, a number of potential problems have threatened the team ' s ability to hit the targeted release date.

What should the agile practitioner do?

A.

Deal with the issues in a retrospective if they ever come up again.

B.

Create a task board to track issues when they appear.

C.

Identify and monitor issues through a risk burndown chart.

D.

Create an issue log as an information radiator and monitor.

Full Access
Question # 38

What should the agile practitioner do next?

A.

Identify a team member to do a proof of concept using this framework.

B.

Email the team directing them to immediately begin using this new framework.

C.

Obtain feedback from team members on the new framework, and then suggest that the product owner create a backlog item to do a spike on it.

D.

Discuss this option at the next retrospective.

Full Access
Question # 39

A newly formed, colocated team is participating in daily standups, but is otherwise working largely as individual contributors. This has resulted in misalignment of activities. Planned velocity is being met.

What should the agile practitioner do?

A.

Plan activities that will require the team to work collaboratively on a regular basis.

B.

Set collaboration metrics and evaluate individuals against those metrics.

C.

Request that line management add more collaborative team members to the team.

D.

Allow the team to continue with no interference as activities are being met.

Full Access
Question # 40

During the retrospective meeting, it is revealed that an external dependency is causing a reoccurring impact. The impact is that an external team is not providing a fix or a stable testing environment. The scrum master has been unable to resolve this after escalating the situation to upper management several times.

What should the scrum master do now?

A.

Guide the development team to accept and adapt to the existing situation by finding sustainable workarounds.

B.

Assure that the development team plans the scope of work with this risk absorbed in the estimation.

C.

Establish a communications channel with the external team and monitor the implementation of the external task.

D.

Collect empirical data and influence upper management to be accountable for end-to-end. cross-team delivery.

Full Access
Question # 41

Two team members are working together to deliver an asset management tool. The code delivered by team member A during this sprint is not aligning with the specifications written by team member B. Both team members do not seem to agree on the look and feel of some functionality.

What should the Scrum Master do in this situation?

A.

Understand the root cause of this issue and recommend discussing their differences to find common ground.

B.

Hold a team meeting to discuss these issues and help direct the whole team on how to proceed further.

C.

Let the two team members resolve the conflict on their own.

D.

Ask their functional manager to intervene and resolve the issue.

Full Access
Question # 42

What should the agile project manager do?

A.

Since the team has extra time, notify the product owner and secure approval for the extra work on this feature.

B.

Encourage the team to document the improvement and prioritize it for the upcoming iteration, instead of building it now.

C.

Instruct the Scrum Master to have the team use the extra time to complete the extra feature work in the current iteration.

D.

Notify the product owner and have the product owner verify the backlog priority, then encourage team to continue working on the backlog.

Full Access
Question # 43

What should the agile practitioner do?

A.

Coach the product owner to update only the acceptance criteria.

B.

Instruct the agile team to fix the user stories during the next retrospective.

C.

Facilitate a user story workshop with the agile team.

D.

Inform the product owner ' s manager that the work items provide insufficient detail.

Full Access
Question # 44

A project is to be started with a team of nine existing and nine new members. The Scrum Master feels that the team is too large and wants to break it into three teams. The Scrum Master sets a constraint that each team have an equal number of existing team members for knowledge sharing and experience.

What should the Scrum Master do to accomplish this?

A.

Ask the team members ' functional managers for guidance on how to group the team members.

B.

Observe which team members are comfortable working together, then assign accordingly.

C.

Ensure that members begin to self-organize as small teams with efficiently distributed skills.

D.

Assign team members to their respective teams based on the skills known to the Scrum Master.

Full Access
Question # 45

Case Study

An agile project lead for a company is leading a sales team who has committed to delivering new product functionality to the customer at the end of five sprints. The agile project lead performed initial planning with the team and with the team ' s support has committed to the scope and deadline.

Check in with the project in three stages to answer the associated questions.

How do two additional features and more story points added by the product owner impact the team ' s progress and ability to complete work within the iteration, considering the burndown rate of the team has not changed? (Refer to the Case Study and End of Sprint 3 Exhibit)

A.

The scope of the items in the backlog has been increased to reflect an increase in velocity.

B.

The backlog has been increased and the velocity of the project may no longer be on track.

C.

The team has committed to additional work added to the backlog and will increase velocity.

D.

The team did not complete the backlog items at the same velocity due to external issues

Full Access
Question # 46

A product owner worked with the customer to define the success criteria for the launch of a new product in the manufacturing industry. The project team responsible for development is seeking guidance on what to develop first.

Which two actions should the product owner take? (Choose two.)

A.

Work with the team to establish goals for the product at the beginning of each scheduled iteration.

B.

Send the team the latest version of the release plan so they can provide feedback.

C.

Invite the customer to the sprint planning meeting to explain what is deemed most critical to their business.

D.

Ensure all iteration goals are fully developed at the beginning of the project.

E.

Refine the product backlog and identify the Minimum Viable Product

Full Access
Question # 47

Who should the Scrum Master invite to the meeting?

A.

The core team and the customer

B.

The product owner and key stakeholders

C.

The customer and the sponsor

D.

The core team and the product owner

Full Access
Question # 48

During project inception, an agile practitioner engages the stakeholder to ensure alignment on the project ' s strategy and vision. The stakeholder asks for detailed requirements, design, and delivery plans.

What should the agile practitioner do?

A.

Provide all information requested by the stakeholder

B.

Set expectations regarding the appropriate level of details requested during this stage

C.

Inform the stakeholder that no detailed documents are provided using agile practices

D.

Ask the team to supply the information to the stakeholder

Full Access
Question # 49

What should the team do?

A.

Collaborate with the product owner to reprioritize the product backlog, thus ensuring that more features will be completed before the release.

B.

Ask the team lead to calculate the team ' s target velocity according to the project plan, and assign additional resources to increase capacity.

C.

Focus on velocity and schedule concerns during the retrospective to inspect, adapt, and improve the process and plans.

D.

Reestimate the backlog items from the release, ensuring that contingency is included to set stakeholder expectations.

Full Access
Question # 50

An agile development team is working on a digital transformation project and is facing challenges in obtaining consistent feedback from stakeholders who are dispersed around the world. The product owner is under pressure as this lack of engagement has led to prolonged decision-making cycles and has adversely affected the outcomes of sprints.

How should the team improve stakeholder engagement to help ensure timely feedback and better decision-making? (Refer to Stakeholder Power/Interest Grid)

A.

Implement a dynamic feedback platform leveraging collaboration tools, accommodating diverse schedules and enabling stakeholders to provide feedback asynchronously.

B.

Establish a rotating stakeholder committee composed of representatives from different regions and departments, ensuring diverse perspectives are considered in decision-making processes.

C.

Enforce a strict policy requiring stakeholders to attend weekly synchronous feedback sessions, leveraging technology to accommodate various time zones and scheduling conflicts.

D.

Appoint regional liaison officers responsible for coordinating stakeholder interactions within their respective time zones, facilitating regular communication and feedback exchange.

Full Access
Question # 51

A new software development team has just been formed. 5 sprints have passed and the team is now familiar with their way of working. In the 6th sprint, the scrum master notices the team members arguing about the technical design of an upcoming new feature during a backlog refinement meeting. After the refinement meeting, the scrum master notices team members talking about the topic informally and taking sides. There is noticeable tension among the team.

How should the scrum master help the team to resolve the issue?

A.

Bring a subject matter expert (SME) from the technology design team to act as a consultant for the team.

B.

Coach the team individually then the whole team during the Sprint review on how to resolve this conflict.

C.

Delegate the decision for the best feature implementation to the most senior team member.

D.

Decide on the technical implementation that best fits the purpose of the technical design.

Full Access
Question # 52

What should the agile project manager have done to avoid this?

A.

Invited end customers to attend the stand-ups

B.

Organized design review sessions with the customer to obtain sign-off

C.

Held regular meetings with the product owner and project team to elicit detailed business requirements

D.

Conducted frequent review meetings with the customer to continually enhance delivery effectiveness

Full Access
Question # 53

The team is aware that they will need to integrate a new component to their solution in the next few weeks. The team does not have any experience with this component.

What should the team do next?

A.

Ask for a team extension so that an engineer with the needed experience can be added to the team.

B.

Suggest that the Product Owner perform the initial investigation and present the outcome to the team.

C.

Request that the Product Owner include a spike in the next iteration ' s backlog so they can perform an initial investigation.

D.

Propose alternative components with which the team has experience.

Full Access
Question # 54

What should the Scrum Master do?

A.

Ask the product owner how upper management ' s comments can be redirected.

B.

Direct the developer team to ignore the phone calls and emails.

C.

Ask the product owner to enter the requests into the product backlog as high priority.

D.

Personally respond to upper management ' s phone calls and emails.

Full Access
Question # 55

How should an agile project leader interact with the Product Owner?

A.

Conduct regular one-on-one meetings to review development features and trace them back to the product roadmap

B.

Ensure that they attend regular sprint meetings to provide product-feature feedback

C.

Share any new versions of the project plan with them including updated statuses for tasks and project milestones

D.

Schedule meetings where they can provide team direction regarding new-feature priorities and upcoming sprints

Full Access
Question # 56

An agile coach is working on a software development project. Their team is approaching the sprint deadline, but their client is requesting to include additional features that will bring added value.

What should the agile coach do to address this requirement?

An agile coach is working on a software development project. Their team is approaching the sprint deadline, but their client is requesting to include additional features that will bring added value.

What should the agile coach do to address this requirement?

A.

Explain to the client that the sprint deadline is approaching and the feature can be included in the next iteration.

B.

Remind the team and the client of the importance of assessing the risks of these features before deciding to include them

C.

Negotiate with the team to add the additional features in this sprint because they are important requirements.

D.

Ask the client for an extension of the deadline to enable delivery of this sprint with the additional features.

Full Access
Question # 57

An agile team is building a training safety video based on current government regulations. The agile coach knows the regulations are likely to change before the release date.

How should the agile coach address this change?

A.

Plan for the second release to include regulatory changes and new features.

B.

Hold off making changes during the current release because the regulatory changes cannot be planned for.

C.

Verify the team is building the product in increments which can be adapted at the last minute if necessary.

D.

Monitor regulatory discussions to get a head start on the upcoming regulatory changes.

Full Access
Question # 58

How can this issue be resolved?

A.

Break down the feature into smaller parts, and commit to completing the minimum viable product.

B.

Complete the iteration to which they have already committed, and include the feature in the next release.

C.

Change the planned features to include only the vitally important one.

D.

Extend the iteration to complete the feature.

Full Access
Question # 59

More details for a story are required before the upcoming sprint planning meeting.

What should the Scrum Master do?

A.

Email the product owner requesting detailed story specifications and wait for a response

B.

Gather the details from the team members before sprint planning

C.

Schedule a story grooming session with the product owner before sprint planning

D.

Conduct a planning poker session with the team

Full Access
Question # 60

A client is pressed for time and wants to launch a product with three components as soon as possible to gain market share. An agile lead proposes the following agile strategy to gain time: Three teams will work on the design and development of each component. Once all three components are finished, they will be tested and integrated.

Is this agile strategy appropriate?

A.

Yes, this is a case of sequential development where working in parallel is an accepted strategy in agile to gain time.

B.

Yes, this is a case of hybrid development where a product is divided into components and agile is used for component development and integration.

C.

No, dividing the development team into three separate teams will diminish communication and result in delays.

D.

No the feedback loops are being altered, which can result in big failures and delays

Full Access
Question # 61

An agile project was underway for two months and delivered the expected value to the stakeholders. However, during a sprint review, a team member complained that the product owner constantly changes requirements and the member feels that this is blocking the team’s performance.

How can the scrum master handle this situation?

A.

Work with the product owner to include fewer features in the next sprint planning.

B.

Hire more team members to elevate the team ' s velocity to increase performance.

C.

Tell the team members that changes are natural and welcome if the project is delivering value.

D.

Schedule more meetings with the team and the product owner to refine the backlog constantly.

Full Access
Question # 62

What should the agile practitioner have done to ensure stakeholder satisfaction?

A.

Communicated early and often, as outlined in the communications matrix

B.

Ensured engagement among stakeholders and the product owner

C.

Conducted additional stakeholder reviews and demos

D.

Worked with the product owner to prioritize user stories

Full Access
Question # 63

What should the agile practitioner do?

A.

Work with the agile team and product owner to agree on the definition of done

B.

Ask the project sponsor to determine whether the product is completed

C.

Plan another review after the product has been tested

D.

Add testing to the backlog, and have the product owner reprioritize

Full Access
Question # 64
A.

Coach team members to improve functional specialties and increase overall velocity.

B.

Identify where team processes misalign with accepted Scrum practices.

C.

Facilitate the identification of problems or issues and help the team resolve them.

D.

Review the backlog to ensure that it is prioritized, refined, and properly tasked.

Full Access
Question # 65

How should the agile practitioner address this?

A.

Implement a burnup chart and add the issue resolution as a task to the product backlog for the customer to prioritize.

B.

Add the issue to the Kanban board and assign it to the team member who has made the most progress on resolving it.

C.

Conduct a root-cause analysis on the issue and identify related risks and risk response owners at the next retrospective.

D.

Document all project issues in a common space and ask the team members to decide on task allocation principles.

Full Access
Question # 66

What should the agile coach do?

A.

Meet with the agile team lead to discuss ways to improve team velocity and get back on track

B.

Use this as a learning opportunity and allow the team to handle the situation when the marketing campaign begins

C.

In the upcoming retrospective, discuss ways to improve sharing project status information

D.

Meet with the marketing stakeholders to explain that the team will miss the planned release date

Full Access
Question # 67

A company is planning to launch a new service to improve the customer checkout experience.

What should the project manager do to meet the objective of reducing time to market to gain a competitive advantage in the industry?

A.

Engage the project stakeholders to assess the best practices to apply and plan the deliverables before implementation.

B.

Recommend an Agile delivery approach and provide information to the stakeholders on Agile values and principles.

C.

Educate the team about Scrum and ensure that all members are aligned to the roles required.

D.

Consult executive leadership for the most appropriate method for delivery using existing organizational practices.

Full Access
Question # 68

What should the team do to improve the accuracy of their estimates?

A.

Decrease the sprint time box until the team is able to deliver the entire agreed-upon sprint backlog in a single sprint

B.

Discuss estimating techniques in the daily scrum meeting

C.

Increase the size of the development team until the team is able to deliver the entire agreed-upon sprint backlog in a single sprint

D.

Begin tracking estimated effort metrics as an input to performance evaluation

Full Access
Question # 69

A project team member expresses frustration about the length of time it takes to make decisions for a complex project. Approvals need to happen at many levels in the company.

What should the team lead do to improve decision quality and reduce the time required to make decisions?

A.

Make sure the project owner is fully embedded into the project team so that they are readily available to make quick decisions.

B.

Establish collaborative behaviors among all members of the organization through a group decision-making process.

C.

Ensure all decisions are routed as quickly as possible to the project sponsor and have the rules of engagement visibly posted.

D.

Reduce the number of required approvals and expand the decision-control limits to the scrum master.

Full Access
Question # 70

A team working with a new technology faces a significant amount of uncertainty about its ability to deliver stories due to technical issues. What should the team do?

A.

Capture risks and make them visible, and use a burndown chart to focus on reducing risks early in the project.

B.

Ask the Scrum Master to extend the sprint ' s duration to allow more time to work through technical issues.

C.

Place the impacted stories on the story board, and use daily stand-ups to make the product owner aware of the technical issues.

D.

Seek guidance from the development manager.

Full Access
Question # 71

During an interview for an agile team lead for a global company, a candidate is asked: " How do you ensure your project is aligned with the stakeholders ' priorities? "

How should the candidate respond?

A.

Engage the change management team to determine prioritization of the backlog.

B.

Allow the stakeholders to decide on the priority and build the backlog.

C.

The entire team should discuss and prioritize the backlog factoring in stakeholder input.

D.

Only the agile team lead and team need to decide how to prioritize the project deliverables.

Full Access
Question # 72

An agile project manager has noticed their teams declining morale, mistrust, and isolation over the last 6 months of working on a project. What should the agile project manager do to enhance productivity and create a cohesive team culture?

A.

Develop a reward system related to position and years of experience.

B.

Clarify project goals and project contract constraints.C Promote cross-training and —entering among tea— members

C.

Introduce performance standards and evaluation methods.

Full Access
Question # 73

A Scrum Master would like to provide information to key stakeholders on the daily resource and project activities. Which tool should the Scrum Master use to provide these updates?

A.

Shared vision statement and sprint goal

B.

Release burnup chart

C.

Velocity metrics

D.

Iteration burndown chart

Full Access
Question # 74

What should the agile coach ensure that developers do?

A.

Establish pair programming partners, and regularly perform peer reviews.

B.

Perform demos at the end of each iteration.

C.

Send coding to the quality assurance (QA) team upon completion.

D.

Demonstrate each feature to the client as soon as coding is complete.

Full Access
Question # 75

A scrum team is experiencing lengthy discussions leading to no concrete actions during their scrum events. The scrum master determines that these inefficient meetings are producing waste.

What should the scrum master do to make the meetings more efficient?

A.

Issue fixed agendas and a decision log for all scrum events to ensure that only relevant agenda points are discussed and decisions are appropriately captured.

B.

Remind the team of the purpose of each scrum event, and implement a policy that long conversations deviating from the scope of each event will be stopped.

C.

Ask the product owner to conduct these discussions in individual meetings with the team members.

D.

Remind the team that staying on topic during meetings is part of being a self-managing team.

Full Access
Question # 76

An agile team consisting of eight members is in their 11th iteration of a project. In the last iteration, the team was not able to complete every scope item it had committed to before the demonstration.

Which approach should the agile lead take?

An agile team consisting of eight members is in their 11th iteration of a project. In the last iteration, the team was not able to complete every scope item it had committed to before the demonstration.

Which approach should the agile lead take?

A.

Coach the team to decompose the backlog activities to granular, simple tasks that are easier to estimate and complete.

B.

Evaluate the team ' s capacity and help them select user stories for the iteration based on 60% of their capacity utilization.

C.

Discuss options to add more people to the team so they can complete the tasks on time and within budget.

D.

Evaluate the team ' s capacity and help them select user stories for the iteration based on 80% of their capacity utilization.

Full Access
Question # 77

During planning sessions, an agile practitioner notices that some team members do not share common ideas.

What should the agile practitioner do?

A.

Ask the team if they would like to adopt alternative techniques

B.

Create a team norms document to set participation guidelines

C.

Ask the Scrum Master to resolve the issue at the stand-up meeting

D.

Capture feedback during lessons learned at the end of the iteration

Full Access
Question # 78

What should the product owner do?

A.

Accept responsibility for the product ' s delay.

B.

Ensure that the project sponsor ' s priorities are in the product backlog.

C.

Negotiate with the project sponsor for increased funding.

D.

Empower the project sponsor to manage the product backlog.

Full Access
Question # 79

An agile coach is working on a digital transformation project. The project team is in the middle of a 5-week sprint. The agile coach notices constant arguing among team members on what should be the preferred technical approach to solve a current business problem. What can the agile coach do to promote collaboration and consensus-building among team members?

A.

Work with team members to resolve the issue.

B.

Escalate the issue to the product owner.

C.

Allow team members to resolve the issue.

D.

Escalate the issue to senior management.

Full Access
Question # 80

During team meetings, the team often struggles with making decisions about their technical approach.

What should be done to improve the quality and timeliness of decisions?

A.

Work with the team to improve collaboration by fostering group decision-making and conflict resolution techniques.

B.

Promote team discussion but give the Product Owner the ultimate decision-making authority.

C.

Assign individual team members as decision owners for each key decision to avoid conflict.

D.

Identify team members that demonstrate servant leadership qualities to facilitate discussion and make decisions.

Full Access
Question # 81

An executive sponsor asks a team when a specific feature will be ready for release. A team member states the feature will be ready by the end of release 3 because it is not a core feature. The team member directs the sponsor to an information radiator, where the sponsor sees several notes grouped by release numbers and posted on the wall.

What is the sponsor looking at?

A.

Project management plan

B.

Product backlog

C.

Gantt chart

D.

Product roadmap

Full Access
Question # 82

To help the team gain confidence, what should the agile practitioner suggest?

A.

Develop a spike

B.

Create an Ishikawa diagram

C.

Perform a pre-mortem analysis

D.

Complete a variance and trend analysis

Full Access
Question # 83

During initial planning, a project team investigates several approaches to building new application software, emphasizing the most valuable deliverables. The team needs to convince stakeholders and win their approval.

How can the project team achieve this?

A.

Use a successful platform on which several object-oriented products have been developed in the past.

B.

Create a quick mock-up of the product to serve as a visual tool and adjust it until consensus is reached.

C.

Include brief exploratory iterations, proof-of-concept (POC). to reduce project risk at the beginning of every project cycle.

D.

Deliver an iteration planning diagram, allowing a 2-week refactoring period at the end of the project.

Full Access
Question # 84

A.

It trended ahead of schedule and completed everything on time

B.

It took more time than expected and had to be lengthened

C.

It trended behind schedule and did not complete everything on time

D.

It took less time than expected and had to be shortened

Full Access
Question # 85

Halfway through the execution of an agile project, a retrospective meeting is held. One of the team members believes that the actual time and cost to complete the work has consistently been greater than what was originally estimated.

Which of the following activities should be performed next?

A.

The product owner should reduce the scope of the project so that the items delivering the highest business value can be completed.

B.

The team should perform a spike to conduct research on their technical solutions and prove their viability.

C.

The team should consolidate small stories into larger ones so that there are less work items to be estimated.

D.

The team should reevaluate time and cost estimates to reflect the latest understanding of the work effort.

Full Access
Question # 86

In a project, the customer asks for a requirement that clearly deviates from the contract terms.

How should the contractor react?

A.

Proceed with the work only after the contract is amended.

B.

Discuss the value of the change for the project with the customer.

C.

Evaluate effort and impact and ask for steering committee and shareholder approval.

D.

Stick with the contract terms and agree to review the requirement if time allows.

Full Access
Question # 87

An executive sponsor of a new Scrum team actively attends Scrum ceremonies.

How does this benefit the team?

A.

It helps the team to focus on and meet sprint goals.

B.

It reminds the team about who sponsors the project.

C.

It provides high-level project updates to the sponsor.

D.

It helps to quickly resolve issues using the sponsor ' s influence.

Full Access
Question # 88

An agile team has been given a complex project with a basic set of requirements which need further elaboration and review. How should the team iteratively build out the backlog of requirements with the stakeholders?

A.

Conduct a requirements gathering workshop.

B.

Deliver the basic requirements iteratively.

C.

Have the product owner fill out the requirements backlog.

D.

Have the stakeholders fill out the backlog before starting the project.

Full Access
Question # 89

A product owner is working on a special agile project for the automobile industry. The project team is responsible for all of the issues related to vehicle electronic control units. The team has observed a significant backlog of items in the “In progress ' column (Refer to the kanban board). This accumulation is causing delays in task completion and impacting overall project timelines. The team operates in a dynamic environment where requirements frequently change, and stakeholders demand quick turnarounds.

What should the project team adopt to address this issue and improve task flow, considering all the demands?

A.

Increase the number of items allowed in the ' In progress " column to accommodate the high volume of tasks and provide flexibility.

B.

Limit the work in progress (WIP) and implement strict policies to encourage team members to focus on completing existing tasks before starting new ones, ensuring a balanced workload.

C.

Move tasks to the ' Done " column regardless of their completion status to give the appearance of progress and alleviate the pressure of the backlog.

D.

Add more team members with varying levels of expertise to handle the increased workload, aiming to accelerate task completion and reduce the backlog in the ' In progress " column.

Full Access
Question # 90

The agile coach of a development team uses a servant leadership approach. The team is starting the third iteration of an upgrade to a software product, and work is going slower than initially planned.

What should the coach do to help the team?

A.

Help the team to remove impediments that stall project progress.

B.

Work with the development team to adjust the work plan.

C.

Ask the product owner to assign more resources to the project.

D.

Command and control the team to achieve plan goals.

Full Access
Question # 91

A product owner is responsible for a new product. The internal customer questions using an agile approach because they need a product that works without any bugs or missing features once it is launched.

What should the product owner do?

A.

Plan regular retrospectives with the development team to continuously improve processes to eliminate any potential issues with the product.

B.

Apply an agile approach to write the specifications in an incremental way and develop the product once the final specifications are agreed upon.

C.

Set up test-driven development to focus on customer requirements and eliminate issues in the software as testing progresses,

D.

Ask the customer to provide additional representatives to help test and evaluate the product for early and frequent feedback.

Full Access
Question # 92

How can an agile practitioner ensure that all key stakeholders are properly engaged in planning?

A.

Collect stakeholder requirements

B.

Conduct an iteration planning meeting

C.

Communicate product backlog items to the stakeholders

D.

Facilitate a product development roadmap workshop

Full Access
Question # 93

A project ' s Product Owner asks the Scrum Master to facilitate the estimation activity. The Scrum Master then meets with the team and the Product Owner to clarify the user stories. Following the meeting, the team assembles and provides individual user-story estimates.

What technique did the team use?

A.

Lessons learned

B.

Wideband Delphi

C.

Formal point counting

D.

Planning poker

Full Access
Question # 94

What should the agile coach do to develop members into a high-performance team?

A.

Teach the team how to work comfortably in chaos.

B.

Provide strong facilitation and conflict-resolution guidance.

C.

Allow the team to resolve issues on their own.

D.

Observe each team member and advise them on team relationships.

Full Access
Question # 95

A Kanban team is struggling to prioritize and determine which tasks to handle first according to value.

What should the team do to improve this situation?

A.

Involve their product owner.

B.

Review their work in progress (WIP) limits.

C.

Use class of service.

D.

Measure their lead time.

Full Access
Question # 96

A healthcare agency has contracted a vendor to provide a financial accountability solution. During a daily coordination meeting, the lead developer reports they cannot complete the stories for this iteration because the project director requested a document detailing all testing planned for the solution. The team lead met with the project director to discuss alternatives but insists they need the detailed plan by the end of that week. The team lead advises the lead developer to continue coding.

What should the team lead do next?

A.

Negotiate with the project director to reduce the types of tests for which they need details to reduce the impact of this request.

B.

Escalate this as an issue to the executive project sponsor for a decision because it will impact the ability of the team to deliver the product on time.

C.

Ask the test manager to provide a detailed estimate of the time required to write the plan for the solution and their capacity for the remainder of the week.

D.

Ask the team to put their work on hold and collaborate on the documentation because it can be completed quicker if everyone shares the work.

Full Access
Question # 97

A global subscription-based service is pursuing enterprise agility across digital product development teams. Product teams release updates frequently, but customer usage data and support trends are reviewed only at the end of each quarter. As a result, several low-adoption features continue to receive investment while customer churn gradually increases. Leadership wants the product teams to respond more quickly to changing customer behavior.

What should the agile practitioner recommend?

A.

Schedule monthly executive reviews to assess customer usage and feedback to support investment decisions.

B.

Integrate customer usage analytics into feature prioritization processes to adjust investment decisions.

C.

Delegate feature prioritization decisions to regional business managers based on customer usage analytics.

D.

Increase the number of features delivered each quarter to drive customer usage and improve overall satisfaction.

Full Access
Question # 98

What should the agile team do next?

A.

Ensure that the product owner reviews the acceptance criteria for delivered user stories.

B.

Augment the quality assurance and continuous integration processes for delivery.

C.

Approach the relevant developers and testers regarding quality issues in upcoming iterations.

D.

Ask the product owner to define the entire scope of delivery two to three iterations in advance.

Full Access
Question # 99

A new team member asks what changes could accelerate a change to the project plan.

What should be the proper response?

A.

Competitors joined forces with the team

B.

The customer changed requirements

C.

Project team members obtained additional certifications

D.

Technology which did not interfere with the final product

Full Access
Question # 100

During a project review, the team discovers customer feedback that would add scope. The project leader is concerned that the team will be unable to incorporate this feedback and still meet the product launch date.

What should the project leader do?

A.

Finalize the feedback in the form of a change request

B.

Limit the scope of the feedback to only those changes that the team can feasibly accommodate

C.

Encourage all feedback then work with the customer to prioritize work for future sprints

D.

Allow the team to decide what feedback to incorporate

Full Access
Question # 101

What should the agile team lead do?

A.

Create a new team to deliver the dependencies, and bring team B under performance management.

B.

Conduct a vision-sharing session with the teams to communicate the project ' s overall goals.

C.

Swap team members from both teams so that deliveries are better supported.

D.

Discuss negotiating the delivery timelines with team A.

Full Access
Question # 102

When considering impact on a project, to whom should an agile project manager give top priority on the stakeholder list?

A.

The stakeholder who can prevent the project from delivering within budget

B.

The stakeholder who can prevent the project from achieving its goals

C.

The stakeholder who can delay the project

D.

The stakeholder who can work as a friend and help prepare the stakeholder list

Full Access
Question # 103

Just before a scheduled product launch, the customer declined to accept the final deliverable after seeing the demo. What should the project manager do to prevent this in the future?

A.

Ensure the teams are working together daily throughout the product development and are keeping the team ' s progress up to date.

B.

Ensure there is an environment where team members feel comfortable sharing their ideas, concerns, and feedback.

C.

Ensure the customer is provided with regular project status updates and that the meeting minutes are well documented.

D.

Ensure the team is able to release new features and updates frequently so that customers can see the product and provide feedback.

Full Access
Question # 104

The systems integrator for an enterprise resource planning (ERP) project has been onboarded. During an iteration planning session, the team determines that the next highest priority item will take longer than expected to complete in the current sprint.

What should the agile practitioner do next?

A.

Schedule a meeting with the product owner to review the sprint priorities.

B.

Put the high-priority item back into the product backlog.

C.

Extend the sprint end date to accommodate the high-priority item.

D.

Ask the project sponsor to add more resources to ensure timely completion.

Full Access
Question # 105

How should the project team address this issue?

A.

Suggest pair programming during the retrospective.

B.

Ask the product owner to re-prioritize the user stories at the next retrospective.

C.

Re-estimate the story points with team members at the next iteration planning meeting.

D.

Assign less complex user stories to the inexperienced software engineer at the next iteration planning meeting.

Full Access
Question # 106

An agile team has started to worry because lately they have seen an increase in the number of issues. There seems to be a large variance in the quality of the work items delivered. The team now realizes that a shared understanding of quality may not exist among team members.

What should the team do?

A.

The team should move to test-driven development as defects are not being detected during testing.

B.

The team should account for the increased problems in their velocity forecasts since unexpected changes occur in agile projects.

C.

The team should discuss their definition of done (DoD) and make changes to ensure there is common understanding of the acceptance criteria.

D.

The team ' s agile project manager should facilitate the development of a new, detailed test procedure that all team members must follow.

Full Access
Question # 107

There is a debate within the organization on whether projects need to be agile or waterfall. Some agile terms and principles are understood differently by the key stakeholders and this delays the decision-making process.

How should the scrum master proceed?

A.

Allow stakeholders to discuss without the scrum master ' s intervention.

B.

Recommend an external facilitator as no one in the organization is able to eliminate this roadblock.

C.

Facilitate a face-to-face discussion and have stakeholders agree to shift to agile for future projects.

D.

Organize training sessions to create awareness around the agile values for stakeholders.

Full Access
Question # 108

A global organization is migrating its IT infrastructure from traditional, physical assets to cloud-based assets. Agile concepts are new to the organization because it currently uses a predictive approach.

What should an Agile Coach do to facilitate a culture change to an Agile approach?

A.

Develop and distribute a high-level summary of how Agile offers greater benefit than predictive to mid-level managers and let them decide if it should be distributed to lower-level workers.

B.

Develop and distribute a high-level summary of competing vendors ' product alignment and Agile project execution to the Product Owner for approval.

C.

Develop and distribute a high-level summary of how Agile offers greater benefits than predictive to all members of the organization.

D.

Develop and distribute a high-level summary of how Agile offers greater benefits than predictive to the organization ' s executive directors, and if executive directors agree with the summary, distribute it organization-wide.

Full Access
Question # 109

What should the team do?

A.

Reduce work in progress (WIP) limits to accommodate slack for riskier stories

B.

Create a triage step on the Kanban board to pre-identify risky stories

C.

Set a policy to break down stories larger than a specified complexity, then adjust the WIP

D.

Create a dedicated overflow swimlane on the Kanban board for stories that are too large

Full Access
Question # 110

An agile team is continuously interrupted by stakeholders wanting to ask product backlog questions. Distractions can have a negative impact on value delivery and quality.

Who is responsible for protecting against distractions?

A.

Product owner

B.

Project manager

C.

Agile leader

D.

Developers

Full Access
Question # 111

Why is stakeholder engagement important for project success?

A.

To participate in establishing a shared vision as a member of the team

B.

To provide the acceptance criteria for the delivered items

C.

To propose implementation methods to the development team

D.

To evaluate the performance of the development team

Full Access
Question # 112

A project team realizes that an important task on the iteration backlog will take more time than originally estimated.

What should the project team do?

A.

Continue working on the task until it is completed

B.

Remove the task owner from the project team

C.

Add resources to reduce time to task completion

D.

Stop working on the task and include it in the next iteration

Full Access
Question # 113

During a project ' s last few sprints, an agile practitioner notices an increase in defects. A root-cause analysis indicates that a poor understanding of the requirements was caused by the inability of the product owner to communicate clearly.

What should the agile practitioner do?

A.

Inform the product owner ' s manager so that corrective action may be taken.

B.

Communicate this to the product owner, and offer to help facilitate discussions with the team.

C.

Encourage a team member to raise this during the retrospective to ensure that the product owner is aware.

D.

Escalate this issue to the sponsor so that corrective action may be taken.

Full Access
Question # 114

How can an agile project manager ensure that all stakeholders have a clear understanding of the release plan by the end of a release planning meeting? (Choose two.)

A.

Stated understanding of the release goal

B.

Complete vision of the end product

C.

Timeline of the project

D.

List of the user stories that will be part of the next releases

E.

Complete roadmap of the next iterations

Full Access
Question # 115

A global manufacturing organization has launched an enterprise agility initiative to accelerate its sustainability transformation. Product, operations, and compliance teams disagree on how quickly to shift toward lower-carbon materials, with some concerns centered on cost impacts and others on environmental commitments. Tension is increasing in cross-functional meetings, and collaboration has slowed.

What should the agile practitioner recommend in this situation?

A.

Initiate discussions to understand the underlying impact and devise plans to align teams around shared sustainability outcomes.

B.

Define targets to support sustainability outcomes and require all business units to strictly comply with the revised timelines.

C.

Establish executive decision authority to determine the appropriate levels of using sustainable materials.

D.

Create measurable key performance indicators (KPIs) to maximize the support of using sustainable materials.

Full Access
Question # 116

A new Scrum team is struggling with the various ceremonies of Scrum. Among other things, the product owner and stakeholders find the technical architecture and design presentations during sprint reviews less than informative.

What should the team do?

A.

Refocus the sprint review meetings to demonstrate working software and seek feedback on the product.

B.

Reach out to other, more experienced teams to seek input as to how to present the technical details in a more informative manner.

C.

Explain the importance of the technical architecture and design presentations and improve the presentation format.

D.

Invite technical managers and architects who will be a more appropriate audience to their sprint reviews.

Full Access
Question # 117

What should the agile team lead do?

A.

Ask the team to conduct research to find a viable solution.

B.

Select a better technology for team implementation.

C.

Obtain customer input on their technology requirements.

D.

Consult the product owner about their non-functional requirements.

Full Access
Question # 118

A senior executive contacted an agile lead about starting an agile project to solve a problem for the human resources (HR) department of a company. The project idea is not clear and no backlog has been developed.

How should the agile lead start the project?

A.

More work is needed to refine the idea and there is no backlog to start working on, so there is no way to help the manager.

B.

Identify the persona that needs help and conduct a workshop applying the empathy map technique about that persona.

C.

Review how similar problems have been resolved in other companies and see if a solution is available on the market.

D.

Start working on a list of user stones to create a backlog and suggest a product owner be assigned to the project.

Full Access
Question # 119

During an interview for an agile team lead role at a global company, a candidate is asked: “How do you ensure your project is aligned with the stakeholders’ priorities?”

How should the candidate respond?

A.

Engage the change management team to determine prioritization of the backlog.

B.

Allow the stakeholders to decide on the priority and build the backlog.

C.

The entire team should discuss and prioritize the backlog, factoring in stakeholder input.

D.

Only the agile team lead and team need to decide how to prioritize the project deliverables.

Full Access
Question # 120

An agile coach is facing a dilemma: On one hand, there is a requirement that is vital and will consume all capacity of the team. On the other hand, there are some chore-related tasks that will improve the team ' s ability to produce results. The team insists on implementing these tasks since they will increase efficiency.

What should the agile coach do?

A.

Characterize chores as low priority since they do not add obvious value to the product

B.

Delegate chore-related tasks to another team.

C.

Escalate the issue to the shareholders/steering committee.

D.

Get the product owner and team to meet to prioritize the work.

Full Access
Question # 121

An agile team lead noticed their team’s velocity was slowing down. They did not deliver a working software during the last iteration and there have been miscommunications between team members.

What should the agile team lead do at the end of this iteration?

A.

Focus on performance in the retrospective, then present performance indices and validate with the team.

B.

Start using feedback loops in every sprint to reevaluate project and team performance.C Emphasize business requirements and investigate the pair-programming approach

C.

Run a spike at the end of the sprint to investigate the issue and reduce project risk.

Full Access
Question # 122

An agile team is having a meeting with a customer to formulate the product requirements for the next iteration. The outcome of the meeting is a set of clear and detailed requirements.

What should the team do next?

A.

Run automated tests on the legacy functionality.

B.

Ask the customer to write tests that will be used to know when a story has been correctly developed.

C.

Start coding on the selected user stories to meet the requirements.

D.

Write tests that will be used to know when a story has been correctly developed.

Full Access
Question # 123

A development team is working on the implementation of a human resources (HR) solution. The team has decided to work together with different business units to deliver value early and often.

Which agile value or principle is being practiced in this scenario?

A.

Deliver working software often, with a preference for shorter timescales and responsiveness to changing requirements.

B.

The best architectures, requirements, and designs emerge from self-organizing teams.

C.

Contributions and interactions are more important to success than processes and tools.

D.

Customer-centric product development practices are more important than product-centric approaches.

Full Access
Question # 124

During a project ' s last iteration, an agile team struggled with a feature ' s delivery due to the lack of a required skill. The project has already incurred a five-day delay. A further delay of at least 10 days is anticipated.

What should the agile project leader have done to avoid this situation?

A.

Provided just-in-time training of the required skill to specific team members

B.

Lowered the feature ' s priority until a team member acquired the skill to build it

C.

Assigned the feature to another agile team that had members with the required skills

D.

Ensured that the team was comprised of cross-functional, generalized specialists

Full Access
Question # 125

What should a team do when they complete all sprint goals earlier than expected?

A.

Begin working on an item in the backlog

B.

Ask the Scrum Master to select an item from the backlog on which to work

C.

Ask the Product Owner to select an item from the backlog on which to work

D.

Jointly decide with the Scrum Master on an item from the backlog on which to work

Full Access
Question # 126

During a team meeting, conflicting opinions arise regarding the best approach to complete a project task. The project manager wants to ensure that the team can effectively handle these conflicts and come to a resolution that benefits the project.

What is an effective way to handle conflicting opinions in team meetings in an agile environment?

During a team meeting, conflicting opinions arise regarding the best approach to complete a project task. The project manager wants to ensure that the team can effectively handle these conflicts and come to a resolution that benefits the project.

What is an effective way to handle conflicting opinions in team meetings in an agile environment?

A.

End the discussion until there is consensus.

B.

Wait for the problem to resolve itself.

C.

Choose the option that is best for the team.

D.

Restate the positions to find what is in common.

Full Access
Question # 127

A customer has given a project team several requests for new features on a product. The customer is upset that the requests have been placed in the backlog and are not currently being worked on by the team.

What should the team do next?

A.

Review the feature requests and reject the most complex ones.

B.

Organize the feature requests from simple to complex.

C.

Prioritize the requests for the next sprint.

D.

Turn the requests into user stories and prioritize them.

Full Access
Question # 128

What is the project leader trying to create?

A.

A safe space for team members to learn to trust one another, leading to collaborative relationships.

B.

A safe space for team members to learn to be vulnerable, leading to high performance relationships.

C.

A safe space for team members to learn to share, leading to collaborative relationships.

D.

A safe space for team members to learn about each other ' s weaknesses and strengths.

Full Access
Question # 129

What should the product owner do to resolve this?

A.

Ask the development team to address the issue since it is in their domain.

B.

Review the project ' s risk matrix, and follow the steps outlined in the risk mitigation plan.

C.

Meet with the team and stakeholders to address rework and rewrite stories as needed.

D.

Cancel the current sprint, and meet with stakeholders to reassess the project ' s validity.

Full Access
Question # 130

During a sprint, the team encounters a technical problem that becomes an impediment to completing two stories.

What should the Scrum Master do?

A.

Ask the lead developer to identify a solution, and then share the details with the team

B.

Ask a technical manager or architect to determine a solution to the problem

C.

Work with the product owner to add a spike to the next sprint to identify a solution

D.

Create a collaborative team environment so that the team can explore a solution together

Full Access
Question # 131

During a sprint demo, a business representative identifies missing requirements. The agile practitioner realizes that all key stakeholders were not included during requirements detailing.

What should the agile practitioner have done to avoid the situation?

A.

Included the stakeholders in the project planning meeting

B.

Organized an earlier demo to solicit business feedback

C.

Ensured all business leaders signed off on requirements

D.

Engaged key stakeholders periodically to collect requirements

Full Access
Question # 132

What do the principles of Extreme Programming (XP) include?

A.

Communication, respect, and courage

B.

Communication, process flow, and authoritarian structure

C.

Value people over processes, communication, respect disagreement, and strive for consensus

D.

Rapid feedback, assume simplicity, incremental change, embrace change, and quality work

Full Access
Question # 133

The first project vision statement meeting for a newly formed team did not achieve its outcome. Lack of participation combined with conflicting views of those who participated led to disagreement on how to proceed.

How can the team improve their collaboration?

A.

Set clear expectations and allow everyone to contribute.

B.

Prepare the project vision statement and then present it to the team.

C.

Ask senior management to address the situation.

D.

Seek assistance from the scrum master to mediate the conflict.

Full Access
Question # 134

What should the project team do next?

A.

Estimate the project team ' s capacity.

B.

Determine how much work can be delivered.

C.

Calculate how much work will fit into the next iteration.

D.

Estimate items in the product backlog.

Full Access
Question # 135

There is a throughput of 200 tickets in a customer service line. The tickets are raised by employees, with each 8-hour shift averaging 50 tickets in progress.

What is the cycle time to resolve a ticket?

A.

0.25 hour

B.

1 hour

C.

2 hours

D.

4 hours

Full Access
Question # 136

During a review close to a product release, the customer spotted several features that will need to be changed. What caused this to happen?

A.

Reduced or improper customer collaboration.

B.

Reduced or improper product knowledge by the development team.

C.

Reduced or improper release planning.

D.

Reduced or improper product specification.

Full Access
Question # 137

How should this be handled?

A.

The story should be assigned eight story points as per the majority vote

B.

The story should be added to the backlog and reassessed later

C.

The story should be assigned points after a discussion with the fifth team member to see if a consensus can be reached

D.

The decision for the number of story points should be made by the customer

Full Access
Question # 138

A software company is developing an accounting software system to market to customers. The team has been working on the project for six weeks and has great velocity. One of the major stakeholders approached the Scrum Master and asked for a bi-weekly status report because they feel they are not being properly updated.

How should the Scrum Master respond to this request?

A.

Inform the stakeholder that all updates are provided in the sprint review sessions and encourage them to attend.

B.

Create and update bi-weekly project status reports for the stakeholder who requested the report.

C.

Escalate this to the stakeholder ' s supervisor because this is an unreasonable request.

D.

Ignore the stakeholder ' s request and continue working on the project as they have been for the past six weeks.

Full Access
Question # 139

The team is working to build a new Al model that will summarize and create presentation materials for executive leaders from external and internal content. The team believes there is value in increasing the scope of work as it will benefit the organization.

Which two actions should the product owner take first? (Choose two.)

A.

Determine the cost and resource requirements.

B.

Create a spike to determine the dependencies.

C.

Create a change request to formalize the requirements.

D.

Seek executive approval on the approach.

E.

Determine the purpose and value proposition on the approach.

Full Access
Question # 140

An agile lead is experienced with predictive and agile approaches. The agile lead was recently invited by human resources (HR) to be part of a learning team. During roundtable discussions with the project management team, the agile lead states: " I foster a safe environment for disagreement so my team feels empowered to move forward without obstacles. "

What is the agile lead attempting to highlight?

A.

Ownership, because team members will be in charge of whatever happens during the project life cycle.

B.

Conflict is not productive and team members should resolve issues by themselves.

C.

Better decision-making, because the team is encouraged to join in constructive conflict.

D.

Leaders should incentivize conflict because it is inevitable in the workplace.

Full Access
Question # 141

Part way through a project, several team members are in conflict over whether or not a deliverable has been properly completed.

How should the agile leader reduce this conflict?

A.

Facilitate team agreement on the definition of done (DoD) during the chartering process.

B.

Motivate the team during Tuckman ' s " storming " phase.

C.

Ensure the product owner is grooming the backlog so user stories are clearly written.

D.

Ensure epics are broken down into smaller user stories for clarity.

Full Access
Question # 142

What should an agile practitioner do to ensure that the end product meets business requirements?

A.

Invite the team to iteration review meetings

B.

Obtain agreement from the product owner on business requirements

C.

Request that regular reports are sent to stakeholders

D.

Confirm managers and stakeholders are invited to product review meetings

Full Access
Question # 143

A development team and product owner disagree on a user story in the product backlog. What should the agile practitioner do?

A.

Have the development team follow the product owner ' s direction

B.

Openly challenge the product owner in an effort to poke holes in their approach

C.

Facilitate a conversation about the user story between the development team and the product owner

D.

Serve as a nonpartisan evaluator of each option, and provide direction to the development team and product owner

Full Access
Question # 144

A project team has been working on a new application. The application is technically challenging, because the team is using new technology unknown to the development team and business requirements are unclear. The product owner has been working closely with the stakeholders to ensure alignment with requirements and other issues. The agile lead is working with the team and product owner on the product backlog.

What is the role of the team?

A.

Estimate and define the work items.

B.

Assess user story quality and independent, negotiable, valuable, estimable, small, and testable (INVEST) criteria.

C.

Add features to the product backlog.

D.

Determine if the demand is or is not feasible.

Full Access