Weekend Sale - Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70dumps

CAPM Questions and Answers

Question # 6

While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?

A.

Utilize the change control process.

B.

Crash the schedule to fix the defect.

C.

Leave the defect in and work around it.

D.

Fast-track the remaining development.

Full Access
Question # 7

Which group of inputs will a project manager use during the Monitor Stakeholder Engagement process?

A.

Project charter, business documents, and project management plan

B.

Agreements, scope baseline, and project management plan

C.

Project charter, business case, and project management plan

D.

Work performance data, enterprise environmental factors, and project management plan

Full Access
Question # 8

Select two key benefits of the Control Procurements process

A.

Enables the development of make-or-buy decisions

B.

Ensures that contract performance meets the terms of the legal agreement

C.

Guarantees that legal agreements influence vendor selection

D.

Assures that legal agreements guide contract closings

E.

Helps determine whether a certain type of contract should be used

Full Access
Question # 9

Perform Quality Control is accomplished by:

A.

Identifying quality standards that are relevant to the project and determining how to satisfy them.

B.

Monitoring and recording the results of executing the quality activities to assess performance and recommend necessary changes.

C.

Ensuring that the entire project team has been adequately trained in quality assurance processes.

D.

Applying Monte Carlo, sampling, Pareto analysis, and benchmarking techniques to ensure conformance to quality standards.

Full Access
Question # 10

Which Process Group ' s purpose is to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes?

A.

Monitoring and Controlling

B.

Initiating

C.

Planning

D.

Executing

Full Access
Question # 11

What key component of the project charter defines the conditions for dosing a project phase?

A.

Purpose

B.

Approval requirements

C.

Exit criteria

D.

High-level requirements

Full Access
Question # 12

While preparing the project management plan on a weekly basis, the project manager indicates the intention to provide an issues report to the staff via e-mail. In which part of the plan will this type of information be included?

A.

Communications management plan

B.

Human resource plan

C.

Quality management plan

D.

Procurement management plan

Full Access
Question # 13

Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?

A.

Identify Risks

B.

Perform Qualitative Risk Analysis

C.

Plan Risk Management

D.

Perform Quantitative Risk Analysis

Full Access
Question # 14

The precedence diagramming method (PDM) is also known as:

A.

Arrow Diagram.

B.

Critical Path Methodology (CPM).

C.

Activity-On-Node (AON).

D.

schedule network diagram.

Full Access
Question # 15

Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:

A.

project documents updates.

B.

project management plan updates.

C.

change requests.

D.

work performance information.

Full Access
Question # 16

What does leadership involve?

A.

Working with others through discussion or debate to guide them from one point to another

B.

Directing another person from one point to another using a known set of expected behaviors

C.

Working with a person using expert judgment to develop the technical deliverables

D.

Directing another person to develop the necessary expertise to establish technical deliverables

Full Access
Question # 17

Which risk management strategy seeks to eliminate the uncertainty associated with a particular upside risk by ensuring that the opportunity is realized?

A.

Enhance

B.

Share

C.

Exploit

D.

Accept

Full Access
Question # 18

A project team conducts regular standup meetings to keep everyone updated on what each one of them is working on. What type of communication is this?

A.

Informal

B.

Unofficial

C.

Formal

D.

Hierarchical

Full Access
Question # 19

A project manager is experiencing a project with a high degree of change. Which type of stakeholder engagement does this project require?

A.

Discussing with management

B.

Escalating to the sponsors

C.

Engaging regularly with stakeholders

D.

Engaging only with decision makers

Full Access
Question # 20

Two resources are performing a peer review of an artifact. What should be the outcome of the peer review?

A.

All business rules and data requirements for each process are documented.

B.

All relevant business rules for each process are documented.

C.

The resulting documentation adheres to established organizational standards.

D.

The data requirements for each process are documented.

Full Access
Question # 21

Which of the following documents ate created as part of Project Integration Management?

A.

Project charter and project management plan

B.

Communications management plan and scope management plan

C.

Quality management plan and risk management plan

D.

Project scope statement and communications management plan

Full Access
Question # 22

Which process develops options and actions to enhance opportunities and reduce threats to project objectives?

A.

Identify Risks

B.

Control Risks

C.

Plan Risk Management

D.

Plan Risk Responses

Full Access
Question # 23

Given the following information.

Activity A takes one week.

Activity B takes three weeks.

Activity C takes two weeks.

Activity D takes five weeks.

Activity A starts at the same time as Activity B.

Activity C follows Activity B and Activity A.

Activity D follows Activity C.

How long will it take to complete the project?

A.

Eleven weeks

B.

Nine weeks

C.

Eight weeks

D.

Ten weeks

Full Access
Question # 24

Which tasks should a project manager accomplish in order to manage project scope correctly?

A.

Define. Validate, and Control Scope. Control Schedule; Control Costs and Manage Stakeholder Engagement

B.

Collect Requirements. Define Scope. Create WBS. Develop Schedule, and Manage Stakeholder Engagement

C.

Plan Scope Management; Collect Requirements; Define. Validate, and Control Scope; and Create WBS

D.

Define. Validate, and Control Scope. Control Costs. Manage Stakeholder Engagement, and keep budget under control

Full Access
Question # 25

In what type of organizational structure does a project manager develop their role and work with a team assigned by job function?

A.

Matrix - strong

B.

Matrix - balanced

C.

Virtual

D.

Functional

Full Access
Question # 26

The Identify Stakeholders process is found in which Process Group?

A.

Initiating

B.

Monitoring and Controlling

C.

Planning

D.

Executing

Full Access
Question # 27

A project manager is calculating the current budget. The earned value (EV) of the project is lower than the actual cost (AC) of the project.

How should the project manager report the status of the project?

A.

The project is at risk as the cost variance (CV) is negative.

B.

The project is within budget and within schedule.

C.

The project is within budget but is delayed.

D.

The project is tracking well as the cost variance (CV) is negative.

Full Access
Question # 28

One of the tools and techniques of the Manage Project Team process is:

A.

organization charts.

B.

ground rules.

C.

organizational theory,

D.

conflict management.

Full Access
Question # 29

Match the project life cycle type with its corresponding definition.

Question # 29

Full Access
Question # 30

Which project management process is used by the project manager to ensure that stakeholders receive timely and relevant information?

A.

lan Communications Management

B.

Manage Communications

C.

Monitor Communications

D.

Develop Project Management Plan

Full Access
Question # 31

What can the cost management plan be established?

A.

Cost baseline

B.

Cost estimates

C.

Basis of estimates

D.

Control thresholds

Full Access
Question # 32

The project management processes are usually presented as discrete processes with defined interfaces, while in practice they:

A.

operate separately.

B.

move together in batches,

C.

overlap and interact.

D.

move in a sequence.

Full Access
Question # 33

A project manager read the initial contract when a project was started. The contract states a house has to be built in one year, and the foundation has to be completed in 30 days. What should the project manager do?

A.

Add the milestones to the risk register, as time is short.

B.

Add the two milestones to the project plan, as they are mandatory.

C.

Calculate the duration of the two milestones stated in the contract.

D.

Start the project as soon as possible, as time is short.

Full Access
Question # 34

A project manager is preparing to meet with three crucial project stakeholders on a new project Which tools and techniques can the project manager use to capture stakeholder interest?

A.

Review stakeholder register and meeting

B.

Data analysis and communication skills

C.

Data gathering and data analysis

D.

Communication skills and cultural awareness

Full Access
Question # 35

Which is an aspect of the requirements management plan?

A.

Detailed project scope statement

B.

Creation of work breakdown strucure (WBS)

C.

Impact analysis

D.

Duration for implementation

Full Access
Question # 36

Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?

A.

Reserve analysis

B.

Three-point estimating

C.

Parametric estimating

D.

Analogous estimating

Full Access
Question # 37

An output of the Direct and Manage Project Work process is:

A.

Deliverables.

B.

Activity lists.

C.

A work breakdown structure.

D.

A scope statement.

Full Access
Question # 38

Which project performance domain is the work breakdown structure (WBS) developed?

A.

Development approach and life cycle

B.

Delivery performance

C.

Project work

D.

Planning

Full Access
Question # 39

Which action should a project manager take to ensure that the project management plan is effective and current?

A.

Conduct periodic project performance reviews.

B.

Identify quality project standards.

C.

Follow ISO 9000 quality standards.

D.

Complete the quality control checklist.

Full Access
Question # 40

Which of the following is an information gathering technique in Identify Risks?

A.

Influence diagrams

B.

Brainstorming

C.

Assumption analysis

D.

SWOT analysis

Full Access
Question # 41

In agile projects while performing scope management. What is the definition of requirements

A.

Metrics

B.

Sprint

C.

Charter

D.

Backlog i

Full Access
Question # 42

During project selection, which factor is most important?

A.

Types of constraints

B.

Internal business needs

C.

Budget

D.

Schedule

Full Access
Question # 43

Which process should be conducted from the project inception through completion?

A.

Monitor and Control Project Work

B.

Perform Quality Control

C.

Perform Integrated Change Control

D.

Monitor and Control Risks

Full Access
Question # 44

In a large organization, with projects of different types and sizes, what kind of approach or method would be best to use?

A.

Predictive

B.

Adaptive

C.

A mix

D.

Agile

Full Access
Question # 45

An important project stakeholder has low risk tolerance. Which type ot communication should a project manager use to provide this stakeholder with a difficult update?

A.

Informal conversation

B.

Face-to-face meeting

C.

Short email update

D.

Written report

Full Access
Question # 46

Which input to the Plan Risk Management process provides information on high-level risks?

A.

Project charter

B.

Enterprise environmental factors

C.

Stakeholder register

D.

Organizational process assets

Full Access
Question # 47

What is the primary purpose of Project Scope Management?

A.

Determining and managing stakeholder needs

B.

Contorting the status of the product scope and managing changes to its be seine

C.

Defining and controlling what is and is not included in the project

D.

Differentiating between the product scope and project scope

Full Access
Question # 48

A new game development process must have three versions. Each version is to be developed in approximately five iteration cycles with a duration of one month each. This will help this small enterprise to have a return on investment (ROI) as the project runs from the first cycle. Which methodology should the project manager adopt and implement in the project?

A.

Feature-driven development (FDD) as it will deliver product segments and the milestones are controlled by the development manager.

B.

Kanban as it will provide flexibility to the team for working at their own pace in the time frame requested.

C.

Scrum as it uses sprints and retrospectives, maximizing time delivery and the value of the product.

D.

Extreme Programming (XP) as it will help deliver more quickly since developers will work in pairs.

Full Access
Question # 49

A team is working on a project using an adaptive approach. During project execution, the project gets delayed by one month due to an unforeseen risk. What should the team do next to deliver this project?

A.

Stop working on the project completely, even if the team can continue working on the tasks with the identified risk.

B.

Accept the project delay and add the risk to the lessons learned document for the next project.

C.

Change the delivery date and deliver the initially agreed-upon scope after mitigation of the identified risk.

D.

Reprioritize the work based on the increased visibility of the current risks.

Full Access
Question # 50

Once the make-or-buy analysis is completed, which document defines the project delivery method?

A.

Procurement statement of work (SOW)

B.

Procurement strategy

C.

Terms of reference

D.

Change request

Full Access
Question # 51

What statement describes the function or responsibility of a project manager?

A.

Works with the sponsor to address internal political and strategic issues that may impact the team

B.

Seeks ways to develop relationships that assist the team in achieving organizational goals and objectives

C.

Ensures that the project ' s business operations are efficient

D.

Provides management oversight for a project’s functional or business units

Full Access
Question # 52

What is the primary benefit of meeting quality requirements?

A.

Quality metrics

B.

Less rework

C.

Quality control measurements

D.

Benchmarking

Full Access
Question # 53

A project team is working on relocating offices to another building and providing new furniture. The new furniture was purchased from an international vendor. The price was negotiated in a foreign currency, and due to changes in the exchange rate, the cost has increased by 10%. There is no contingency in the project budget. What should the project manager do?

A.

Escalate this issue to the project management office (PMO).

B.

Escalate this issue to the chief financial officer (CFO).

C.

Escalate this issue to the procurement team.

D.

Escalate this issue to the project sponsor.

Full Access
Question # 54

Which three techniques can be estimate costs?

A.

Financing, bottom-up estimating, and expert judgment

B.

Cost aggregation, analogous estimating, and financing

C.

Expert judgment, financing, and cost aggregation

D.

Expert judgment, analogous estimating, and bottom-up estimating

Full Access
Question # 55

During what project management process does the project team begin identifying risks?

A.

Initiating

B.

Planning

C.

Executing

D.

Monitoring and Controlling

Full Access
Question # 56

Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project:

A.

manager.

B.

success.

C.

deadline.

D.

scope.

Full Access
Question # 57

A project team of telecommuters located in three different time zones regularly misses project deadlines Daily meetings often start and end with the same person talking and the rest of the team listening The project manager determines that communication among team members must be addressed.

What communication step is missing from the daily meetings?

A.

Interpersonal communication

B.

Feedback response communication

C.

Push communication

D.

Pull communication

Full Access
Question # 58

Deciding the phases of a project life cycle would be considered a part of which of these knowledge areas?

A.

Project Schedule Management

B.

Project Scope Management

C.

Project Resource Management

D.

Project Integration Management

Full Access
Question # 59

What process is included in Project Integration Management?

A.

Monitor and Control Project Work

B.

Control Scope

C.

Control Schedule

D.

Develop Team

Full Access
Question # 60

In the Plan Stakeholder Management process, expert judgment is used to:

A.

Provide information needed to plan appropriate ways to engage project stakeholders.

B.

Ensure comprehensive identification and listing of new stakeholders.

C.

Analyze the information needed to develop the project scope statement.

D.

Decide the level of engagement of the stakeholders at each required stage.

Full Access
Question # 61

A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?

A.

Cost-reimbursable

B.

Time and material

C.

Fixed price or lump-sum

D.

Cost-plus-fixed-fee

Full Access
Question # 62

For what project management process is work performance information an output?

A.

Implement Risk Responses

B.

Plan Stakeholder Engagement

C.

Monitor Stakeholder Engagement

D.

Plan Quality Management

Full Access
Question # 63

A project manager has recently been assigned a new agile project and needs to determine an appropriate leadership style. The project manager aims to empower the team members so they feel committed and motivated to deliver value.

Which leadership style should be used for this project?

A.

A servant leadership style

B.

A laissez-faire leadership style

C.

A collaborative leadership style

D.

A directive leadership style

Full Access
Question # 64

Which tool within the Perform Quality Control process identifies whether or not a process has a predictable performance?

A.

Cause and effect diagram

B.

Control charts

C.

Pareto chart

D.

Histogram

Full Access
Question # 65

In a functional organization, the director of an important stakeholder business group expressed concern to a line manager about the progress of the project. What should the line manager do next?

A.

Hold a face-to-face meeting with the project manager and warn them.

B.

Point the director to a link where they can take a look at the reports.

C.

Invite stakeholders to attend monthly progress review meetings.

D.

Ask the project manager to update the monthly status report distribution list.

Full Access
Question # 66

Which of the following is a category of organizational process assets?

A.

Government standards

B.

Organizational culture

C.

Employee capabilities

D.

Organizational knowledge bases

Full Access
Question # 67

The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as:

A.

exploit

B.

avoid

C.

mitigate

D.

share

Full Access
Question # 68

Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations?

A.

Mandatory

B.

Discretionary

C.

Internal

D.

External

Full Access
Question # 69

Outputs of the Control Communications process include:

A.

expert judgment and change requests

B.

work performance information and change requests

C.

project management plan updates and work performance information

D.

issue logs and organizational process assets updates

Full Access
Question # 70

Taking out insurance in relation to risk management is called what?

A.

Transference

B.

Avoidance

C.

Exploring

D.

Mitigation

Full Access
Question # 71

Risk responses reflect an organization ' s perceived balance between:

A.

risk taking and risk avoidance.

B.

known risk and unknown risk.

C.

identified risk and analyzed risk.

D.

varying degrees of risk.

Full Access
Question # 72

The following is a network diagram for a project.

Question # 72

The shortest non-critical path for the project is how many days in duration?

A.

10

B.

12

C.

14

D.

16

Full Access
Question # 73

A project manager needs information to finish their work on the project charter for a clinical trial.

Which procedure is used to obtain the requirements information?

A.

Forecasting

B.

Simulations

C.

Elicitation

D.

Quantitative analysis

Full Access
Question # 74

What does expert judgment provide as an input to the resource management plan?

A.

Geographic distribution of facilities and resources

B.

Physical resource management policies and procedures

C.

Estimated lead times based on lessons learned

D.

Templates for the resource management plan

Full Access
Question # 75

A project using the agile/adaptive approach has reached the Project Integration Management phase. What is the project manager ' s key responsibility during this phase?

A.

Defining the scope of the project

B.

Building a collaborative environment

C.

Creating a detailed project management plan

D.

Directing the delivery of the project

Full Access
Question # 76

A project manager Is addressing risks and potential concerns related to stakeholder management, and Is clarifying and resolving previously Identified issues. In which process is the project manager engaged?

A.

Identify Stakeholders

B.

Plan Stakeholder Engagement

C.

Manage Stakeholder Engagement

D.

Monitor Slakeholder Engagement

Full Access
Question # 77

What document gathers all of the lessons learned at the end of a phase or project

A.

Lessons learned register

B.

Lessons learned list

C.

Lessons learned project asset

D.

Lessons learned repository

Full Access
Question # 78

Which Process Group and Knowledge Area include the Sequence Activities process?

A.

Executing Process Group and Project Time Management

B.

Executing Process Group and Project Cost Management

C.

Planning Process Group and Project Time Management

D.

Planning Process Group and Project Cost Management

Full Access
Question # 79

Which set of activities should a project manager use as part of the Develop Team process?

A.

Training and establishing ground rules

B.

Networking activities and estimating team resources

C.

Conflict management activities and tracking team performance

D.

Recruit new team members and training

Full Access
Question # 80

Which risk response strategy is common for both positive and negative risks?

A.

Share

B.

Accept

C.

Mitigate

D.

Transfer

Full Access
Question # 81

Whose approval may be required for change requests after change control board (CCB) approval?

A.

Functional managers

B.

Business partners

C.

Customers or sponsors

D.

Subject matter experts

Full Access
Question # 82

Which of the following techniques should a project manager of a large project with virtual teams use to enhance collaboration?

A.

Resource breakdown structure

B.

Physical resources assignment

C.

Team building activities

D.

Integrated Change Control

Full Access
Question # 83

The definition of operations is a/an:

A.

organizational function performing the temporary execution of activities that produce the same product or provide repetitive service.

B.

temporary endeavor undertaken to create a unique product, service, or result.

C.

organization that provides oversight for an administrative area.

D.

organizational function performing the ongoing execution of activities that produce the same product or provide repetitive service.

Full Access
Question # 84

In project management, a temporary project can be:

A.

Completed without planning

B.

A routine business process

C.

Long in duration

D.

Ongoing to produce goods

Full Access
Question # 85

What tools or techniques are necessary to create the project management plan?

A.

Meetings and data analysis

B.

Expert judgment and data gathering

C.

Interpersonal skills and change control

D.

Data analysis and expert judgment

Full Access
Question # 86

A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:

A.

risk management plan

B.

human resource management plan

C.

scope management plan

D.

procurement management plan

Full Access
Question # 87

A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?

A.

Slack

B.

Float

C.

Lag

D.

Lead

Full Access
Question # 88

Reserve analysis is a tool and technique used in which process?

A.

Plan Risk Management

B.

Plan Risk Responses

C.

Identify Risks

D.

Control Risks

Full Access
Question # 89

The project manager is looking at a precedence diagram.... the duration of this task?

The project manager is looking at a precedence diagram and needs to report back about the project status The total duration of the task is ten days, and both Activity A and B need be completed. Activity A has a duration of six days, and activity B has a duration of four days Activity B has a finish-to-start relationship with activity A Under current circumstances, activity A will take about seven days to complete.

What is the outcome of the duration of this task ' ?

A.

The task will be completed on time.

B.

The task will not be completed on time.

C.

Activity A is not a critical path task

D.

The precedence diagram cannot be used to provide answers for duration calculations

Full Access
Question # 90

Which additional considerations should the project manager make when managing risks in an agile/adaptive project?

A.

Add more risk categories

B.

Identify, analyze, and manage risk during each iteration of the project

C.

Add new values to the probability and impact matrix

D.

Increase the reserves because of the high variability environment

Full Access
Question # 91

Which of the following is an output of the Perform Integrated Change Control process?

A.

Cost-benefit analysis

B.

Updated project charter

C.

Approved change request

D.

Multicriteria decision analysis

Full Access
Question # 92

A project team has completed the first iteration and the testing manager approved the test report, indicating that the acceptance criteria have been met. The manager of the business unit that will use the new product is asking for additional functionality before approving the rollout for their team.

What should the project manager do next?

A.

Escalate this issue to the project sponsor.

B.

Reschedule the rollout to start with another business unit.

C.

Reschedule the rollout to include the new requirements.

D.

Escalate this issue to the project management office (PMO).

Full Access
Question # 93

An employee was hired to work on ongoing, repetitive activities in the accounting department. The employee ' s duties are managing and controlling day-to-day activities. Which type of managing is the employee performing?

A.

Strategic

B.

Finance

C.

Project

D.

Operations

Full Access
Question # 94

A program consists of four agile teams. Each team has a separate daily standup. Later each day, there is another standup meeting attended by one member from each team.

Which Scrum technique is this?

A.

Scaled Agile Framework (SAFe®)

B.

Disciplined Agile® (DA™)

C.

Large Scale Scrum (LeSS)

D.

Scrum of Scrums

Full Access
Question # 95

Which of the following can a project manager conduct if they have a stakeholder who is unresponsive and/or unsupportive?

A.

Interactive communications

B.

Pull communications

C.

Push communications

D.

Communication style assessment

Full Access
Question # 96

A project manager is reviewing a past project with similar.... team choosing for tailoring?

A project manager is reviewing a past project with similar requirements to the project that is currently chartered. The project team decided to adopt quality tools, techniques and templates recommended at the organizational level after reviewing the lessons learned of the previous project What specific area of quality, is the project team choosing for tailoring?

A.

Policy compliance and auditing

B.

Standards and compliance

C.

Review of lessons learned

D.

Test and inspection planning

Full Access
Question # 97

Considering a highly dynamic project environment, which approach should the project manager adopt to manage the project team?

A.

A self-organizing approach to increase team focus and maximize collaboration

B.

A virtual team to minimize feeling of isolation and gaps on sharing knowledge

C.

A distributed team to improve tracking progress, productivity, and performance

D.

A norming approach that requires team members to adjust their behavior and work together

Full Access
Question # 98

Which statement correctly describes the value of a business case?

A.

It provides the necessary information to determine if a project is worth the required investment.

B.

It provides for alternative dispute resolution procedures in event of contract default.

C.

It offers one of several alternative scenarios which assist in performing qualitative risk analysis.

D.

It is used to help a project manager understand the scope of commercial advantages.

Full Access
Question # 99

A project team is evaluating criteria to determine project viability. Which of these activities will provide insight into making a go/no-go decision to start the project?

A.

Cost of quality (COQ)

B.

Lessons learned

C.

Cost-benefit analysis

D.

Benchmarking

Full Access
Question # 100

A special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables is called a:

A.

triangular distribution

B.

tornado diagram

C.

beta distribution

D.

fishbone diagram

Full Access
Question # 101

What can the project manager find among the factors that could lead a project to be tailored

A.

Company Culture

B.

Return on investment

C.

Earned Value

D.

Schedule Performance Index

Full Access
Question # 102

Which of the following can be used as an input for Define Scope?

A.

Product analysis

B.

Project charter

C.

Scope baseline

D.

Project scope statement

Full Access
Question # 103

Which of the following documents allows the project manager to assess risks that may require near term action?

A.

Probability and impact matrix

B.

Contingency analysis report

C.

Risk urgency assessment

D.

Rolling wave plan

Full Access
Question # 104

Change requests, project management plan updates, project document updates, and organizational process assets updates are all outputs of which project management process?

A.

Plan Risk Responses

B.

Manage Stakeholder Expectations

C.

Define Scope

D.

Report Performance

Full Access
Question # 105

What can a project1 manager review to understand the status of project?

A.

Work breakdown structure (WBS) status

B.

Quality and technical performance measures

C.

Cost and scope baselines

D.

Business case completeness

Full Access
Question # 106

Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?

A.

Organizational process updates

B.

Quality metrics

C.

Change requests

D.

Quality control measurements

Full Access
Question # 107

The individual or group that provides resources and support for a project and is accountable for success is the:

A.

sponsor

B.

customer

C.

business partners

D.

functional managers

Full Access
Question # 108

A project manager held a meeting and listed all team members ' ideas for improving the product on a white board. What data gathering technique did the project manager apply?

A.

Focus groups

B.

Interviews

C.

Brainstorming

D.

Delphi technique

Full Access
Question # 109

What is the definition of Direct and Manage Project Execution?

A.

Integrating all planned activities

B.

Performing the activities included in the plan

C.

Developing and maintaining the plan

D.

Execution of deliverables

Full Access
Question # 110

During a kickoff meeting, the project sponsor presents a very ambitious project. Unfortunately, the stakeholders are not very excited as the work associated with the new project seems inefficient.

What could be missing from the business case?

A.

Work breakdown structure (WBS)

B.

Approval from the stakeholders

C.

Feasibility study of the solution

D.

Root cause analysis of the problem

Full Access
Question # 111

An input to the Plan Procurement Management process is:

A.

Source selection criteria.

B.

Market research.

C.

A stakeholder register.

D.

A records management system.

Full Access
Question # 112

Who should the stakeholders consult to discuss concerns about the current work package?

A.

Project manager

B.

Business analyst

C.

Project coordinator

D.

Project sponsor

Full Access
Question # 113

Stakeholder identification and engagement should begin during what phase of the project?

A.

After the project management plan is completed

B.

After the stakeholder engagement plan is completed

C.

As soon as the project charter has been approved

D.

After the communications management plan is completed

Full Access
Question # 114

What is the equation to calculate cost variance (CV)?

A.

CV = EV / BAC

B.

CV = EV - AC

C.

CV = EV - BAC

D.

CV = EV / AC

Full Access
Question # 115

What should be the frequency for meetings when transitioning from Scrum to Kanban?

A.

Weekly

B.

Daily

C.

When required

D.

Monthly

Full Access
Question # 116

Which type of project management office (PMO) supplies templates, best practices, and training to project teams?

A.

Supportive

B.

Directive

C.

Controlling

D.

Instructive

Full Access
Question # 117

Which is a major component of an agreement?

A.

Change request handling

B.

Risk register templates

C.

Lessons learned register

D.

Procurement management plan

Full Access
Question # 118

Which estimating technique uses the actual costs of previous similar projects as a basis for estimating the costs of the current project?

A.

Analogous

B.

Parametric

C.

Bottom-up

D.

Top-down

Full Access
Question # 119

The project manager and the project team are having a meeting with the purpose of identifying risks. Which tools and techniques might help in this process?

A.

Prompt lists and data analysis

B.

Reports and representations of uncertainty

C.

Data analysis and risk audits

D.

Interpersonal and team skills and project management Information system

Full Access
Question # 120

A construction project is underway, and during... tasks impacted the painting work

A construction project is underway, and during the progress review the painter complained that the task could not be started because the mason has not finished the plastering job What kind ot relationship between the tasks impacted the painting work?

A.

Finish-to-Finish (FF)

B.

Start-to-Finish (SF)

C.

Finish-to-Start(FS)

D.

Start-to-Slart(SS)

Full Access
Question # 121

An output of the Plan Quality Management process is:

A.

A process improvement plan,

B.

Quality control measurements.

C.

Work performance information,

D.

The project management plan.

Full Access
Question # 122

A project manager is updating their CV or resume and realizes that they need to improve skills related to expertise in the industry and organizational knowledge. Which dimension of PMI’s Talent Triangle best relates to this need to improve?

A.

Strategic and business management skills

B.

Leadership skills

C.

Technical project management

D.

Organizational management

Full Access
Question # 123

A project sponsor has asked the project manager to determine how soon the project can be completed. Which of the following methods can a project manager use to find this information?

A.

Scope baseline

B.

Decomposition

C.

Critical path method (CPM)

D.

Work breakdown structure (WBS)

Full Access
Question # 124

A project manager is reviewing some techniques that can be used to evaluate solution results. The intent is to determine if the solution provides the functionality for typical usage by a stakeholder with in-depth business knowledge.

Which evaluation technique is most effective for this situation?

A.

Day-in-the-life testing

B.

Exploratory testing

C.

User acceptance testing

D.

Integration testing

Full Access
Question # 125

A company is moving from a predictive to an adaptive approach. How should the company now translate the already planned work breakdown structure (WBS) to adaptive iterations?

A.

Create a product backlog with the information depicted in the WBS and prioritize the newly developed user stories into iterations.

B.

Accept this limitation and perform accordingly since the WBS can only be used in Scrum iterations.

C.

Consider reforming the structure of the company first as it is difficult for a company to transition from predictive to adaptive methods.

D.

Save the WBS in the historical data as the information can only be used for educational purposes and not as inputs for creating user stories.

Full Access
Question # 126

A large portion of a projects budget is typically expended on the processes in which Process Group?

A.

Executing

B.

Planning

C.

Monitoring and Controlling

D.

Closing

Full Access
Question # 127

Projects are separated into phases or subprojects; these phases include:

A.

feasibility study, concept development, design, and prototype.

B.

initiate, plan, execute, and monitor.

C.

Develop Charter, Define Activities, Manage Stakeholder Expectations, and Report Performance.

D.

Identify Stakeholders, develop concept, build, and test.

Full Access
Question # 128

What tool or technique is primarily used to plan risk responses ' ?

A.

Risk categorization

B.

Project risk document updates

C.

Strategies for overall project risk

D.

Risk management plan

Full Access
Question # 129

In which domain of project management would a Pareto chart provide useful information?

A.

Project Scope Management

B.

Project Time Management

C.

Project Communications Management

D.

Project Quality Management

Full Access
Question # 130

A project manager is launching an information system to provide a lessons learned database. This action is necessary for recipients to access content at their own discretion. Which communication method is described?

A.

Push communication

B.

Pull communication

C.

Interactive communication

D.

Stakeholder communication

Full Access
Question # 131

Which process involves determining, documenting, and managing stakeholders ' needs and requirements to meet project objectives?

A.

Collect Requirements

B.

Plan Scope Management

C.

Define Scope

D.

Define Activities

Full Access
Question # 132

Which quality management and control tool is useful in visualizing parent-to-child relationships in any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship?

A.

Interrelationship digraphs

B.

Tree diagram

C.

Affinity diagram

D.

Network diagram

Full Access
Question # 133

The creation of an internet site to engage stakeholders on a project is an example of which type of communication?

A.

Push

B.

Pull

C.

Interactive

D.

Iterative

Full Access
Question # 134

What is an example of an emerging trend in procurement management?

A.

Online technology enable projects to postpone ordering long lead items until the items are needed

B.

Online technologies allow a project ' s progress to be viewed by all stakeholders to build better relations

C.

Online procurement tools provide buyers with multiple sources to advertise to sellers.

D.

Online procurement tools provide sellers with designated sources for procurement documents and the resources to complete them.

Full Access
Question # 135

Which of the following best correspond to the organizational process assets (OPAs) that affect the project?

A.

Policies and lessons learned from other projects

B.

Information technology software and employee capability

C.

Resource availability and employee capability

D.

Marketplace conditions and legal restrictions

Full Access
Question # 136

Which process determines the risks that may affect the project and documents their characteristics?

A.

Control Risks

B.

Plan Risk Management

C.

Plan Risk Responses

D.

Identify Risks

Full Access
Question # 137

The application of knowledge, skills, tools, and techniques to project activities to meet project requirements describes management of which of the following?

A.

Project

B.

Scope

C.

Contract

D.

Program

Full Access
Question # 138

A project manager is working with the team to prepare the estimates for various work items. The team needs to compare the relative sizing of the items. What should the project manager suggest the team use?

A.

Project task estimation

B.

Dependency planning

C.

Story point estimation

D.

Sprint planning

Full Access
Question # 139

The component of the risk management plan that documents how risk activities will be recorded is called:

A.

tracking

B.

scoping

C.

timing

D.

defining

Full Access
Question # 140

What benefit does the Manage Stakeholder Engagement process offer?

A.

Allows the project manager to increase support and minimize resistance from stakeholders

B.

Maintains or increases the efficiency and effectiveness of stakeholder engagement activities as the project evolves and its environment changes

C.

Provides an actionable plan to interact effectively with stakeholders

D.

Enables the project team to identify the appropriate focus for engagement of each stakeholder or group of stakeholders

Full Access
Question # 141

Which type of graphic is displayed below?

Question # 141

A.

Work breakdown structure

B.

Context diagram

C.

Control chart

D.

Pareto diagram

Full Access
Question # 142

A collection of projects managed as a group to achieve strategic objectives is referred to as a:

A.

plan

B.

process

C.

program

D.

portfolio

Full Access
Question # 143

Conditions that are not under the control of the project team that influence, direct, or constrain a project are called:

A.

Enterprise environmental factors

B.

Work performance reports

C.

Organizational process assets

D.

Context diagrams

Full Access
Question # 144

How many Project Management Process Groups are there?

A.

3

B.

4

C.

5

D.

6

Full Access
Question # 145

What is an output of the plan resource management process

A.

Project charter

B.

Risk register

C.

Scope baseline

D.

Stakeholder register

Full Access
Question # 146

The following is a network diagram for a project.

Question # 146

What is the critical path for the project?

A.

A-B-C-F-G-I

B.

A-B-C-F-H-I

C.

A-D-E-F-G-I

D.

A-D-E-F-H-I

Full Access
Question # 147

On a clinical trial project, the project manager is worried about maintaining control of the project. The project manager decides to use a requirements traceability matrix.

What is the advantage of using this tool?

A.

Scope creep will be prevented.

B.

Resource allocation will be kept to a minimum.

C.

Project closure will be established.

D.

Project costs will be controlled.

Full Access
Question # 148

In which process is a project manager identified and given the authority to apply resources to project activities?

A.

Acquire Project Team

B.

Develop Project Management Plan

C.

Manage Project Execution

D.

Develop Project Charter

Full Access
Question # 149

In the project charter process, which three of the following are discussed during meetings held with stakeholders? (Choose three) D Cost

A.

High-level deliverables

B.

Success criteria

C.

Project objectives

D.

Phase transitions

Full Access
Question # 150

The technique of subdividing project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level is called:

A.

a control chart.

B.

baseline.

C.

Create WBS.

D.

decomposition.

Full Access
Question # 151

The table represents the possible durations of a specific project task.

Using the three-point estimating technique what is the expected number of days it should take to complete the task?

A.

2

B.

3

C.

4

D.

6

Full Access
Question # 152

After winning a large government contract, a company needs to hire a portfolio manager What vital qualification should candidates possess?

A.

Ability to manage strategic goals across multiple projects

B.

Skills to manage a large project

C.

Competency to manage multiple projects that align departments

D.

Capability of managing project schedules

Full Access
Question # 153

Which Perform Quality Control tool graphically represents how various elements of a system interrelate?

A.

Control chart

B.

Flowchart

C.

Run chart

D.

Pareto chart

Full Access
Question # 154

Which method should be used to elicit a cross-functional requirement?

A.

Focus groups

B.

Prototyping

C.

Facilitated workshops

D.

Interviews

Full Access
Question # 155

What are the project management processes associated with project quantity management?

A.

Plan Quality Management, Manage Quality, and Control Quality

B.

Plan Quality Management, Manage Quality, and Cost of Quality

C.

Manage Quality, Customer Satisfaction, and Control Quality

D.

Customer Satisfaction, Control Quality, and Continuous Improvement

Full Access
Question # 156

Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area?

A.

Project Time Management

B.

Project Cost Management

C.

Project Scope Management

D.

Project Human Resource Management

Full Access
Question # 157

High-level project risks are included in which document?

A.

Business case

B.

Risk breakdown structure

C.

Project charter

D.

Risk register

Full Access
Question # 158

An organization that is being interviewed online has recently experienced a severe network outage. Consequently, the organization has stated that it is required to have a working data network.

Which classification should be assigned to data network requirements?

A.

Customer requirement

B.

Transition requirement

C.

Solution requirement

D.

Business requirement

Full Access
Question # 159

When can we say that a project is completed?

A.

When the planned time duration is completed

B.

When the project objectives have been reached

C.

When the project manager has left the team

D.

When the project team decides to stop the work on the project

Full Access
Question # 160

What is the best tool to calculate the critical path on a project?

A.

Critical chain method

B.

Graphical evaluation and review technique (GERT) diagram

C.

Gantt chart

D.

Project network diagram

Full Access
Question # 161

Which tools and techniques will a project manager use to develop a project charter?

A.

Project manager experience, expert judgment, scope statement, and meetings

B.

Lessons learned database. Interpersonal and team skills, cost baseline, and meetings

C.

Expert judgment, data gathering. scope statement, schedule baseline, and meetings

D.

Expert judgment, data gathering. interpersonal and team skills, and meetings

Full Access
Question # 162

It you established a contingency reserve including time, money, and resources, how are you handling risk?

A.

Accepting

B.

Transferring

C.

Avoiding

D.

Mitigating

Full Access
Question # 163

Which is a list of organizational systems that may have an impact on a project?

A.

Internal policies, company procedures, and organizational resources

B.

Company culture, purchasing system, and project management information system

C.

Organizational structure, governance framework, and management elements

D.

Organizational process assets, enterprise environmental factors, and corporate knowledge

Full Access
Question # 164

The project manager is working with some functional managers and stakeholders on the resource management plan Which elements may be included in this plan?

A.

Team values, team agreements, and conflict resolution process

B.

Conflict resolution process, communication guidelines, and meeting schedules

C.

Team roles and responsibilities, team management, and training plan

D.

Resource requirements, resource assignments, and team performance assessments

Full Access
Question # 165

Which of the following is used as input to prepare a cost management plan?

A.

Expert judgment

B.

Lessons learned

C.

Cost estimates

D.

Project management plan

Full Access
Question # 166

Which of the following project documents is an input to the Control Scope process?

A.

Vendor risk assessment diagram

B.

Risk register

C.

Requirements traceability matrix

D.

Area of responsibility summary

Full Access
Question # 167

A project manager has a project schedule baseline. How can the critical path be determined from the finalized schedule?

A.

Identify the crashed project schedule to find the shortest duration to complete the project.

B.

Identify the longest activity path in the schedule with the shortest possible duration.

C.

Identify the tasks with float duration, which do not impact the duration of the project.

D.

Identify the path through the schedule with leveled resources and the shortest duration.

Full Access
Question # 168

Which process requires implementation of approved changes?

A.

Direct and Manage Project Execution

B.

Monitor and Control Project Work

C.

Perform Integrated Change Control

D.

Close Project or Phase

Full Access
Question # 169

Which output of Project Cost Management consists of quantitative assessments of the probable costs required to complete project work?

A.

Activity cost estimates

B.

Earned value management

C.

Cost management plan

D.

Cost baseline

Full Access
Question # 170

A project manager is performing a specific process and has..........is being referred to?

A project manager is performing a specific process and has a list of accepted deliverables One of the stakeholders points out that they have just reviewed the verified deliverables, and come up with the list of accepted deliverables Which process is being referred to?

A.

Control Quality

B.

Validate Scope

C.

Validate Quality

D.

Control Scope

Full Access
Question # 171

An issue log is an input to which Project Human Resource Management process?

A.

Manage Project Team

B.

Acquire Project Team

C.

Plan Human Resource Management

D.

Develop Project Team

Full Access
Question # 172

The probability and impact matrix is primarily used to:

A.

Quantify risk issues for trends during a quality audit.

B.

Develop a risk register for risk planning.

C.

Evaluate each risk’s importance and priority during Perform Qualitative Risk Analysis.

D.

Define risk and compare impacts during Perform Quantitative Risk Analysis.

Full Access
Question # 173

Variance and trend analysis is a tool and technique used in which process?

A.

Perform Qualitative Risk Analysis

B.

Perform Quantitative Risk Analysis

C.

Control Risks

D.

Plan Risk Responses

Full Access
Question # 174

While executing a building construction project, the supplier may delay the delivery and increase the cost of materials due to new safety regulations. The team has identified an option to absorb the cost by reducing the lag for some of the tasks.

What should the team do to ensure that this situation is managed?

A.

Implement Appropriate Response

B.

Plan Project Risk Management

C.

Perform Quantitative Risk Analysis

D.

Perform Qualitative Risk Analysis

Full Access
Question # 175

The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:

A.

Plan Human Resource Management.

B.

Acquire Project Team.

C.

Manage Project Team.

D.

Develop Project Team.

Full Access
Question # 176

Information collected on the status of project activities being performed to accomplish the project work is known as what?

A.

Project management information system

B.

Work performance information

C.

Work breakdown structure

D.

Variance analysis

Full Access
Question # 177

A production support system is being managed by a team. The team members cannot plan their work in advance, even for a week, because they do not know when new support issues will be submitted. The team cannot start working on new issues until they finish existing issues, no matter how long it takes to finish the existing issues.

Which method should be used in this situation?

A.

SAFe®, as it does not allow for scaling work across different teams in the organization.

B.

Extreme Programming (XP), as it does not allow for moving on to new items until the existing items are finished.

C.

Kanban, because the team does not start new work until the existing work is finished.

D.

Scrum, as it allows for completing the whole architecture up front without leaving any technical debt for the future.

Full Access
Question # 178

What important leadership quality/qualities should project managers possess?

A.

Skills and behaviors related to specific domains of project management

B.

Skills and behaviors needed to guide a team and help an organization reach its goals

C.

Industry expertise that helps to better deliver business outcomes

D.

Industry and organizational expertise that enhances performance

Full Access
Question # 179

DRAG DROP

Match the praxes manager ' s sphere of influence with the associated primary role:

Question # 179

Full Access
Question # 180

The zero duration of milestones in project planning occurs because milestones:

A.

Are unpredictable and challenge the Plan Schedule Management process.

B.

Occur at random times in the project plans.

C.

Represent a moment in time such as a significant project point or event.

D.

Represent both significant and insignificant points in the project and are difficult to anticipate.

Full Access
Question # 181

What is the purpose of the project management process groups?

A.

To define a new project

B.

To track and monitor processes easily

C.

To logically group processes to achieve specific project objectives

D.

To link specific process inputs and outputs

Full Access
Question # 182

Which of the following does a portfolio combine?

A.

Projects, programs, and operations

B.

Operations, strategies, and business continuity

C.

Projects, programs, and risks

D.

Projects, change management, and operations

Full Access
Question # 183

During what project management process does the project manager invest the most effort into creating the work breakdown structure (WBS)?

A.

Initiating

B.

Planning

C.

Executing

D.

Monitoring and Controlling

Full Access
Question # 184

Which type of managers do composite organizations involve?

A.

Functional managers and manager of project managers

B.

Functional managers only

C.

Project managers only

D.

Technical managers and project managers

Full Access
Question # 185

The executive committee of a company is reviewing its portfolios. Which of the following would be helpful to evaluate success?

A.

Charter the strategic objectives.

B.

Control environmental changes.

C.

Monitor changes continuously.

D.

Aggregate benefits realization.

Full Access
Question # 186

Which document in the project management plan can be updated in the Plan Procurement Management process?

A.

Budget estimates

B.

Risk matrix

C.

Requirements documentation

D.

Procurement documents

Full Access
Question # 187

The staffing management plan is part of the:

A.

organizational process assets.

B.

resource calendar.

C.

human resource plan.

D.

Develop Project Team process.

Full Access
Question # 188

What is one reason why stakeholders must be identified when performing business analysis?

A.

To identify project timelines through business reviews

B.

To allow the business analyst to determine the project budget

C.

To identify who should define the business requirements for the project

D.

To determine a cost-benefit analysis for the project

Full Access
Question # 189

Which tool is used to develop technical details within the project management plan?

A.

Expert judgment

B.

Project management methodology

C.

Project management information system (PMIS)

D.

Project selection methods

Full Access
Question # 190

How should the project manager obtain the maximum engagement from stakeholders that have recently changed to become more connected to social media?

A.

Adopt co-creation, sharing responsibilities with stakeholders

B.

Adopt participation of stakeholders in main meetings, listening to their opinion.

C.

Adopt social media tools, improving communication with stakeholders

D.

Adopt involvement of stakeholders in lessons learned sessions, sharing experiences with them

Full Access
Question # 191

The project manager is explaining to others the essential business aspects of the project. To which skill category does this ability belong?

A.

Technical project management skills

B.

Time management skills

C.

Strategic and business management skills

D.

Leadership skills

Full Access
Question # 192

What internal enterprise environmental factor (EEF) can impact a project?

A.

Cultural influences

B.

Physical environmental elements

C.

Commercial databases

D.

Infrastructure

Full Access
Question # 193

The Monitoring and Controlling Process Group includes processes that:

A.

Establish the scope, objectives, and course of action of a project,

B.

Define a new project or a new phase of an existing project.

C.

Track, review, and regulate the progress and performance of a project.

D.

Complete the work defined in the project management plan.

Full Access
Question # 194

Which of the following are outputs of the Define Scope process in Project Scope Management?

A.

Requirements documentation and requirements traceability matrix

B.

Scope management plan and requirements management plan

C.

Project scope statement and project documents updates

D.

Scope baseline and project documents updates

Full Access
Question # 195

Which statement describes the various purposes of project scheduling?

A.

Define the policies, rules, and techniques to run a schedule; serve as a tool to manage stakeholder expectations; and serve as a base for backlog management

B.

Define how and when deliverables will be completed, serve as communication tool, and serve as a base for performance reporting

C.

Define the life cycle, traditional or agile approach, and tools to control schedule; serve as a reference for scope management; and serve as a base for risk management

D.

Define activities, sequences, duration, and dependencies, serve as a reference for resource allocation, serve as a base for earned value analysis.

Full Access
Question # 196

A strengths, weaknesses, opportunities, and threats (SWOT) analysis is a tool or technique used in which process?

A.

Identify Risks

B.

Control Risks

C.

Perform Quantitative Risk Analysis

D.

Perform Qualitative Risk Analysis

Full Access
Question # 197

A project manager is performing the procurement management process with three vendors The project team is reviewing the requests for proposal (RFPs).

What type of procurement document is the RFP?

A.

Bid document

B.

Statement of work (SOW)

C.

Source selection criteria

D.

Independent cost estimate

Full Access
Question # 198

A project manager is monitoring and recording results of executing the quality management activities to assess performance and ensure the project outputs are complete, correct, and meet customer expectations. Which output is the project manager using?

A.

Approved change requests

B.

Verified deliverables

C.

Lessons learned

D.

Work performance data

Full Access
Question # 199

A subject matter expert (SME) was recently assigned to a project to manage the new compliance requirement. The SME claimed that the activity ' s prioritization needed to change and the schedule could be cut to mitigate the effect of this new compliance need.

How should the project manager proceed?

A.

Perform Integrated Change Control.

B.

Conduct a risk assessment with the team.

C.

Update the schedule to include compliance.

D.

Manage Stakeholder Engagement.

Full Access
Question # 200

A weighting system is a tool for which area of Conduct Procurements?

A.

Plan contracting

B.

Requesting seller responses

C.

Selecting seller ' s

D.

Planning purchase and acquisition

Full Access
Question # 201

A project manager is reporting the project performance as 25 days worth of work completed against 13 days originally planned. What is the schedule variance (SV)?

A.

-12

B.

1.15

C.

38

D.

12

Full Access
Question # 202

As the project progresses, which of the following is routinely collected from the project activities?

A.

Communication management activities

B.

Change requests

C.

Configuration verification and audit

D.

Work performance information

Full Access
Question # 203

Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?

A.

The risk of achieving the shortened project time is increased.

B.

The critical path will have positive total float.

C.

Contingency reserves are released for redeployment by the project manager.

D.

Duration buffers are added to maintain a focus on planned activity durations.

Full Access
Question # 204

What cost control technique is used to compare actual project performance to planned or expected performance?

A.

Cost aggregation

B.

Trend analysis

C.

Forecasting

D.

Variance analysis

Full Access
Question # 205

Inputs to the Plan Risk Management process include the:

A.

cost management plan.

B.

risk management plan,

C.

activity list,

D.

risk register.

Full Access
Question # 206

A tool or technique in Perform Quality Control that a project manager would use is:

A.

quality audits.

B.

process analysis.

C.

benchmarking.

D.

inspection.

Full Access
Question # 207

Company A’s accountant sends notification about a change in the company’s tax classification.

What would a project have to be initiated?

A.

To change business and technological strategies

B.

To improve processes and services

C.

To meet regulatory and legal requirements

D.

To satisfy stakeholder requests

Full Access
Question # 208

What communication methods would a project manager use for overall effective project communication?

A.

Interactive communication, push communication, interpersonal communication

B.

Interactive communication, push communication, pull communication

C.

Push communication, pull communication, interpersonal communication

D.

Pull communication, interactive communication, interpersonal communication

Full Access
Question # 209

What earned value (EV) measure indicates the cost efficiency of the work completed?

A.

Cost variance (CV)

B.

Cost performance index (CPI)

C.

To-complete performance index (TCPI)

D.

Variance at completion (VAC)

Full Access
Question # 210

A project manager has joined the sponsor to verify the last deliverable of the project. The sponsor is measuring and examining the deliverable to determine whether it meets the requirements and product acceptance criteria. Which activity is being performed?

A.

Inspection

B.

Prototyping

C.

Decision making

D.

Brainstorming

Full Access
Question # 211

Which type of analysis is used as a general management technique within the Plan Procurements process?

A.

Risk assessment analysis

B.

Make or buy analysis

C.

Contract value analysis

D.

Cost impact analysis

Full Access
Question # 212

What organizational asset can influence the Plan Risk Management process?

A.

Corporate policies and procedures for social media, ethics, and security

B.

Organizational risk policy

C.

Stakeholder register templates and instructions

D.

Organizational communication requirements

Full Access
Question # 213

A method of obtaining early feedback on requirements by providing a working model of the expected product before actually building is known as:

A.

Benchmarking.

B.

Context diagrams.

C.

Brainstorming.

D.

Prototyping.

Full Access
Question # 214

Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?

A.

Procurement documents

B.

Communications plan

C.

Project charter

D.

Stakeholder register

Full Access
Question # 215

What method for categorizing stakeholders is suitable for small projects with simple relationships among stakeholders ' ?

A.

Prioritization

B.

Directions of influence

C.

Salience model

D.

Power/influence grid

Full Access
Question # 216

In which type of contract are the performance targets established at the onset and the final contract price determined after completion of all work based on the sellers performance?

A.

Firm-Fixed-Price (FFP)

B.

Fixed Price with Economic Price Adjustments (FP-EPA)

C.

Fixed-Price-Incentive-Fee (FPIF)

D.

Cost Plus Fixed Fee (CPFF)

Full Access
Question # 217

The project has a current cost performance index of 0.80. Assuming this performance wi continue, the new estimate at completion is $1000. What was the original budget at completion for the project?

A.

$800

B.

$1000

C.

$1250

D.

$1800

Full Access
Question # 218

The project manager released a report A few stakeholders express the view that report should

have been directed to them

Which of the 5Cs of written communications does the project manager need to address?

A.

Correct grammar and spelling

B.

Concise expression and elimination of excess words

C.

Clear purpose and expression directed to the needs of the reader

D.

Coherent logical flow of ideas

Full Access
Question # 219

Which of the Perform Quality Assurance tools and techniques may enhance the creation of the work breakdown structure (VVBS) to give structure to the decomposition of the scope?

A.

Activity network diagrams

B.

Affinity diagrams

C.

Matrix diagrams

D.

Interrelationship digraphs

Full Access
Question # 220

Which of the following is a group decision-making technique?

A.

Brainstorming

B.

Focus groups

C.

Affinity diagram

D.

Plurality

Full Access
Question # 221

Which of the following must be included in the risk register when the project manager completes the Identify Risks process?

A.

List of identified risks, potential risk owners, list of potential risk response

B.

List of identified risks, list of causes, list of risk categories

C.

Short risk titles, list of potential risk owners, list of impacts on objectives

D.

List of activities affected, list of potential risk responses, list of causes

Full Access
Question # 222

A member of the agile project team has questions about a task which will start in the next sprint. The team member needs clarification from the product owner regarding some inconsistencies. When should the team discuss these inconsistencies?

A.

During the next sprint planning

B.

During the next sprint meeting

C.

During the next sprint review session

D.

During the next sprint retrospective

Full Access
Question # 223

Which of the following is a tool and technique used to monitor risk?

A.

Technical performance measurement

B.

Cost performance baseline

C.

Benchmarking

D.

Cost of quality

Full Access
Question # 224

Which of the following is TRUE about most project life cycles?

A.

Staffing level is highest at the start.

B.

The stakeholders ' influence is highest at the start.

C.

The level of uncertainty is lowest at the start.

D.

The cost of changes is highest at the start.

Full Access
Question # 225

An input required in Define Scope is an organizational:

A.

structure.

B.

process asset.

C.

matrix.

D.

breakdown structure.

Full Access
Question # 226

The integrative nature of project management requires which Process Group to interact with the other Process Groups?

A.

Planning

B.

Executing

C.

Monitoring and Controlling

D.

Project Management

Full Access
Question # 227

A project manager is assigned to a strategic project Senior management asks the project manager to give a presentation in order to request support that will ensure the success of the project.

Which entities will the project manager attempt to influence?

A.

The project and the organization

B.

The organization and the industry

C.

The subject matter experts and the project

D.

The change control board and the organization

Full Access
Question # 228

Which of the following describes the similarities of the process groups and project life cycle?

A.

The life cycle involves three project management process groups.

B.

Both provide a basic framework to manage the project.

C.

Each project must have a life cycle and all processes in the five process groups.

D.

The project life cycle is managed by executing the processes within the five process groups.

Full Access
Question # 229

What is one of the main purposes of the project chatter?

A.

Formal authorization of the existence of the project

B.

Formal acceptance of the project management plan

C.

Formal approval of the detailed project budget

D.

Formal definition of stakeholder roles and responsibilities

Full Access
Question # 230

Which of the following processes audits the quality requirements and the results from quality control measures to ensure appropriate quality standards and operational definitions are used?

A.

Perform Quality Control

B.

Quality Metrics

C.

Perform Quality Assurance

D.

Plan Quality

Full Access
Question # 231

While working in an adaptive environment, a business analyst is collaborating with other roles in drafting a product roadmap. Which three roles are involved in establishing the product roadmap? (Choose three)

A.

Project sponsor

B.

Portfolio manager

C.

End user

D.

Program manager

E.

Internal inspector

Full Access
Question # 232

Which of the following lists represents trends and emerging practices in Project Risk Management?

A.

Integrated risk management, non-event risks, and project resilience

B.

Representation of uncertainty, strategies for opportunities, and strategies for overall project risk

C.

Dormancy, proximity, and propinquity

D.

Simulation, sensitivity analysis, and decision tree analysis

Full Access
Question # 233

When large or complex projects are separated into distinct phases or subprojects, all of the Process Groups would normally be:

A.

divided among each of the phases or subprojects.

B.

repeated for each of the phases or subprojects.

C.

linked to specific phases or subprojects.

D.

integrated for specific phases or subprojects.

Full Access
Question # 234

A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:

A.

Start-to-start (SS).

B.

Start-to-finish (SF).

C.

Finish-to-start (FS).

D.

Finish-to-finish (FF).

Full Access
Question # 235

A project in which the scope, time, and cost of delivery are determined as early as possible is following a life cycle that is:

A.

Adaptive

B.

Predictive

C.

Incremental

D.

Iterative

Full Access
Question # 236

Which of the following response strategies are appropriate for negative risks or threats?

A.

Share, Accept, Transfer, or Mitigate

B.

Exploit, Enhance, Share, or Accept

C.

Mitigate, Share, Avoid, or Accept

D.

Avoid, Mitigate, Transfer, or Accept

Full Access
Question # 237

The project manager is leading a construction project that has been ongoing for eight years. The project manager needs to calculate the correct static payback period and consults the cash flow statement of the construction project investment.

What equation should the project manager use?

Cash Flow Statement of the Project Investment Unit: US$ Billion

Period: 0, 1, 2, 3, 4, 5, 6, 7, 8

Cash inflow: 0, 0, 0, 0, 1200, 1200, 1200, 1200

Cash outflow: 0, 700, 800, 500, 700, 700, 700, 700, 700

Net cash flow (NCF): 0, -700, -800, 300, 500, 500, 500, 500, 500

Accumulative total of net cash flow: 0, -700, -1500, -1200, -700, -200, 300, 800, 1300

A.

Static payback period = 3 + |-1200| / 500 = 5.4

B.

Static payback period = 6 + |300| / 500 = 6.6

C.

Static payback period = 5 + |-200| / 500 = 5.4

D.

Static payback period = 4 + |-700| / 500 = 5.4

Full Access
Question # 238

What do top project managers do to maximize their sphere of influence within a project team?

A.

Consider management standards, economic factors, and sustainability strategies

B.

Contribute knowledge and expertise to others within the profession

C.

C Address political and strategic issues that impact the project ' s viability or quality

D.

D Demonstrate superior relationship and communication skills while displaying a positive attitude

Full Access
Question # 239

In the basic communication model, which term refers to the method that is used to convey the message?

A.

Decode

B.

Encode

C.

Medium

D.

Noise

Full Access
Question # 240

In Project Cost Management, which input is exclusive to the Determine Budget process?

A.

Scope baseline

B.

Organizational process assets

C.

Project schedule

D.

Resource calendars

Full Access
Question # 241

In a preliminary meeting for a project, team members decide to execute the project with methodology A finance team member wants to know how project cost will be determined at this early stage. How will the project team determine project cost?

A.

Use a lightweight cost estimation due to the nature of angile projects.

B.

Use a detailed cost estimation for agile projects.

C.

Retrieve a dudget from a previous project and create a baseline of this project based on it.

D.

Use a detailed work breakdown structure (WBS) to get cost estimation.

Full Access
Question # 242

Which of the following items is a technique for data gathering?

A.

Facilitation

B.

Meeting management

C.

Conflict management

D.

Interviews

Full Access
Question # 243

Which item is a formal proposal to modify any document, deliverable, or baseline?

A.

Change request

B.

Requirements documentation

C.

Scope baseline

D.

Risk urgency assessment

Full Access
Question # 244

A project manager is assigned to a project during the execution phase and consults the documents created by the previous project manager.

Which document should the project manager study to identify the ownership of the project outcome?

A.

The lessons learned repository

B.

The project charter

C.

The business case

D.

The organizational plan

Full Access
Question # 245

Which type of dependency is contractually required or inherent in the nature of the work?

A.

External

B.

Lead

C.

Discretionary

D.

Mandatory

Full Access
Question # 246

A tool or technique used in the Control Procurements process is:

A.

Expert judgment.

B.

Performance reporting.

C.

Bidder conferences.

D.

Reserve analysis.

Full Access
Question # 247

Which process identifies whether the needs of a project can best be met by acquiring products, services, or results outside of the organization?

A.

Plan Procurement Management

B.

Control Procurements

C.

Collect Requirements

D.

Plan Cost Management

Full Access
Question # 248

Which of the following is an output of the Monitor and Control Project Work process?

A.

Change requests

B.

Performance reports

C.

Organizational process assets

D.

Project management plan

Full Access
Question # 249

The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:

A.

Planning.

B.

Executing,

C.

Monitoring and Controlling.

D.

Closing.

Full Access
Question # 250

Which of the following is a narrative description of products, services, or results to be delivered by a project?

A.

Project statement of work

B.

Business case

C.

Accepted deliverable

D.

Work performance information

Full Access
Question # 251

Which characteristic do projects and operational work share in common?

A.

Performed by systems

B.

Constrained by limited resources

C.

Repetitiveness

D.

Uniqueness

Full Access
Question # 252

Match the process with its corresponding Process Group:

Question # 252

Full Access
Question # 253

In an agile or adaptive environment. when should risk be monitored and prioritized?

A.

Only during the initiation and Closing phases

B.

During the initiation and Planning phases

C.

During each iteration as the project progresses

D.

Throughout the Planning process group and retrospective meeting

Full Access
Question # 254

The project sponsor wants to know when an in-flight adaptive project will be done. Which of the following metrics will help the team to predict how much longer the project will take?

A.

Risk burnup and control chart

B.

Customer satisfaction index and workload

C.

Average burndown and velocity

D.

Average velocity and cycle time

Full Access
Question # 255

How can you describe the role of the project.... of influence concept?

A.

The proiect manager proactivnly interacfS with other project managers creating a positive influence Km fulfilling project needs, working with other managers and sponsor to address internal political and strategic issues and ensunng that the project managemenl plan aligns with the portfolio or program plan

B.

The project manager leads the team, performs communication roles between stakeholders, and uses interpersonal sills to balance conflicting goals

C.

The proiect manager stays informed about current technology developments lakes into account new quality management standards, and uses relevant technical support tools

D.

The proiect manager participates in project management trainings, contributes to the organization professional community sharing knowledge, and maintains subied matter expertise

Full Access
Question # 256

During the execution of a predicted project, the need for a new product feature has been proposed by the customer. What should the project manager do next?

A.

Decline any request by the customer and continue the project as initially planned.

B.

Accept the customer ' s request and continue with elicitation of the new product features.

C.

Investigate the possibility of using the management reserve to pay for the extra hours the team will need to work.

D.

Investigate the effect that such an integration will have on the project plan and propose a change request.

Full Access
Question # 257

Which knowledge area includes the processes to identify, define, and unify the various project management processes?

A.

Project Integration Management

B.

Project Communications Management

C.

Project Qualify Management

D.

Project Risk Management

Full Access
Question # 258

What is the function of a Project Management Office (PMO)?

A.

To focus on the coordinated planning, prioritization, and execution of projects and subprojects that are tied to the parent organizations or the client ' s overall business objectives.

B.

To coordinate and manage the procurement of projects relevant to the parent organization ' s business objectives and to administer the project charters accordingly.

C.

To administer performance reviews for the project manager and the project team members and to handle any personnel and payroll issues.

D.

To focus on the specified project objectives and to manage the scope, schedule, cost, and quality of the work packages.

Full Access
Question # 259

Who determines which dependencies are mandatory during the Sequence Activities process?

A.

Project manager

B.

External stakeholders

C.

Internal stakeholders

D.

Project team

Full Access
Question # 260

A project manager engages a highly specialized resource who is in a different location and cannot join the regular team meetings. This is leading to delays in productivity. How can the project manager assist the team to resolve the issue?

A.

Request the new resource be relocated with the rest of the team and document a change request forthe project.

B.

Ask the team to identify possible options to resolve the issue with minimal impact to the new resource.

C.

Log this issue in the issue log and escalate it to the management team, asking them to replace the new team member.

D.

Consult the communications management plan to review available options, such as special virtual meetings, with the new resource.

Full Access
Question # 261

An input of the Plan Procurement Management process is:

A.

Make-or-buy decisions.

B.

Activity cost estimates.

C.

Seller proposals.

D.

Procurement documents.

Full Access
Question # 262

Which Process Group contains those processes performed to define a new project?

A.

Initiating

B.

Planning

C.

Executing

D.

Closing

Full Access
Question # 263

Which is the main benefit of managing and tailoring strategies in the Stakeholder Engagement process?

A.

Increased support and minimized resistance from stakeholders

B.

Increased performance of the project team

C.

Maintenance of stakeholder satisfaction because costs and scope are under control

D.

Updated project documents, as requested by stakeholders

Full Access
Question # 264

When closing a project or phase, part of the process may require the use of which type of analysis?

A.

Reserve analysis

B.

Regression analysis

C.

Document analysis

D.

Product analysis

Full Access
Question # 265

Which of the following is a project constraint?

A.

Twenty-five percent of staff turnover is expected.

B.

The technology to be used is cutting-edge.

C.

Project leadership may change due to a volatile political environment.

D.

The product is needed in 250 days.

Full Access
Question # 266

Which of the following can a project manager use to represent dellned team member roles in a group of tasks?

A.

Work breakdown structure (WBS)

B.

Responsibility assignment matrix (RAM)

C.

Organizational breakdown structure (OBS)

D.

Resource breakdown structure (RBS)

Full Access
Question # 267

A tool and technique used in the Develop Project Charter process is:

A.

change control tools

B.

expert judgment

C.

meetings

D.

analytical techniques

Full Access
Question # 268

Testing falls into which of the following categories of cost of quality?

A.

Internal failure costs

B.

Prevention costs

C.

Appraisal costs

D.

External failure costs

Full Access
Question # 269

In which process might a project manager use risk reassessment as a tool and technique?

A.

Perform Qualitative Risk Analysis

B.

Monitor and Control Risk

C.

Monitor and Control Project Work

D.

Plan Risk Responses

Full Access
Question # 270

Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?

A.

Risk and uncertainty increase; the cost of changes increases.

B.

Risk and uncertainty increase; the cost of changes decreases,

C.

Risk and uncertainty decrease; the cost of changes increases.

D.

Risk and uncertainty decrease; the cost of changes decreases.

Full Access
Question # 271

Plan Communications Management develops an approach and plan for project communications based on stakeholders ' needs and requirements and:

A.

Available organizational assets

B.

Project staff assignments

C.

Interpersonal skills

D.

Enterprise environmental factors

Full Access
Question # 272

Which is an output from Distribute Information?

A.

Earned value analysis

B.

Trend analysis

C.

Project records

D.

Performance reviews

Full Access
Question # 273

In a project using agile methodology, who may perform the quality control activities?

A.

A group of quality experts at specific times during the project

B.

The project manager only

C.

All team members throughout the project life cycle

D.

Selected stakeholders at specific times during the project

Full Access
Question # 274

A project manager has just consolidated the project risk management plan and sent it to the sponsor. The sponsor wants to reduce the likelihood of a specific risk.

Which approach should the project manager take?

A.

Escalate

B.

Mitigate

C.

Avoid

D.

Transfer

Full Access
Question # 275

Market conditions and published commercial information are examples of which input to the Estimate Costs process?

A.

Scope baseline

B.

Organizational process assets

C.

Enterprise environmental factors

D.

Risk register

Full Access
Question # 276

What three strategies are used to respond to threats?

A.

Escalate, accept, and mitigate

B.

Accept share, and avoid

C.

Escalate, transfer, and exploit

D.

Mitigate, accept, and prioritize

Full Access
Question # 277

The degree, amount, or volume of risk that an organization or individual will withstand is known as its risk:

A.

Analysis

B.

Appetite

C.

Tolerance

D.

Response

Full Access
Question # 278

Which of the following is an input to Develop Human Resource Plan?

A.

Team performance assessment

B.

Roles and responsibilities

C.

Staffing management plan

D.

Enterprise environmental factors

Full Access
Question # 279

When is a project finished?

A.

After verbal acceptance of the customer or sponsor

B.

After lessons learned have been documented in contract closure

C.

When the project objectives have been met

D.

After resources have been released

Full Access
Question # 280

Which of the following is an output of Define Scope?

A.

Project scope statement

B.

Project charter

C.

Project plan

D.

Project schedule

Full Access
Question # 281

A project manager is appointed full-time to a project and is given full-time administrative staff and full-time project team members. This situation describes which type of organizational structure?

A.

Projectized

B.

Weak matrix

C.

Functional

D.

Balanced matrix

Full Access
Question # 282

Which tool or technique is used to manage change requests and the resulting decisions?

A.

Change control tools

B.

Expert judgment

C.

Delphi technique

D.

Change log

Full Access
Question # 283

Which Process Group typically consumes the bulk of a project ' s budget?

A.

Monitoring and Controlling

B.

Executing

C.

Planning

D.

Initiating

Full Access
Question # 284

The following chart contains information about the tasks in a project.

Question # 284

Based on the chart, what is the cost performance index (CPI) for Task 2?

A.

0.8

B.

1

C.

1.25

D.

1.8

Full Access
Question # 285

The process of monitoring the status of the project to update project progress and manage changes to the schedule baseline is:

A.

Control Schedule.

B.

Quality Control.

C.

Perform Integrated Change Control.

D.

Develop Schedule.

Full Access
Question # 286

In which Knowledge Area is the project charter developed?

A.

Project Cost Management

B.

Project Scope Management

C.

Project Time Management

D.

Project Integration Management

Full Access
Question # 287

When executing a project, a recently hired subject matter expert (SME) who reviewed the execution progress remarked that the schedule could be crashed and that the schedule was not assessed properly. What should the project manager do next?

A.

Update the schedule baseline

B.

Review the schedule baseline

C.

Initiate a change request

D.

Update the risk register

Full Access
Question # 288

Resource calendars are included in the:

A.

staffing management plan.

B.

work breakdown structure (WBS).

C.

project communications plan.

D.

project charter.

Full Access
Question # 289

What are the formal and informal policies, procedures, and guidelines that could impact how the project ' s scope is managed?

A.

Organizational process assets

B.

Enterprise environmental factors

C.

Project management processes

D.

Project scope management plan

Full Access
Question # 290

A project manager is assigned to a new project with a defined scope. The project requires advanced planning at the start of the project. Which approach should the project manager select for the project?

A.

Predictive

B.

Hybrid

C.

Kanban

D.

Adaptive

Full Access
Question # 291

A project manager has the task of determining the deliverables for a six-month project using a predictive approach. How should the project manager determine which processes to include in the project management plan?

A.

Follow organizational methodology and produce all required deliverables.

B.

Discuss the processes and deliverables needed to meet the project objectives with the team.

C.

Identify the processes and deliverables for only the current phase first.

D.

Integrate hybrid approach processes and deliverables to meet the short delivery timeline.

Full Access
Question # 292

What is the responsibility of the project manager and the functional manager respectively?

A.

Oversight for an administrative area; a facet of the core business

B.

Achieving the project objectives; providing management oversight for an administrative area

C.

A facet of the core business; achieving the project objectives

D.

Both are responsible for achieving the project objectives.

Full Access
Question # 293

Ensuring that both parties meet contractual obligations and that their own legal rights are protected is a function of:

A.

Conduct Procurements.

B.

Close Procurements.

C.

Administer Procurements,

D.

Plan Procurements.

Full Access
Question # 294

An adaptive team is performing the kickoff meeting and planning the project management approach. After defining project events, one team member argues that the artifacts are missing. The project manager coaches the team to complete the planning.

Which two of the following items should be included in the planning? (Choose two)

A.

Daily scrum

B.

Sprint backlog

C.

Sprint review

D.

Increments

E.

Sprint retrospective

Full Access
Question # 295

Which statement is related to the project manager ' s sphere of influence at the organizational level?

A.

A project manager interacts with other project managers to detect common interests and impacts between their projects.

B.

A project manager facilitates communication between the suppliers and contractors on the project.

C.

A project manager considers the current industry trends and evaluates how they can impact or be applied to the project.

D.

A project manager may inform other professionals about the value of project management.

Full Access
Question # 296

According to the PMI Talent Triangle. leadership skills relate to the ability to:

A.

understand the high-level overview of the organization

B.

tailor traditional and agile tools for the project

C.

work with stakeholders to develop an appropriate project delivery

D.

guide, motivate, and direct a team to reach project goals

Full Access
Question # 297

During a retrospective, the team finds that all of the user stories are not complete. What should be done with the incomplete user stories?

A.

Move these user stories back to the product backlog for reprioritization.

B.

Remove these user stories as they are not important.

C.

Advance these user stories to the top of the next sprint backlog.

D.

Complete these user stories in the current sprint and extend the sprint length.

Full Access
Question # 298

Which of the following is contained within the communications management plan?

A.

An organizational chart

B.

Glossary of common terminology

C.

Organizational process assets

D.

Enterprise environmental factors

Full Access
Question # 299

A project manager is formalizing acceptance of the completed project deliverables. What is an input to this process?

A.

Verified deliverables

B.

Validated deliverables

C.

Accepted deliverables

D.

Completed change requests

Full Access
Question # 300

The cost benefit analysis tool is used for creating:

A.

Pareto charts.

B.

quality metrics.

C.

change requests,

D.

Ishikawa diagrams.

Full Access
Question # 301

A key project team member complains about being left out of the communication loop. In order to ensure that each key member is involved, who should review the business analysis communications management plan?

A.

Business analyst, project manager, and sponsor

B.

Business analyst, project manager, and stakeholders

C.

Business analyst and project manager

D.

Only the business analyst

Full Access
Question # 302

Responsible, accountable, consult and inform (RACI) is an example of which of the following?

A.

Text-oriented formal

B.

Resource management plan

C.

Organization chart

D.

Responsibility assignment matrix (RAM)

Full Access
Question # 303

What should a project manager use to determine how much money is needed to complete a project?

A.

Earned value management (EVM)

B.

Estimate at completion (EAC)

C.

Earned value analysis (EVA)

D.

Budget at completion (BAG)

Full Access
Question # 304

Which of the following are processes associated with Project Cost Management?

A.

Develop Costs. Estimate Costs, Determine Budget. Control Costs

B.

Develop Budget, Determine Budget, Determine Risks, Control Costs

C.

Plan Cost Management, Estimate Costs. Determine Budget. Control Costs

D.

Plan Budget Management. Determine Budget, Create Cost Accounts. Control Costs

Full Access
Question # 305

Which provides the basic framework for managing a project?

A.

Project life cycle

B.

Work breakdown structure (WBS)

C.

Enterprise environmental factors

D.

Project initiation

Full Access
Question # 306

Which of the following is part of the project sponsor ' s responsibility?

A.

Monitoring the business value

B.

Advocating the business value

C.

Tracking the business value

D.

Auditing the business value

Full Access
Question # 307

Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?

A.

Bottom-up

B.

Parametric

C.

Analogous

D.

Three-point

Full Access
Question # 308

Which Control Scope input is compared to actual results to determine if corrective action is required for the project?

A.

Scope baseline

B.

Scope management plan

C.

Change management plan

D.

Cost baseline

Full Access
Question # 309

Which is the correct formula for calculating expected activity cost for three-point estimating?

A.

Ce = (C0 + 6Cm + Cp)/4

B.

Ce = (6C0 + Cm + Cp)/4

C.

Ce = (C0 + 4Cm + Cp)/6

D.

Ce = (C0 + C„, + 4Cp) / 6

Full Access
Question # 310

What is main purpose of Project Quantity Management?

A.

To meet customer requirements by overworking the team

B.

To fulfill project schedule objectives by rushing planned inspections

C.

To fulfill project requirements of both quality and grade

D.

To exceed customer expectations

Full Access
Question # 311

Configuration identification, configuration status accounting, and configuration verification and audit are all activities in which process?

A.

Perform Quality Assurance

B.

Direct and Manage Project Work

C.

Monitor and Control Project Work

D.

Perform Integrated Change Control

Full Access
Question # 312

Which category of contracts are sellers legally obligated to complete, with possible financial damages if the project objectives are not met?

A.

Cost-reimbursable contracts

B.

Time and Material contracts (TandM)

C.

Fixed-price contracts

D.

Cost Plus Fixed Fee Contracts (CPFF)

Full Access
Question # 313

To ensure stakeholder satisfaction; identified stakeholder needs should all be

A.

Vetted

B.

Ranked from greatest to least

C.

Qualified

D.

Documented in the stakeholder engagement plan

Full Access
Question # 314

The process of monitoring the status of the project and product scope as well as managing the changes to the scope baseline is known as:

A.

Validate Scope.

B.

Plan Scope Management.

C.

Control Scope.

D.

Define Scope.

Full Access
Question # 315

What can a requirements traceability matrix enable regardless of the project methodology being used?

A.

Creation of a solid business case

B.

Investigation of the viability of a new product

C.

Identification of missing and superfluous requirements

D.

Evaluation of solution and system performance

Full Access
Question # 316

When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?

A.

Bottom-up

B.

Parametric

C.

Analogous

D.

Three-point

Full Access
Question # 317

An input used in developing the communications management plan is:

A.

Communication models.

B.

Enterprise environmental factors.

C.

Organizational communications,

D.

Organizational cultures and styles.

Full Access
Question # 318

To which knowledge area does the Collect Requirements process belong?

A.

Quality Management

B.

Scope Management

C.

Cost Management

D.

Integration Management

Full Access
Question # 319

A project team is tasked with decomposing the scope to enable detailed cost and duration estimates. What should the team do to achieve this requirement?

A.

Prepare a WBS with task sequencing and detail the duration and cost estimates.

B.

Prepare a WBS to work package level to effectively manage duration and cost estimates.

C.

Prepare a WBS for immediate tasks in the plan to work package level for duration and cost estimates.

D.

Prepare a work breakdown structure (WBS) to include each deliverable with a target duration and cost estimate.

Full Access
Question # 320

In an agile and adaptive project, which scope management entity invokes stakeholder engagement?

A.

Collect Requirements

B.

Create work breakdown structure (WBS)

C.

Plan Scope Management

D.

Scope Baseline

Full Access
Question # 321

During project planning, team members seemed clear on deliverables. However, as the project progressed deeper into the execution phase, team members expressed the need for smaller components to better understand what must be delivered.

What should the project manager do?

A.

Inform the stakeholders that the stakeholder register needs to be recreated, as the team does not understand the requirements.

B.

Share the project management plan with the team members again to bring them up to speed on the requirements.

C.

Schedule additional meetings with the customer to explain the requirements for each deliverable at length.

D.

Revisit the work breakdown structure (WBS) again during execution, as the WBS can be defined at different points in the project.

Full Access
Question # 322

Which of these is true project integration management?

A.

Project Integration Management is mandatory and more effective in larger projects

B.

Project Integration Management and Expert Judgement are mutually exclusive

C.

Project Integration Management is the responsibility of the project manager

D.

Project Integration Management excludes the triple constraints if cost performance index (CPI) equals zero

Full Access
Question # 323

Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?

A.

Work breakdown structure

B.

Organizational breakdown structure

C.

Resource breakdown structure

D.

Bill of materials

Full Access
Question # 324

During which process group is the quality policy determined?

A.

Initiating

B.

Executing

C.

Planning

D.

Controlling

Full Access
Question # 325

Recognition and rewards are tools and techniques of which process?

A.

Develop Team

B.

Manage Team

C.

Control Resources

D.

Plan Resource Management

Full Access
Question # 326

A complete set of concepts, terms, and activities that make up an area of specialization is known as:

A.

a Knowledge Area

B.

a Process Group

C.

program management

D.

portfolio management

Full Access
Question # 327

Which procurement management process includes obtaining seller response, seller selection, and contract awarding?

A.

Plan Procurement

B.

Manage Procurement

C.

Conduct Procurements

D.

Perform Procurement

Full Access
Question # 328

Which technique is commonly used for the Perform Quantitative Risk Analysis process?

A.

Brainstorming

B.

Strategies for opportunities

C.

Decision tree analysis

D.

Risk data quality assessment

Full Access
Question # 329

Based on a previous project that has been completed, a project manager decides the best way to estimate costs is through historical data. What kind of estimating is this?

A.

Three-point

B.

Bottom-up

C.

Parametric

D.

Analogous

Full Access
Question # 330

Skills necessary for project management such as motivating to provide encouragement; listening actively; persuading a team to perform an action; and summarizing, recapping, and identifying next steps are known as:

A.

organizational skills

B.

technical skills

C.

communication skills

D.

hard skills

Full Access
Question # 331

Which Control Stakeholder Engagement tool or technique allows the project manager to consolidate and facilitate distribution of reports?

A.

Information management systems

B.

Work performance reports

C.

Stakeholder analysis

D.

Data gathering and representation

Full Access
Question # 332

A project manager in a bank is developing market risk-related processes and is midway through the project. More than half of the product backlog items are developed and delivered to the customer. Due to regulatory and compliance changes in the industry, new backlog items were added to the product backlog with a significant impact on the project schedule. Who should the project manager send this change request to?

A.

The project steering committee (PSC)

B.

The project management office (PMO)

C.

The change control board (CCB)

D.

The change management committee (CMC)

Full Access
Question # 333

Which Develop Schedule tool and technique produces a theoretical early start date and late start date?

A.

Critical path method

B.

Variance analysis

C.

Schedule compression

D.

Schedule comparison bar charts

Full Access
Question # 334

Which action is included in the Control Costs process?

A.

Identify how the project costs will be planned, structured, and controlled

B.

Determine policies, objectives, and responsibilities to satisfy stakeholder needs

C.

Develop an approximation of the monetary resources needed to complete project activities

D.

Monitor cost performance to isolate and understand variances from the approved cost baseline

Full Access
Question # 335

What process is performed periodically throughout the project as needed?

A.

Plan Risk Management

B.

Plan Communications Management

C.

Plan Resource Management

D.

Plan Cost Management

Full Access
Question # 336

A business analyst has encountered a conflict related to competing requirements on an existing project. What tool should the business analyst use to resolve this issue?

A.

Peer review

B.

Procurement management

C.

Weighted ranking

D.

Risk assessment

Full Access
Question # 337

Monte Carlo is which type of risk analysis technique?

A.

Probability

B.

Quantitative

C.

Qualitative

D.

Sensitivity

Full Access
Question # 338

Which of these statements is true of subsidiary management plans?

A.

Subsidiary management plans are mandatory for any project

B.

Subsidiary management plans use the project charier as input

C.

Subsidiary management plans can be independently managed

D.

Subsidiary management plans do not need regular updates

Full Access
Question # 339

The diagram below is an example of a:

A.

Risk breakdown structure (RBS).

B.

Project team.

C.

SWOT Analysis.

D.

Work breakdown structure (WBS).

Full Access
Question # 340

The process of identifying and documenting project roles, responsibilities, required skills, and reporting relationships and creating a staffing management plan is known as:

A.

Develop Project Team.

B.

Manage Project Team.

C.

Acquire Project Team.

D.

Plan Human Resource Management.

Full Access
Question # 341

If the estimate at completion (EAC) is 25, and the budget at completion (BAC) is 17, what is the variance at completion (VAC)?

A.

-8

B.

425

C.

1.4

D.

8

Full Access
Question # 342

Which organizational process assets update is performed during the Close Procurements process?

A.

Procurement audit

B.

Lessons learned

C.

Performance reporting

D.

Payment requests

Full Access
Question # 343

Which of the following answers includes an input, a technique, and an output of the Plan Stakeholders Engagement process?

A.

Project management plan, data gathering, and stakeholder engagement plan

B.

Business documents, meetings, and stakeholder register

C.

Organizational process assets, data gathering, and project document updates

D.

Project management plan, data analysis, and change requests

Full Access
Question # 344

The project leam is brainstorming on approaches to deliver the upcoming product launch for which the project has been chartered. The project manager is laying out hybrid, adaptive, iterative methods. What is the team trying to address?

A.

Co-location

B.

Lite-cycle

C.

Diversity

D.

Management

Full Access
Question # 345

If you are using an Ishikawa diagram to determine the root cause of problems, which process are you engaged in?

A.

Plan Quality Management

B.

Control Quality

C.

Risk Management

D.

Plan Scope Management

Full Access
Question # 346

Change request status updates are an output of which process?

A.

Perform Integrated Change Control

B.

Direct and Manage Project Execution

C.

Close Project or Phase

D.

Monitor and Control Project Work

Full Access
Question # 347

Which defines the portion of work included in a contract for items being purchased or acquired?

A.

Procurement management plan

B.

Evaluation criteria

C.

Work breakdown structure

D.

Procurement statement of work

Full Access
Question # 348

It’s time to perform code review on a software project that has over three million lines of code written. Which management tool should the project manager use?

A.

Pareto chart

B.

Regression analysis

C.

Statistical sampling

D.

Automated testing tools

Full Access
Question # 349

Which type of analysis would be used for the Plan Quality process?

A.

Schedule

B.

Checklist

C.

Assumption

D.

Cost-Benefit

Full Access
Question # 350

Which key benefit can a project manager obtain by identifying stakeholders?

A.

Identify the appropriate focus for engagement of each stakeholder.

B.

Assess the risk exposure for each stakeholder.

C.

Map stakeholder power and influence grid.

D.

Identify the appropriate channels of communication with all stakeholders.

Full Access
Question # 351

The procurement requirements for a project include working with several vendors. What should the project manager take into consideration during the Project Procurement Management processes?

A.

Work performance information

B.

Bidder conferences

C.

Complexity of procurement

D.

Procurement management plan

Full Access
Question # 352

Which is the order of steps in the Procurement Management process?

A.

Identifying and planning procurement requirements, obtaining quotes or proposals, negotiating with vendors, contracting with selected vendors, and controlling procurements

B.

Identifying and planning procurement requirements, negotiating with vendors, contracting with selected vendors, obtaining quotes or proposals, and controlling procurements

C.

Controlling procurements, identifying and planning procurement requirements, obtaining quotes or proposals, negotiating with vendors, and contracting with selected vendors

D.

Obtaining quotes or proposals, identifying and planning procurement requirements, negotiating with vendors, contracting with selected vendors, and controlling procurements

Full Access
Question # 353

A reward can only be effective if it is:

A.

Given immediately after the project is completed.

B.

Something that is tangible.

C.

Formally given during project performance appraisals.

D.

Satisfying a need valued by the individual.

Full Access
Question # 354

Quality metrics are an output of which process?

A.

Plan Quality

B.

Perform Quality Control

C.

Perform Quality Assurance

D.

Perform Qualitative Risk Analysis

Full Access
Question # 355

Directing another person to get from one point to another using a known set of expected behaviors and the ability to lead a team and inspire them to do their jobs well is related to?

A.

Influence and challenge

B.

Innovation and administration

C.

Leadership and management

D.

Engagement and guidance

Full Access
Question # 356

What is the recommended approach for handling risk in a high-variability environment?

A.

Adaptive

B.

Predictive

C.

Iterative

D.

Incremental

Full Access
Question # 357

Which of the following is a tool and technique used in the Develop Schedule process?

A.

Three-point estimates

B.

Resource leveling

C.

Precedence diagramming method

D.

Bottom-up estimating

Full Access
Question # 358

Which of the following tasks is related to perform the qualitative risk analysis process?

A.

Identify the project risks and assign a probability of occurrance

B.

Perform a sensitivity analysis to determine which risk has the most potential for impacting the project

C.

Analyze the effect of identified project risks as numerical data

D.

Prioritize each project risk and assign the probability of occurrence and impact for each one

Full Access
Question # 359

Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a specific sequence is desired, even though there may be other acceptable sequences?

A.

External

B.

Internal

C.

Mandatory

D.

Discretionary

Full Access
Question # 360

Which process is engaged when a proiect learn inember makes a change to project budget with the project manager ' s approval?

A.

Manage Cost Plan

B.

Estimate Costs

C.

Determine Budget

D.

Control Costs

Full Access
Question # 361

What Knowledge Area must be led by the project manager and cannot be delegated to other specialists?

A.

Project Cost Management

B.

Project Integration Management

C.

Project Risk Management

D.

Project Schedule Management

Full Access
Question # 362

Which project risk listed in the table below is most likely to occur?

Question # 362

A.

1

B.

2

C.

3

D.

4

Full Access
Question # 363

Project reporting is a tool that is most closely associated with which process?

A.

Communicate Plan

B.

Manage Communications

C.

Report Performance

D.

Control Communications

Full Access
Question # 364

The Plan Stakeholder Management process belongs to which Process Group?

A.

Executing

B.

Initiating

C.

Planning

D.

Monitoring and Controlling

Full Access
Question # 365

At the start of a typical project life cycle, costs are:

A.

low, peak as work is carried out, and drop as the project nears the end.

B.

low, become steady as work is carried out, and increase as the project nears the end.

C.

high, drop as work is carried out, and increase as the project nears the end.

D.

high, become low as work is carried out, and drop as the project nears the end.

Full Access
Question # 366

Which of the following is used as an input to prepare a cost management plan?

A.

Expert judgment

B.

Lessons learned

C.

Cost estimates

D.

Project management plan

Full Access
Question # 367

A project manager is working in an environment where requirements are not very clear and may change during the project. In addition, the project has several stakeholders and is technically complex.

Which strategies should the project manager take into account for risk management in this environment?

A.

Occasionally identify, evaluate, and classify risks.

B.

Review requirements and cross-functional project teams.

C.

Include contingency reserves and update the project management plan frequently.

D.

Frequently review incremental work products and update the requirements for proper prioritization.

Full Access
Question # 368

Lessons learned are created and project resources are released in which Process Group?

A.

Planning

B.

Executing

C.

Closing

D.

Initiating

Full Access
Question # 369

The process to ensure that appropriate quality standards and operational definitions are used is:

A.

Plan Quality.

B.

Perform Quality Assurance.

C.

Perform Quality Control.

D.

Total Quality Management.

Full Access
Question # 370

Which process involves documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans?

A.

Collect Requirements

B.

Direct and Manage Project Execution

C.

Monitor and Control Project Work

D.

Develop Project Management Plan

Full Access
Question # 371

When is a Salience Model used?

A.

In a work breakdown structure (WBS)

B.

During quality assurance

C.

In stakeholder analysis

D.

During quality control (QC)

Full Access
Question # 372

Which enterprise environmental factors should be considered when creating a new procurement contract?

A.

Supply chains

B.

Trial engagements

C.

Lessons learned register

D.

Local laws and regulalk

Full Access
Question # 373

Which cost is associated with nonconformance?

A.

Liabilities

B.

Inspections

C.

Training

D.

Equipment

Full Access
Question # 374

Which actions should a project manager follow to manage stakeholders?

A.

Identify the key stakeholders and keep them informed at all times.

B.

Identify the stakeholders, planning, managing and monitoring their engagement

C.

Meet and keep informed any person related to the project, at all times

D.

Identify the stakeholders and monitor their level of satisfaction

Full Access
Question # 375

On which type of project.... only after the final iteration?

On wtiich type of project lite cycle is ihe deliverable produced trough a series of ileralrons considering thai the deliverable ts completed only after the Imal iteration?

A.

Incremental life cycle

B.

Predictive life cycle

C.

Iterative life cycle

D.

Adaptive life cycle

Full Access
Question # 376

Which project document is updated in the Control Stakeholder Engagement process?

A.

Project reports

B.

Issue log

C.

Lessons learned documentation

D.

Work performance information

Full Access
Question # 377

Which two of the following can be used as communication tools between the business analyst and the rest of the project team? (Choose two)

A.

Project management plan

B.

Pareto chart

C.

Gantt chart

D.

Responsible, accountable, consult, inform (RACI) matrix

E.

Process flows

Full Access
Question # 378

Which of the following is an input to Control Scope?

A.

Project schedule

B.

Organizational process assets updates

C.

Project document updates

D.

Work performance information

Full Access
Question # 379

How is the schedule variance calculated using the earned value technique?

A.

EV less AC

B.

AC less PV

C.

EV less PV

D.

AC less EV

Full Access
Question # 380

Which of the following is an input to Direct and Manage Project Execution?

A.

Requested changes

B.

Approved change requests

C.

Work performance information

D.

Implemented defect repair

Full Access
Question # 381

Organizational theory is a tool used in which Project Human Resource Management process?

A.

Manage Project Team

B.

Acquire Project Team

C.

Develop Project Team

D.

Plan Human Resource Management

Full Access
Question # 382

Which is an example of an internal enterprise environmental factor?

A.

Market Share brand recognition

B.

Factory location

C.

Local government regulation

D.

Industry research

Full Access
Question # 383

What is the primary benefit of the Manage Quality process?

A.

Increases the probability of meeting quality objectives

B.

Enhances the performance of the product berg created

C.

Defines quality roles and responsibilities

D.

Ensures that the project is completed as originally planned

Full Access
Question # 384

Project Scope Management is primarily concerned with:

A.

Developing a detailed description of the project and product.

B.

Determining how requirements will be analyzed, documented, and managed.

C.

Defining and controlling what is and is not included in the project.

D.

Formalizing acceptance of the completed project deliverables.

Full Access
Question # 385

The process of defining how the project scope will be validated and controlled is known as:

A.

Define Scope.

B.

Develop Project Management Plan.

C.

Plan Scope Management.

D.

Plan Quality Management.

Full Access
Question # 386

An example of a group decision-making technique is:

A.

nominal group technique

B.

majority

C.

affinity diagram

D.

multi-criteria decision analysis

Full Access
Question # 387

Which process includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?

A.

Perform Qualitative Risk Analysis

B.

Perform Quantitative Risk Analysis

C.

Plan Risk Management

D.

Plan Risk Responses

Full Access
Question # 388

An input to Conduct Procurements is:

A.

Independent estimates.

B.

Selected sellers.

C.

Seller proposals.

D.

Resource calendars.

Full Access
Question # 389

Managing procurement relationships and monitoring contract performance are part of which process?

A.

Conduct Procurements

B.

Plan Procurements

C.

Administer Procurements

D.

Close Procurements

Full Access
Question # 390

What characteristic of servant leadership supports resource management in an agile environment?

A.

Lecturing

B.

Construing

C.

Measuring

D.

Coaching

Full Access
Question # 391

A project manager is working on project cost management. The following information is current.

* Planned value = 30

* Actual cost = 35

* Earned value = 28

Considering this data, which project indicator is correct?

A.

Schedule Variance (SV) = 2

B.

Cost Performance Index (CPI) = 0.80

C.

Schedule Performance Index (SPI) = 1.93

D.

Cost Variance (CV) = 7

Full Access
Question # 392

The purpose of developing a project scope management plan is to:

A.

Manage the timely completion of the project.

B.

Ensure that the project includes all of the work required.

C.

Make sure the project will satisfy the needs for which it was begun.

D.

Reduce the risk of negative events in the project.

Full Access
Question # 393

A project team has missed a milestone.

Which response strategy should be implemented?

A.

Communications

B.

Stakeholder

C.

Contingent

D.

Risk

Full Access
Question # 394

A project manager is searching for solutions that bring some degree of satisfaction to all parties in order to temporarily resolve a conflict. What conflict management technique is described in this situation?

A.

Withdraw/avoid

B.

Smooth /accommodate

C.

Collaborate/problem solve

D.

Compromise/ reconcile

Full Access
Question # 395

During the planning phase, a project manager must create a work breakdown structure (WBS) to improve management of the project ' s components. What should be included in the WBS?

A.

Activity dependencies

B.

Work package risks

C.

Description of work

D.

Resource estimates

Full Access
Question # 396

A measure of cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal and is expressed as the ratio of the cost needed for finishing the outstanding work to the remaining budget is known as the:

A.

budget at completion (BAC)

B.

earned value management (EVM)

C.

to-complete performance index

D.

cost performance index

Full Access
Question # 397

In the business analysis aspect of a construction project, what is the purpose of the requirements validation process?

A.

Ensures a thorough unit test case coverage

B.

Ensures an accurate reflection of the stakeholders ' intentions

C.

Ensures that the business problem is solved

D.

Ensures the successful delivery of business value

Full Access