Pre-Summer Sale - Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70dumps

CAPM Questions and Answers

Question # 6

Which of the following technology platforms is most effective for sharing information when managing virtual project teams?

A.

Video conferencing

B.

Audio conferencing

C.

Shared portal

D.

Email/chat

Full Access
Question # 7

Which type of analysis is used to determine the cause and degree of difference between the baseline and actual performance?

A.

Schedule network analysis

B.

Reserve analysis

C.

Alternative analysis

D.

Variance analysis

Full Access
Question # 8

Which of the following is an input to the Perform Qualitative Risk Analysis process?

A.

Risk register

B.

Risk data quality assessment

C.

Risk categorization

D.

Risk urgency

Full Access
Question # 9

A project manager has just consolidated the project risk management plan and sent it to the sponsor. The sponsor wants to reduce the likelihood of a specific risk.

Which approach should the project manager take?

A.

Escalate

B.

Mitigate

C.

Avoid

D.

Transfer

Full Access
Question # 10

Which process in Project Time Management includes reserve analysis as a tool or technique?

A.

Estimate Activity Resources

B.

Sequence Activities

C.

Estimate Activity Durations

D.

Develop Schedule

Full Access
Question # 11

A project manager is reviewing a past project with similar.... team choosing for tailoring?

A project manager is reviewing a past project with similar requirements to the project that is currently chartered. The project team decided to adopt quality tools, techniques and templates recommended at the organizational level after reviewing the lessons learned of the previous project What specific area of quality, is the project team choosing for tailoring?

A.

Policy compliance and auditing

B.

Standards and compliance

C.

Review of lessons learned

D.

Test and inspection planning

Full Access
Question # 12

Which of the following is a project constraint?

A.

Twenty-five percent of staff turnover is expected.

B.

The technology to be used is cutting-edge.

C.

Project leadership may change due to a volatile political environment.

D.

The product is needed in 250 days.

Full Access
Question # 13

Which tools and techniques will a project manager use to develop a project charter?

A.

Project manager experience, expert judgment, scope statement, and meetings

B.

Lessons learned database. Interpersonal and team skills, cost baseline, and meetings

C.

Expert judgment, data gathering. scope statement, schedule baseline, and meetings

D.

Expert judgment, data gathering. interpersonal and team skills, and meetings

Full Access
Question # 14

A required input for Create WBS is a project:

A.

quality plan.

B.

schedule network.

C.

management document update.

D.

scope statement.

Full Access
Question # 15

Which Process Group and Knowledge Area include the Sequence Activities process?

A.

Executing Process Group and Project Time Management

B.

Executing Process Group and Project Cost Management

C.

Planning Process Group and Project Time Management

D.

Planning Process Group and Project Cost Management

Full Access
Question # 16

A new project manager wishes to recommend creating a project management office to senior management. Which statement would the project manager use to describe the Importance of creating the project management office?

A.

It will give the project manager Independence to make decisions without other departmental input.

B.

It Integrates organizational data and information to ensure that strategic objectives are fulfilled.

C.

The project management office can execute administrative tasks.

D.

The project management office can coordinate projects.

Full Access
Question # 17

The lowest level normally depicted in a work breakdown structure (VVBS) is called a/an:

A.

work package

B.

deliverable

C.

milestone

D.

activity

Full Access
Question # 18

An output of the Manage Stakeholder Engagement process is:

A.

change requests

B.

enterprise environmental factors

C.

the stakeholder management plan

D.

the change log

Full Access
Question # 19

Which tool or technique is required in order to determine the project budget?

A.

Cost of quality

B.

Historical relationships

C.

Project management software

D.

Forecasting

Full Access
Question # 20

A project team of telecommuters located in three different time zones regularly misses project deadlines Daily meetings often start and end with the same person talking and the rest of the team listening The project manager determines that communication among team members must be addressed.

What communication step is missing from the daily meetings?

A.

Interpersonal communication

B.

Feedback response communication

C.

Push communication

D.

Pull communication

Full Access
Question # 21

What is the equation to calculate cost variance (CV)?

A.

CV = EV / BAC

B.

CV = EV - AC

C.

CV = EV - BAC

D.

CV = EV / AC

Full Access
Question # 22

What can the project manager find among the factors that could lead a project to be tailored

A.

Company Culture

B.

Return on investment

C.

Earned Value

D.

Schedule Performance Index

Full Access
Question # 23

Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project?

A.

Issue log

B.

Change log

C.

Expert judgment

D.

Change requests

Full Access
Question # 24

What provides information regarding the ways people, teams, and organizational units behave?

A.

Organizational chart

B.

Organizational theory

C.

Organizational structure

D.

Organizational behavior

Full Access
Question # 25

At the beginning of an iteration, the team will work to determine how many of the highest-priority items on the backlog list can be delivered within the next iteration. Which of the following activities is done first?

A.

Create Work Breakdown Structure (WBS)

B.

Create Scope Baseline

C.

Collect Requirements

D.

Define Scope

Full Access
Question # 26

What is the difference between verified and accepted deliverables?

A.

Accepted deliverables have been completed and checked for correctness; verified deliverables have been formally approved by the customer or authorized stakeholder.

B.

Accepted deliverables have been inspected by the quality team; verified deliverables are outputs from the Validate Scope process.

C.

Accepted deliverables have been formally signed off and approved by the authorized stakeholder; verified deliverables have been completed and checked for correctness.

D.

Accepted deliverables have been formally accepted by the project manager; verified deliverables are the outputs from the Control Quality process.

Full Access
Question # 27

What is one of the objectives of Project Risk Management?

A.

Decrease the probability and impact of an event on project objectives.

B.

Distinguish between a project risk and a project issue so that a risk mitigation plan can be put in place.

C.

Increase the probability and impact of positive events.

D.

Removal of project risk.

Full Access
Question # 28

Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?

A.

Procurement documents

B.

Inspection and audits

C.

Estimate budget

D.

Risk register

Full Access
Question # 29

Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?

A.

Product scope description

B.

Procurement statement of work

C.

Project schedule

D.

Work breakdown structure (WBS)

Full Access
Question # 30

Funding limit reconciliation is a tool and technique used in which process?

A.

Control Costs

B.

Determine Budget

C.

Estimate Costs

D.

Control Budget

Full Access
Question # 31

The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:

A.

Plan Human Resource Management.

B.

Acquire Project Team.

C.

Manage Project Team.

D.

Develop Project Team.

Full Access
Question # 32

Which process involves identifying and documenting the logical relationships between project activities?

A.

Develop Schedule

B.

Sequence Activities

C.

Create WBS

D.

Applying leads and lags

Full Access
Question # 33

Project reporting is a tool that is most closely associated with which process?

A.

Communicate Plan

B.

Manage Communications

C.

Report Performance

D.

Control Communications

Full Access
Question # 34

What does an S-curve from a Monte Carlo analysis show?

A.

Cumulative probability distribution representing probability of achieving a particular outcome

B.

Individual project risks or uncertainties that have the most potential impact on outcome

C.

Best alternative out of the possible solutions, incorporating associated risks and opportunities

D.

Diagram for all project uncertainties and their influence over a period of time

Full Access
Question # 35

A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?

A.

Slack

B.

Float

C.

Lag

D.

Lead

Full Access
Question # 36

In the Develop Project Team process, which of the following is identified as a critical factor for a project ' s success?

A.

Team meetings

B.

Subcontracting teams

C.

Virtual teams

D.

Teamwork

Full Access
Question # 37

The project manager is looking at a precedence diagram.... the duration of this task?

The project manager is looking at a precedence diagram and needs to report back about the project status The total duration of the task is ten days, and both Activity A and B need be completed. Activity A has a duration of six days, and activity B has a duration of four days Activity B has a finish-to-start relationship with activity A Under current circumstances, activity A will take about seven days to complete.

What is the outcome of the duration of this task ' ?

A.

The task will be completed on time.

B.

The task will not be completed on time.

C.

Activity A is not a critical path task

D.

The precedence diagram cannot be used to provide answers for duration calculations

Full Access
Question # 38

Which of the following documents allows the project manager to assess risks that may require near term action?

A.

Probability and impact matrix

B.

Contingency analysis report

C.

Risk urgency assessment

D.

Rolling wave plan

Full Access
Question # 39

Due to new market conditions a five-year project......need to be updated

Due to new market conditions a five-year project requires a full revision of project objectives. Which components to the stakeholder engagement plan need to be updated?

A.

Scope and impact of change to stakeholders

B.

Project scope and stakeholders goals

C.

Engagement level of key stakeholders

D.

Stakeholders expectations for the project

Full Access
Question # 40

A method to manage stakeholder expectations in the scope statement is to clearly:

A.

state the guiding principles of the organization.

B.

identify alternatives to generate different approaches.

C.

state what is out of scope.

D.

outline the results of the Delphi technique.

Full Access
Question # 41

A strengths, weaknesses, opportunities, and threats (SWOT) analysis is a tool or technique used in which process?

A.

Identify Risks

B.

Control Risks

C.

Perform Quantitative Risk Analysis

D.

Perform Qualitative Risk Analysis

Full Access
Question # 42

Work performance information and cost forecasts are outputs of which Project Cost Management process?

A.

Estimate Costs

B.

Plan Cost Management

C.

Determine Budget

D.

Control Costs

Full Access
Question # 43

An input of the Plan Procurement Management process is:

A.

Make-or-buy decisions.

B.

Activity cost estimates.

C.

Seller proposals.

D.

Procurement documents.

Full Access
Question # 44

What internal enterprise environmental factor (EEF) can impact a project?

A.

Cultural influences

B.

Physical environmental elements

C.

Commercial databases

D.

Infrastructure

Full Access
Question # 45

Who determines which dependencies are mandatory during the Sequence Activities process?

A.

Project manager

B.

External stakeholders

C.

Internal stakeholders

D.

Project team

Full Access
Question # 46

Which of the following is a tool or technique of the Define Activities process?

A.

Rolling wave planning

B.

Precedence diagramming method (PDM)

C.

Alternatives analysis

D.

Parametric estimating

Full Access
Question # 47

Which tool or technique is used in Close Procurements?

A.

Contract plan

B.

Procurement plan

C.

Closure process

D.

Procurement audits

Full Access
Question # 48

A software project has completed the first iteration, and the testing manager noted that some features were not incorporated and would not approve the software. The business unit manager who will use the software is satisfied with the software and wants to start the rollout.

What should the project manager do?

A.

Escalate the issue to the project management office (PMO).

B.

Organize a meeting between the two managers.

C.

Ask the project team to resolve all of the open issues.

D.

Escalate to the sponsor to decide when to commence the rollout.

Full Access
Question # 49

What is the most accurate rough order of magnitude (ROM)?

A.

In the Initiation phase, the estimate is in the range of +/- 50%.

B.

In the Planning phase, the estimate is in the range of +/- 50%.

C.

In the Monitoring and Controlling phase, the estimate is in the range of +/- 15%.

D.

In the Closing phase, the estimate is in the range of +/- 15%.

Full Access
Question # 50

Which of the Perform Quality Assurance tools and techniques may enhance the creation of the work breakdown structure (VVBS) to give structure to the decomposition of the scope?

A.

Activity network diagrams

B.

Affinity diagrams

C.

Matrix diagrams

D.

Interrelationship digraphs

Full Access
Question # 51

When large or complex projects are separated into distinct phases or subprojects, all of the Process Groups would normally be:

A.

divided among each of the phases or subprojects.

B.

repeated for each of the phases or subprojects.

C.

linked to specific phases or subprojects.

D.

integrated for specific phases or subprojects.

Full Access
Question # 52

A project is in the planning phase and ready for plan review and approval when a sponsor switch happens. What should the next course of action be?

A.

Plan Communications Management

B.

Plan Stakeholder Engagement

C.

Perform Integrated Change Control

D.

Perform Qualitative Risk Analysis

Full Access
Question # 53

An output of the Direct and Manage Project Work process is:

A.

Deliverables.

B.

Activity lists.

C.

A work breakdown structure.

D.

A scope statement.

Full Access
Question # 54

Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?

A.

Stakeholder register

B.

Scope management plan

C.

Stakeholder management plan

D.

Project charter

Full Access
Question # 55

Which tool or technique of the Define Activities process allows for work to exist at various levels of detail depending on where it is in the project life cycle?

A.

Historical relationships

B.

Dependency determination

C.

Bottom-up estimating

D.

Rolling wave planning

Full Access
Question # 56

Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?

A.

Identify Risks

B.

Plan Risk Management

C.

Perform Qualitative Risk Analysis

D.

Perform Quantitative Risk Analysis

Full Access
Question # 57

Which knowledge area includes the processes to identify, define, and unify the various project management processes?

A.

Project Integration Management

B.

Project Communications Management

C.

Project Qualify Management

D.

Project Risk Management

Full Access
Question # 58

An organization ' s project management office (PMO) has issued guidelines that require a specific template to be used for onboarding resources for a project. Where can the project manager find this template?

A.

Organizational systems access

B.

Organizational process assets

C.

Resources management plan

D.

Procurement management plan

Full Access
Question # 59

The project manager and project team are developing approximations of the cost of resources needed to complete the project work. On which process are they working?

A.

Plan Cost Management

B.

Estimate Activity Resources

C.

Estimate Costs

D.

Determine Budget

Full Access
Question # 60

A new game development process must have three versions. Each version is to be developed in approximately five iteration cycles with a duration of one month each. This will help this small enterprise to have a return on investment (ROI) as the project runs from the first cycle. Which methodology should the project manager adopt and implement in the project?

A.

Feature-driven development (FDD) as it will deliver product segments and the milestones are controlled by the development manager.

B.

Kanban as it will provide flexibility to the team for working at their own pace in the time frame requested.

C.

Scrum as it uses sprints and retrospectives, maximizing time delivery and the value of the product.

D.

Extreme Programming (XP) as it will help deliver more quickly since developers will work in pairs.

Full Access
Question # 61

What document gathers all of the lessons learned at the end of a phase or project

A.

Lessons learned register

B.

Lessons learned list

C.

Lessons learned project asset

D.

Lessons learned repository

Full Access
Question # 62

Which can be used to determine whether a process is stable or has predictable performance?

A.

Matrix diagram

B.

Histogram

C.

Control chart

D.

Flowchart

Full Access
Question # 63

What is the Project Schedule Management practice used to deliver incremental value to the customer ' ?

A.

Resource optimization

B.

Iterative scheduling with a backlog

C.

On-demand scheduling

D.

Critical path method

Full Access
Question # 64

Which category of contracts are sellers legally obligated to complete, with possible financial damages if the project objectives are not met?

A.

Cost-reimbursable contracts

B.

Time and Material contracts (TandM)

C.

Fixed-price contracts

D.

Cost Plus Fixed Fee Contracts (CPFF)

Full Access
Question # 65

DRAG DROP

Match the praxes manager ' s sphere of influence with the associated primary role:

Question # 65

Full Access
Question # 66

Who selects the appropriate processes for a project?

A.

Project stakeholders

B.

Project sponsor and project stakeholder

C.

Project manager and project team

D.

Project manager and project sponsor

Full Access
Question # 67

Which of the following is an input to the Develop Project Charter process?

A.

Work performance information

B.

Project management plan

C.

Business case

D.

Change requests

Full Access
Question # 68

What happens to a stakeholder ' s project influence over time?

A.

Increases

B.

Decreases

C.

Stays the same

D.

Has no bearing

Full Access
Question # 69

A graphic display of project team members and their reporting relationships is known as a:

A.

Resource calendar.

B.

Project organization chart.

C.

Resource breakdown structure (RBS).

D.

Responsibility assignment matrix (RAM).

Full Access
Question # 70

A project team is meeting to seek solutions on a new problem that occurred recently. The meeting is comprised of two parts: the first is a generation of ideas and the second is an analysis.

Which technique is the team using?

A.

Checklists

B.

Interview

C.

Focus group

D.

Brainstorming

Full Access
Question # 71

When the business objectives of an organization change, project goals need to be:

A.

realigned.

B.

performed.

C.

improved.

D.

controlled.

Full Access
Question # 72

What characteristic of servant leadership supports resource management in an agile environment?

A.

Lecturing

B.

Construing

C.

Measuring

D.

Coaching

Full Access
Question # 73

What can a requirements traceability matrix enable regardless of the project methodology being used?

A.

Creation of a solid business case

B.

Investigation of the viability of a new product

C.

Identification of missing and superfluous requirements

D.

Evaluation of solution and system performance

Full Access
Question # 74

Select three elements that apply to agile/ adaptive environments

A.

Frequent team checkpoints

B.

Colocation

C.

Access to information

D.

Virtual team members

E.

Geographically dispersed team

Full Access
Question # 75

A project ' s aim, from a business perspective, is moving an organization from one level to another to achieve a specific objective. What is the goal for a project ' s successful completion?

A.

Current state

B.

Future state

C.

Budgeted state

D.

Planned state

Full Access
Question # 76

The process of defining how the project scope will be validated and controlled is known as:

A.

Define Scope.

B.

Develop Project Management Plan.

C.

Plan Scope Management.

D.

Plan Quality Management.

Full Access
Question # 77

A project manager is responsible for delivering new software for their company. Based on previous experiences, the project manager decides to use the dynamic systems development method (DSDM). The project manager will use this method to prioritize the scope to meet project constraints.

Which elements are included in the DSDM framework?

A.

Time, integration, cost, and deliverables

B.

Schedule, risk, integration, and features

C.

Cost, time, quality, and functionality

D.

Cost, requirements, schedule, and outputs

Full Access
Question # 78

Based on a previous project that has been completed, a project manager decides the best way to estimate costs is through historical data. What kind of estimating is this?

A.

Three-point

B.

Bottom-up

C.

Parametric

D.

Analogous

Full Access
Question # 79

A large portion of a projects budget is typically expended on the processes in which Process Group?

A.

Executing

B.

Planning

C.

Monitoring and Controlling

D.

Closing

Full Access
Question # 80

Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?

A.

Applying calendars

B.

Resource leveling

C.

Resource planning

D.

Resource conflict management

Full Access
Question # 81

During a virtual kick-off session, the project sponsor highlights the significance of the project to the company. What message should be conveyed to the team in this meeting?

A.

Bonuses based on accomplishment criteria

B.

New working contract with more benefits

C.

Promotion opportunities with this project

D.

Assignment of key roles and responsibilities

Full Access
Question # 82

Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?

A.

Work breakdown structure

B.

Organizational breakdown structure

C.

Resource breakdown structure

D.

Bill of materials

Full Access
Question # 83

An input to Conduct Procurements is:

A.

Independent estimates.

B.

Selected sellers.

C.

Seller proposals.

D.

Resource calendars.

Full Access
Question # 84

In a project using agile methodology, who may perform the quality control activities?

A.

A group of quality experts at specific times during the project

B.

The project manager only

C.

All team members throughout the project life cycle

D.

Selected stakeholders at specific times during the project

Full Access
Question # 85

An example of a group decision-making technique is:

A.

nominal group technique

B.

majority

C.

affinity diagram

D.

multi-criteria decision analysis

Full Access
Question # 86

A project team member agrees to change a project deliverable after a conversation with an external stakeholder. It is later discovered that the change has had an adverse effect on another deliverable. This could have been avoided if the project team had implemented:

A.

Quality assurance.

B.

A stakeholder management plan.

C.

Project team building.

D.

Integrated change control.

Full Access
Question # 87

Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?

A.

WBS directory

B.

Activity list

C.

WBS

D.

Project schedule

Full Access
Question # 88

Which enterprise environmental factors are considered during Estimate Costs?

A.

Market conditions and published commercial information

B.

Company structure and market conditions

C.

Commercial information and company structure

D.

Existing human resources and market conditions

Full Access
Question # 89

A technique used to determine the cause and degree of difference between baseline and actual performance is:

A.

Product analysis.

B.

Variance analysis.

C.

Document analysis,

D.

Decomposition.

Full Access
Question # 90

What is an example of a technical project management skill?

A.

Managing a project schedule

B.

Developing a project delivery strategy

C.

Establishing a project team

D.

Understanding organizational objectives

Full Access
Question # 91

When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?

A.

Interactive communication

B.

Claims administration

C.

Conflict management

D.

Performance reporting

Full Access
Question # 92

Project management processes ensure the:

A.

alignment with organizational strategy

B.

efficient means to achieve the project objectives

C.

performance of the project team

D.

effective flow of the project throughout its life cycle

Full Access
Question # 93

A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?

A.

US$S000

B.

US$9500

C.

US$10,000

D.

US$12,500

Full Access
Question # 94

An intentional activity to modify a nonconforming product or product component is called:

A.

defect repair

B.

work repair

C.

corrective action

D.

preventive action

Full Access
Question # 95

How is the schedule variance calculated using the earned value technique?

A.

EV less AC

B.

AC less PV

C.

EV less PV

D.

AC less EV

Full Access
Question # 96

What should a project manager use to determine how much money is needed to complete a project?

A.

Earned value management (EVM)

B.

Estimate at completion (EAC)

C.

Earned value analysis (EVA)

D.

Budget at completion (BAG)

Full Access
Question # 97

When establishing a contingency reserve, including time, money and resources, how is the risk being handled?

A.

Accepting

B.

Transferring

C.

Avoiding

D.

Mitigating

Full Access
Question # 98

A project manager read the initial contract when a project was started. The contract states a house has to be built in one year, and the foundation has to be completed in 30 days. What should the project manager do?

A.

Add the milestones to the risk register, as time is short.

B.

Add the two milestones to the project plan, as they are mandatory.

C.

Calculate the duration of the two milestones stated in the contract.

D.

Start the project as soon as possible, as time is short.

Full Access
Question # 99

Which organizational process asset can make an impact on the outcome of a project?

A.

Political climate

B.

Leadership style

C.

Financial data repository

D.

Organizational structure types

Full Access
Question # 100

Which quality management and control tool is useful in visualizing parent-to-child relationships in any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship?

A.

Interrelationship digraphs

B.

Tree diagram

C.

Affinity diagram

D.

Network diagram

Full Access
Question # 101

Change requests, project management plan updates, project document updates, and organizational process assets updates are all outputs of which project management process?

A.

Plan Risk Responses

B.

Manage Stakeholder Expectations

C.

Define Scope

D.

Report Performance

Full Access
Question # 102

Plan Schedule Management is a process in which Knowledge Area?

A.

Project Scope Management

B.

Project Human Resource Management

C.

Project Integration Management

D.

Project Time Management

Full Access
Question # 103

An output of the Plan Quality Management process is:

A.

A process improvement plan,

B.

Quality control measurements.

C.

Work performance information,

D.

The project management plan.

Full Access
Question # 104

The component of the risk management plan that documents how risk activities will be recorded is called:

A.

tracking

B.

scoping

C.

timing

D.

defining

Full Access
Question # 105

The project manager and the project team are having a meeting with the purpose of identifying risks. Which tools and techniques might help in this process?

A.

Prompt lists and data analysis

B.

Reports and representations of uncertainty

C.

Data analysis and risk audits

D.

Interpersonal and team skills and project management Information system

Full Access
Question # 106

The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?

A.

0.8

B.

0.89

C.

1.13

D.

1.25

Full Access
Question # 107

In which process is a project manager identified and given the authority to apply resources to project activities?

A.

Acquire Project Team

B.

Develop Project Management Plan

C.

Manage Project Execution

D.

Develop Project Charter

Full Access
Question # 108

In which Knowledge Area is the project charter developed?

A.

Project Cost Management

B.

Project Scope Management

C.

Project Time Management

D.

Project Integration Management

Full Access
Question # 109

Responsible, accountable, consult and inform (RACI) is an example of which of the following?

A.

Text-oriented formal

B.

Resource management plan

C.

Organization chart

D.

Responsibility assignment matrix (RAM)

Full Access
Question # 110

Information collected on the status of project activities being performed to accomplish the project work is known as what?

A.

Project management information system

B.

Work performance information

C.

Work breakdown structure

D.

Variance analysis

Full Access
Question # 111

What are the Project Procurement Management processes?

A.

Conduct Procurements, Control Procurements, Integrate Procurements, and Close Procurements

B.

Estimate Procurements, Integrate Procurements, Control Procurements, and Validate Procurements

C.

Plan Procurement Management, Conduct Procurements, Control Procurements, and Close Procurements

D.

Plan Procurement Management, Perform Procurements, Control Procurements, and Validate Procurements

Full Access
Question # 112

A project manager is working on project cost management. The following information is current.

* Planned value = 30

* Actual cost = 35

* Earned value = 28

Considering this data, which project indicator is correct?

A.

Schedule Variance (SV) = 2

B.

Cost Performance Index (CPI) = 0.80

C.

Schedule Performance Index (SPI) = 1.93

D.

Cost Variance (CV) = 7

Full Access
Question # 113

Which of the following involves making information available to project stakeholders in a timely manner?

A.

Plan Communications

B.

Performance reporting

C.

Project status reports

D.

Distribute Information

Full Access
Question # 114

In Plan Risk Management, which of the management plans determines who will be available to share information on various risks and responses at different times and locations?

A.

Schedule

B.

Quality

C.

Communications

D.

Cost

Full Access
Question # 115

Which of the following is an output of Direct and Manage Project Execution?

A.

Project management plan

B.

Change request status updates

C.

Organizational process assets updates

D.

Work performance information

Full Access
Question # 116

The Perform Quality Assurance process occurs in which Process Group?

A.

Executing

B.

Monitoring and Controlling

C.

Initiating

D.

Planning

Full Access
Question # 117

Which of the following is least influenced by a project manager, according to the project manager ' s sphere of influence?

A.

Sponsors

B.

Project team

C.

Steering committees

D.

Stakeholders

Full Access
Question # 118

Which input will be used when tasked with developing the human resource plan?

A.

Project management plan

B.

Activity resource requirements

C.

Resource calendar

D.

Project staff assignments

Full Access
Question # 119

Which is a major component of an agreement?

A.

Change request handling

B.

Risk register templates

C.

Lessons learned register

D.

Procurement management plan

Full Access
Question # 120

To ensure stakeholder satisfaction; identified stakeholder needs should all be

A.

Vetted

B.

Ranked from greatest to least

C.

Qualified

D.

Documented in the stakeholder engagement plan

Full Access
Question # 121

Which type of project life cycle uses an iteration plan?

A.

Agile

B.

Predictive

C.

Waterfall

D.

Product

Full Access
Question # 122

An adaptive team ' s velocity dropped significantly in the last sprint due to the planned vacation of two team members. The project sponsor wants to know how many more sprints it would take to complete the remaining project.

How should the project manager calculate the anticipated velocity for future sprints?

A.

Use the velocity of the last sprint, as it is the most recent one to share.

B.

Add a 30% buffer to the velocity to calculate future velocity.

C.

Calculate the average of the past five sprints to predict future velocity.

D.

Change the adaptive tool that the team is using to calculate velocity.

Full Access
Question # 123

Which of the following is an example of schedule compression?

A.

Activity sequencing

B.

Resource leveling

C.

Lead and lag adjusting

D.

Crashing

Full Access
Question # 124

Which of the following is an example of an organizational system that is arranged based on the job being performed?

A.

Simple

B.

Multi-divisional

C.

Functional

D.

Project-oriented

Full Access
Question # 125

Which of the following are three inputs to the risk register?

A.

Risk register updates, stakeholder register, and quality management plan

B.

Communication management plan, enterprise environmental factors, and activity duration estimates

C.

Risk management plan, activity cost estimates, and project documents

D.

Project scope statement, organizational process assets, and scope baseline

Full Access
Question # 126

At the end of the project, what will be the value of SV?

A.

Positive

B.

Zero

C.

Negative

D.

Greater than one

Full Access
Question # 127

During a retrospective, the team finds that all of the user stories are not complete. What should be done with the incomplete user stories?

A.

Move these user stories back to the product backlog for reprioritization.

B.

Remove these user stories as they are not important.

C.

Advance these user stories to the top of the next sprint backlog.

D.

Complete these user stories in the current sprint and extend the sprint length.

Full Access
Question # 128

What is the primary purpose of Project Scope Management?

A.

Determining and managing stakeholder needs

B.

Contorting the status of the product scope and managing changes to its be seine

C.

Defining and controlling what is and is not included in the project

D.

Differentiating between the product scope and project scope

Full Access
Question # 129

At the completion of a project, a report is prepared that details the outcome of the research conducted on a global trend during the project. Which item did this project create?

A.

Result

B.

Product

C.

Service

D.

Improvement

Full Access
Question # 130

A product owner reviews the list of stakeholders to confirm their continued involvement with the product team. A new stakeholder is identified as actively involved in the next product release.

What should the project manager do next to engage the new stakeholder?

A.

Add the stakeholder to the communications management plan.

B.

Conduct a one-on-one interview with the stakeholder.

C.

Invite the stakeholder to the sprint-planning meeting.

D.

Send the stakeholder a questionnaire.

Full Access
Question # 131

What is the name of the statistical method that helps identify which factors may influence specific variables of a product or process under development or in production?

A.

Failure modes and effects analysis

B.

Design of experiments

C.

Quality checklist

D.

Risk analysis

Full Access
Question # 132

Which of the following are processes associated with Project Cost Management?

A.

Develop Costs. Estimate Costs, Determine Budget. Control Costs

B.

Develop Budget, Determine Budget, Determine Risks, Control Costs

C.

Plan Cost Management, Estimate Costs. Determine Budget. Control Costs

D.

Plan Budget Management. Determine Budget, Create Cost Accounts. Control Costs

Full Access
Question # 133

Which tool or technique is used in the Plan Scope Management process?

A.

Document analysis

B.

Observations

C.

Product analysis

D.

Expert judgment

Full Access
Question # 134

Which tool and technique identifies inefficient and ineffective policies, processes, and procedures?

A.

Scope audits

B.

Scope reviews

C.

Quality audits

D.

Control chart

Full Access
Question # 135

The stakeholder register is an output of:

A.

Identify Stakeholders.

B.

Plan Stakeholder Management.

C.

Control Stakeholder Engagement.

D.

Manage Stakeholder Engagement.

Full Access
Question # 136

A project manager is experiencing a project with a high degree of change. Which type of stakeholder engagement does this project require?

A.

Discussing with management

B.

Escalating to the sponsors

C.

Engaging regularly with stakeholders

D.

Engaging only with decision makers

Full Access
Question # 137

Most experienced project managers know that:

A.

every project requires the use of all processes in the PMBOK® Guide.

B.

there is no single way to manage a project.

C.

project management techniques are risk free.

D.

there is only one way to manage projects successfully.

Full Access
Question # 138

Which type of project management office (PMO) supplies templates, best practices, and training to project teams?

A.

Supportive

B.

Directive

C.

Controlling

D.

Instructive

Full Access
Question # 139

Match each Project Cost Management process with its appropriate keyword

Question # 139

Full Access
Question # 140

Which project risk listed in the table below is most likely to occur?

Question # 140

A.

1

B.

2

C.

3

D.

4

Full Access
Question # 141

Who is responsible for initiating a project?

A.

Project sponsor

B.

Project manager

C.

Program manager

D.

Project management office (PMO)

Full Access
Question # 142

Which of the following sets are inputs to the Collect Requirements process?

A.

Project charter and requirements documentation

B.

Project charter and business documents

C.

Project charter and stakeholder requirements

D.

Business documents and requirements traceability matrix

Full Access
Question # 143

What does ’verified’ in verified deliverable represent?

A.

The correctness of a deliverable

B.

The completeness of a deliverable

C.

The deliverable requirements

D.

The customer acceptance of a deliverable

Full Access
Question # 144

A business manager wants to start a project to launch a new product. How should the manager initiate the project?

A.

Ask a small team to produce a prototype of the product before full-scale development.

B.

Assign a project manager to the project and ask them to document the project scope.

C.

Prepare a detailed business case to document project objectives and success criteria.

D.

Discuss the project requirements with the team for alternative products in the market.

Full Access
Question # 145

The scope management plan is a subsidiary of which project document?

A.

Schedule management plan

B.

Project management plan

C.

Quality management plan

D.

Resource management plan

Full Access
Question # 146

Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference?

A.

Compromising

B.

Collaborating

C.

Smoothing

D.

Problem Solving

Full Access
Question # 147

What is the project manager ' s responsibility in Project Integration Management?

A.

Ensuring that requirements-related work is clarified in the project management plan

B.

Investing sufficient effort in acquiring, managing, motivating, and empowering the project team

C.

Combining the results in all other knowledge areas, and overseeing the project as a whole

D.

Developing a strategy to ensure effective stakeholder communication

Full Access
Question # 148

What important leadership quality/qualities should project managers possess?

A.

Skills and behaviors related to specific domains of project management

B.

Skills and behaviors needed to guide a team and help an organization reach its goals

C.

Industry expertise that helps to better deliver business outcomes

D.

Industry and organizational expertise that enhances performance

Full Access
Question # 149

Which type of manager is assigned by the performing organization to lead the team that is responsible for achieving the project objectives?

A.

Program

B.

Functional

C.

Project

D.

Portfolio

Full Access
Question # 150

Which of the following consists of the detailed project scope statement and its associated WBS and WBS dictionary?

A.

Scope plan

B.

Product scope

C.

Scope management plan

D.

Scope baseline

Full Access
Question # 151

What is main purpose of Project Quantity Management?

A.

To meet customer requirements by overworking the team

B.

To fulfill project schedule objectives by rushing planned inspections

C.

To fulfill project requirements of both quality and grade

D.

To exceed customer expectations

Full Access
Question # 152

The project manager is dividing the project scope into smaller pieces, and repeating this process until no more subdivisions are required. At this point the project manager is able to estimate costs and activities for each element.

What are these elements called?

A.

Project activities

B.

Work packages

C.

Planning packages

D.

Project deliverables

Full Access
Question # 153

When is a Salience Model used?

A.

In a work breakdown structure (WBS)

B.

During quality assurance

C.

In stakeholder analysis

D.

During quality control (QC)

Full Access
Question # 154

Which of the following is an output of the Define Activities process?

A.

Activity list

B.

Project plan

C.

Activity duration estimates

D.

Project schedule

Full Access
Question # 155

A project manager needs to tailor the Project Cost Management process. Which considerations should the project manager apply?

A.

Diversity background

B.

Stakeholder ' s relationships

C.

Technical expertise

D.

Knowledge management

Full Access
Question # 156

Two resources are performing a peer review of an artifact. What should be the outcome of the peer review?

A.

All business rules and data requirements for each process are documented.

B.

All relevant business rules for each process are documented.

C.

The resulting documentation adheres to established organizational standards.

D.

The data requirements for each process are documented.

Full Access
Question # 157

When would resource leveling be applied to a schedule model?

A.

Before constraints have been identified

B.

Before it has been analyzed by the critical path method

C.

After it has been analyzed by the critical path method

D.

After critical activities have been removed from the critical path

Full Access
Question # 158

Which Process Group includes the Manage Stakeholder Engagement process?

A.

Executing

B.

Planning

C.

Monitoring and Controlling

D.

Initiating

Full Access
Question # 159

The creation of an internet site to engage stakeholders on a project is an example of which type of communication?

A.

Push

B.

Pull

C.

Interactive

D.

Iterative

Full Access
Question # 160

Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?

A.

Reserve analysis

B.

Three-point estimating

C.

Parametric estimating

D.

Analogous estimating

Full Access
Question # 161

Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project:

A.

manager.

B.

success.

C.

deadline.

D.

scope.

Full Access
Question # 162

Which process includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?

A.

Perform Qualitative Risk Analysis

B.

Perform Quantitative Risk Analysis

C.

Plan Risk Management

D.

Plan Risk Responses

Full Access
Question # 163

At the end of the third iteration, the project team gathers to discuss the stories to be implemented in the next iteration. What should the team do during this session?

A.

Run a spike to ensure all information available is correct and then decide which stories to implement.

B.

Develop a user story analysis based on the work done, depicting the current status, S-curve, schedule variance (SV), and planned value (PV).

C.

Plan the backlog by estimating and reprioritizing the user stories as new information becomes available.

D.

Bring up all risks for implementing the user stories and discuss possible solutions.

Full Access
Question # 164

What risk response strategy involves removing high- risk scope elements from a project?

A.

Transfer

B.

Avoid

C.

Exploit

D.

Accept

Full Access
Question # 165

When does the project team determine which dependencies are discretionary?

A.

Before the Define Activities process

B.

During the Define Activities process

C.

Before the Sequence Activities process

D.

During the Sequence Activities process

Full Access
Question # 166

Given the following information.

Activity A takes one week.

Activity B takes three weeks.

Activity C takes two weeks.

Activity D takes five weeks.

Activity A starts at the same time as Activity B.

Activity C follows Activity B and Activity A.

Activity D follows Activity C.

How long will it take to complete the project?

A.

Eleven weeks

B.

Nine weeks

C.

Eight weeks

D.

Ten weeks

Full Access
Question # 167

Which are required to create the schedule management plan?

A.

Scope baseline, work breakdown structure (WBS), estimated costs, and milestone list

B.

Resource management plan, organizational process assets, activity list, and business case

C.

Enterprise environmental factors, organizational process assets, project charter, and project management plan

D.

Activity list, project statement of work, project charter, and communications management plan

Full Access
Question # 168

Which tools or techniques are used during the Close Project or Phase process?

A.

Reserve analysis and expert judgment

B.

Facilitation techniques and meetings

C.

Expert judgment and analytical techniques

D.

Performance reviews and meetings

Full Access
Question # 169

Which of the following Process Groups covers all nine Project Management Knowledge Areas?

A.

Executing

B.

Monitoring and Controlling

C.

Planning

D.

Initiating

Full Access
Question # 170

An adaptive project manager is migrating the company ' s new website. The project manager must work with the team to invest full capacity on this project because it is the company ' s top-ranked project in the portfolio. In order to increase throughput and provide consistent delivery, the project manager needs to assign members who are currently involved with other projects.

How should the project manager assign the team members to this project?

A.

Task switching

B.

Multitasking

C.

Prediction

D.

Full allocation

Full Access
Question # 171

Which document in the project management plan can be updated in the Plan Procurement Management process?

A.

Budget estimates

B.

Risk matrix

C.

Requirements documentation

D.

Procurement documents

Full Access
Question # 172

A project receives budget approval, but the risk of extra costs is expected. Which of these inputs should the project manager check in order to make a qualitative risk analysis?

A.

The risk management plan and the assumption log

B.

Costs estimates and cost forecast

C.

The risk management plan and the basis of estimates

D.

The assumption log and the project charter

Full Access
Question # 173

Match the life cycle type to when its requirements are defined.

Question # 173

Full Access
Question # 174

The project team is inspecting the completed project scope to determine if the requirements have been satisfied. What is the result of this inspection?

A.

Accepted deliverables

B.

planning packages

C.

Verified deliverables

D.

Work packages

Full Access
Question # 175

The table represents the possible durations of a specific project task.

Using the three-point estimating technique what is the expected number of days it should take to complete the task?

A.

2

B.

3

C.

4

D.

6

Full Access
Question # 176

A project is composed of three phases that are implemented in parallel without affecting one another. The baselines for each individual phase have been approved by the major stakeholders, and there is a minimal ability to vary the baselines during the execution of the project.

Which methodology did the project manager adopt?

A.

Incremental approach

B.

Predictive approach

C.

Hybrid approach

D.

Iterative approach

Full Access
Question # 177

A project manager has recently been assigned a new agile project and needs to determine an appropriate leadership style. The project manager aims to empower the team members so they feel committed and motivated to deliver value.

Which leadership style should be used for this project?

A.

A servant leadership style

B.

A laissez-faire leadership style

C.

A collaborative leadership style

D.

A directive leadership style

Full Access
Question # 178

Agile release planning provides a high-level summary timeline of the release schedule based on.

A.

Activities and story points

B.

Iteration and prioritization plans

C.

Product roadmap and the product vision

D.

Tasks and user stories

Full Access
Question # 179

Which of the following is used as an input to prepare a cost management plan?

A.

Expert judgment

B.

Lessons learned

C.

Cost estimates

D.

Project management plan

Full Access
Question # 180

One of the key benefits of the Plan Human Resource Management process is that it:

A.

outlines team selection guidelines and team member responsibilities.

B.

establishes project roles and responsibilities.

C.

improves teamwork, interpersonal skills, and competencies.

D.

provides an accurate appraisal of team member performance.

Full Access
Question # 181

The following is a network diagram for a project.

Question # 181

The free float for Activity E is how many days?

A.

2

B.

3

C.

5

D.

8

Full Access
Question # 182

Which of the following are components of the technical project management skill?

A.

Ability to explain business aspects of the project, business strategy, goals and objectives, and business value.

B.

Ability to deal with people, to be collaborative, and to apply persuasion and negotiation.

C.

Ability to focus on relationships with people, inspire trust, and implement decisions and actions that support the business strategy.

D.

Ability to plan and prioritize, gather the right artifacts available for each project, and focus on critical success factors.

Full Access
Question # 183

Which of the following is the key construction to controlling the costs and achieving the schedule in projects with high variability?

A.

Learn methods

B.

collaborative teams

C.

Generalizing specialists

D.

Knowledge sharing

Full Access
Question # 184

What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?

A.

Organizational breakdown structure (OBS)

B.

Work performance information

C.

Work package

D.

Work breakdown structure (WBS)

Full Access
Question # 185

A community project with a large number of stakeholders is scheduled for delivery in six months. The project manager asked the business analyst to ensure effective requirements elicitation. What should the business analyst do?

A.

Ask the project coordinator to facilitate some of the workshops.

B.

Invite both internal and external stakeholders to the workshops.

C.

Engage a consultant that is familiar with the community needs.

D.

Organize a workshop with the sponsor and major stakeholders.

Full Access
Question # 186

Which of these is true project integration management?

A.

Project Integration Management is mandatory and more effective in larger projects

B.

Project Integration Management and Expert Judgement are mutually exclusive

C.

Project Integration Management is the responsibility of the project manager

D.

Project Integration Management excludes the triple constraints if cost performance index (CPI) equals zero

Full Access
Question # 187

Inputs to the Plan Risk Management process include the:

A.

cost management plan.

B.

risk management plan,

C.

activity list,

D.

risk register.

Full Access
Question # 188

Which of the following project documents is an input to the Control Scope process?

A.

Vendor risk assessment diagram

B.

Risk register

C.

Requirements traceability matrix

D.

Area of responsibility summary

Full Access
Question # 189

Which Manage Communications tool or technique focuses on identifying and managing barriers?

A.

Communication methods

B.

Information technology

C.

Communication models

D.

Information management systems

Full Access
Question # 190

The product scope description is used to:

A.

Gain stakeholders ' support for the project.

B.

Progressively elaborate the characteristics of the product, service, or result.

C.

Describe the project in great detail.

D.

Define the process and criteria for accepting a completed product, service, or result.

Full Access
Question # 191

Which of the following lists represents the outputs of the Monitor Communications process?

A.

Project communications, project management plan updates, project documents updates, and organizational process assets updates

B.

Work performance information, change requests, project management plan updates, and project documents updates

C.

Communications management plan, project management plan updates, work performance report, and project documents update

D.

Stakeholder engagement plan, change requests, project management plan updates, and project documents updates

Full Access
Question # 192

During the execution phase of a multibillion-dollar project, the project manager encountered performance issues with some of the team members. In a performance review meeting, the project manager noticed that the team members do not follow SMART objectives.

What are SMART objectives?

A.

Specific, measurable, accurate, relevant, and time-bound.

B.

Specific, measurable, achievable, relevant, and time-bound.

C.

Specific, measurable, accurate, realistic, and time-bound.

D.

Specific, measurable, achievable, realistic, and time-bound.

Full Access
Question # 193

The process of identifying and documenting relationships among the project activities is known as:

A.

Control Schedule.

B.

Sequence Activities.

C.

Define Activities.

D.

Develop Schedule.

Full Access
Question # 194

A project manager has to share a status report with a new stakeholder and is trying to determine the level of detail to include in the report. Which document best details the information the project manager needs lo make this decision?

A.

Organizational process assets

B.

Change management plan

C.

Communications management plan

D.

Resource management plan

Full Access
Question # 195

Which of the following Project Communication Management processes uses performance reports as an input?

A.

Manage Stakeholder Expectations

B.

Report Performance

C.

Distribute Information

D.

Plan Communications

Full Access
Question # 196

What are the two most common contract types used in a project?

A.

Cost plus award fee (CPAF) contract and fixed price contract

B.

Fixed price contract and cost-reimbursable contract

C.

Cost-reimbursable contract and time and material (TandM) contract

D.

Time and material (TandM) contract and cost plus award fee (CPAF) contract

Full Access
Question # 197

Which of the following does a portfolio combine?

A.

Projects, programs, and operations

B.

Operations, strategies, and business continuity

C.

Projects, programs, and risks

D.

Projects, change management, and operations

Full Access
Question # 198

Which process documents the business needs of a project and the new product, service, or other result that is intended to satisfy those requirements?

A.

Develop Project Management Plan

B.

Develop Project Charter

C.

Direct and Manage Project Execution

D.

Collect Requirements

Full Access
Question # 199

Which provides the basic framework for managing a project?

A.

Project life cycle

B.

Work breakdown structure (WBS)

C.

Enterprise environmental factors

D.

Project initiation

Full Access
Question # 200

Control charts, flowcharting, histograms, Pareto charts, and scatter diagrams are tools and techniques of which process?

A.

Perform Quality Control

B.

Perform Quality Assurance

C.

Plan Quality

D.

Report Performance

Full Access
Question # 201

Which type of elaboration allows a project management team to manage at a greater level of detail as the project evolves?

A.

Cyclic

B.

Progressive

C.

Repetitive

D.

Iterative

Full Access
Question # 202

In which Project Cost Management process is work performance data included?

A.

Plan Cost Management

B.

Estimate Costs

C.

Determine Budget

D.

Control Costs

Full Access
Question # 203

Analogous cost estimating relies on which of the following techniques?

A.

Expert judgment

B.

Project management software

C.

Vendor bid analysis

D.

Reserve analysis

Full Access
Question # 204

A company must implement sales software because it is opening a new branch in a foreign market. Although this software is used in every domestic branch, multiple changes are expected during the implementation because It is a foreign location.

Which type of life cycle would the project manager use in this case?

A.

Predictive life cycle

B.

Waterfall life cycle

C.

Hybrid life cycle

D.

Product life cycle

Full Access
Question # 205

When calculating the cost of quality (COQ) for a product or service, money spent for cost of conformance would include the areas of:

A.

training, testing, and warranty work.

B.

equipment, rework, and scrap.

C.

training, document processes, and inspections.

D.

inspections, rework, and warranty work.

Full Access
Question # 206

Which tool or technique is used in the Develop Project Management Plan process?

A.

Pareto diagram

B.

Performance reporting

C.

SWOT analysis

D.

Expert judgment

Full Access
Question # 207

Which is an input to the Verify Scope process?

A.

Performance report

B.

Work breakdown structure (WBS)

C.

Requested changes

D.

Project management plan

Full Access
Question # 208

Which item is an example of personnel assessment?

A.

Resource calendar

B.

Tight matrix

C.

Team-building activity

D.

Focus group

Full Access
Question # 209

The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline is:

A.

Determine Budget.

B.

Baseline Budget.

C.

Control Costs.

D.

Estimate Costs.

Full Access
Question # 210

Which additional considerations should the project manager make when managing risks in an agile/adaptive project?

A.

Add more risk categories

B.

Identify, analyze, and manage risk during each iteration of the project

C.

Add new values to the probability and impact matrix

D.

Increase the reserves because of the high variability environment

Full Access
Question # 211

The primary benefit of the Plan Schedule Management process is that it:

A.

provides guidance to identify time or schedule challenges within the project.

B.

tightly links processes to create a seamless project schedule.

C.

guides how the project schedule will be managed throughout the project.

D.

creates an overview of all activities broken down into manageable subsections.

Full Access
Question # 212

A software team has completed a critical feature and demonstrated it to the project sponsor.

What kind of stakeholder communication was used in this scenario?

A.

Informal written

B.

Formal verbal

C.

Formal written

D.

Informal verbal

Full Access
Question # 213

A project manager should document the escalation path for unresolved project risks in the:

A.

Change control plan

B.

Stakeholder register

C.

Risk log

D.

Communications management plan

Full Access
Question # 214

Which is the best way for a project manager to ensure efficient and frequent communication with management and stakeholders in an agile/adaptive environment?

A.

Post project artifacts in a transparent fashion and engage stakeholders on a regular basis.

B.

Make surveys among the stakeholders and meet with the team once a month.

C.

Create a social network and post news there.

D.

Create personalized emails for each stakeholder, asking for requests and reviewing objectives with them periodically.

Full Access
Question # 215

Which tasks should a project manager perform in order to manage the project schedule effectively?

A.

Plan Schedule Management, Define Activities, Sequence Activities, Estimate Activity Durations, Define Quality of Activities. Develop Schedule

B.

Plan Schedule Management. Define Activities, Sequence Activities, Estimate Activity Durations, Develop Schedule. Control Schedule

C.

Plan Schedule Management. Define Activities, Sequence Activities, Estimate Activity Durations, Estimate Cost of Activities. Develop Schedule

D.

Define Activities. Sequence Activities, Estimate Activity Durations. Define Quality of Activities. Estimate Cost of Activities, Develop Schedule

Full Access
Question # 216

Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?

A.

Cost variance (CV)

B.

Cost performance index (CPI)

C.

Budget at completion (BAC)

D.

Variance at completion (VAC)

Full Access
Question # 217

Which group of inputs will a project manager use during the Monitor Stakeholder Engagement process?

A.

Project charter, business documents, and project management plan

B.

Agreements, scope baseline, and project management plan

C.

Project charter, business case, and project management plan

D.

Work performance data, enterprise environmental factors, and project management plan

Full Access
Question # 218

Which process develops options and actions to enhance opportunities and reduce threats to project objectives?

A.

Identify Risks

B.

Control Risks

C.

Plan Risk Management

D.

Plan Risk Responses

Full Access
Question # 219

A project manager is working on the communications management plan. Which of these documents are inputs to consider?

A.

Stakeholder engagement plan and organizational process assets

B.

Project schedule and stakeholder register

C.

Quality management plan and risk register

D.

Basis of estimates and scope baseline

Full Access
Question # 220

Which of the following is an input to Control Scope?

A.

Project schedule

B.

Organizational process assets updates

C.

Project document updates

D.

Work performance information

Full Access
Question # 221

Given the following information, what is the schedule variance (SV) for this project?

Early start date (ES): 16 weeks

Actual time: 12 weeks

Schedule performance index (SPI): 1.3

A.

5

B.

2

C.

3

D.

4

Full Access
Question # 222

At which point of the project is the uncertainty the highest and the risk of failing the greatest?

A.

Final phase of the project

B.

Start of the project

C.

End of the project

D.

Midpoint of the project

Full Access
Question # 223

Recently, the government published a new tax law giving companies one year to implement the changes. A project was initiated to change the accounting system. Which delivery approach is most suitable in this context?

A.

Predictive, because of the high risk that the company can be fined.

B.

Predictive, because the requirements are clearly defined up-front.

C.

Adaptive, because the government will provide constant feedback.

D.

Adaptive, because the changes have never been implemented before.

Full Access
Question # 224

Which tools or techniques will a project manager use for Develop Project Team?

A.

Negotiation

B.

Roles and responsibilities

C.

Recognition and rewards

D.

Prizing and promoting

Full Access
Question # 225

Which of the following strategies is used to deal with risks that may have a negative impact on project objectives?

A.

Exploit

B.

Share

C.

Enhance

D.

Transfer

Full Access
Question # 226

Which statement correctly describes the value of a business case?

A.

It provides the necessary information to determine if a project is worth the required investment.

B.

It provides for alternative dispute resolution procedures in event of contract default.

C.

It offers one of several alternative scenarios which assist in performing qualitative risk analysis.

D.

It is used to help a project manager understand the scope of commercial advantages.

Full Access
Question # 227

What causes replanning of the project scope?

A.

Project document updates

B.

Project scope statement changes

C.

Variance analysis

D.

Change requests

Full Access
Question # 228

What are the formal and informal policies, procedures, and guidelines that could impact how the project ' s scope is managed?

A.

Organizational process assets

B.

Enterprise environmental factors

C.

Project management processes

D.

Project scope management plan

Full Access
Question # 229

A project manager is working in an environment where requirements are not very clear and may change during the project. In addition, the project has several stakeholders and is technically complex.

Which strategies should the project manager take to account for risk management n this environment’

A.

Occasionally identify evaluate, and classify risks

B.

Review requirements and cross-functional project teams.

C.

Include contingency reserves and update the project management plan frequently.

D.

Frequently review incremental work products and update the requirements for proper prioritization.

Full Access
Question # 230

What does earned value (EV) measure?

A.

Budgeted work that has been completed

B.

Total costs incurred while accomplishing work

C.

Budget associated with planned work

D.

Cost efficiency of budgeted resources

Full Access
Question # 231

In a preliminary meeting for a project, team members decide to execute the project with methodology A finance team member wants to know how project cost will be determined at this early stage. How will the project team determine project cost?

A.

Use a lightweight cost estimation due to the nature of angile projects.

B.

Use a detailed cost estimation for agile projects.

C.

Retrieve a dudget from a previous project and create a baseline of this project based on it.

D.

Use a detailed work breakdown structure (WBS) to get cost estimation.

Full Access
Question # 232

Which process numerically analyzes the effect of identified risks on overall project objectives?

A.

Plan Risk Management

B.

Plan Risk Responses

C.

Perform Quantitative Risk Analysis

D.

Perform Qualitative Risk Analysis

Full Access
Question # 233

What are the key tools for managing project knowledge?

A.

Expert judgment and data gathering

B.

Networking and storytelling

C.

Data analysis and decision making

D.

Prototypes and product analysis

Full Access
Question # 234

Using the three-point estimating technique, if the most likely duration is four months, the optimistic duration is two months, and the pessimistic duration is one year, how many months is the expected activity duration?

A.

Two

B.

Four

C.

Five

D.

Twelve

Full Access
Question # 235

In a construction project schedule, what is the logical relationship between the delivery of the concrete materials and the pouring of concrete?

A.

Start-to-start (SS)

B.

Start-to-finish (SF)

C.

Rnish-to-finish (FF)

D.

Finish-to-start (FS)

Full Access
Question # 236

Which term describes an assessment of correctness?

A.

Accuracy

B.

Precision

C.

Grade

D.

Quality

Full Access
Question # 237

In the project charter process, which three of the following are discussed during meetings held with stakeholders? (Choose three) D Cost

A.

High-level deliverables

B.

Success criteria

C.

Project objectives

D.

Phase transitions

Full Access
Question # 238

Which Knowledge Areas include processes from the Closing Process Group?

A.

Project Quality Management and Project Time Management

B.

Project Scope Management and Project Risk Management

C.

Project Stakeholder Management and Project Cost Management

D.

Project Integration Management and Project Procurement Management

Full Access
Question # 239

The project manager is creating the communications management plan Which group of inputs Is required to begin?

A.

Work performance reports, change requests, and risk register

B.

Work performance data, project documents, and stakeholder engagement plan

C.

Project charter, project management plan, and project documents

D.

Work performance data, stakeholder register, and team management plan

Full Access
Question # 240

Which type of contract is most commonly used by buying organizations because the price for goods is set at the outset and is not subject to change unless the scope of work changes?

A.

Fixed Price with Economic Price Adjustments Contract (FP-EPA)

B.

Cost-Reimbursable Contract (CR)

C.

Firm-Fixed -Price Contract (FFP)

D.

Fixed-Price-Incentive-Fee Contract (FPIF)

Full Access
Question # 241

Lessons learned are created and project resources are released in which Process Group?

A.

Planning

B.

Executing

C.

Closing

D.

Initiating

Full Access
Question # 242

Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?

A.

The risk of achieving the shortened project time is increased.

B.

The critical path will have positive total float.

C.

Contingency reserves are released for redeployment by the project manager.

D.

Duration buffers are added to maintain a focus on planned activity durations.

Full Access
Question # 243

A project manager is assigned to a new project with a defined scope. The project requires advanced planning at the start of the project. Which approach should the project manager select for the project?

A.

Predictive

B.

Hybrid

C.

Kanban

D.

Adaptive

Full Access
Question # 244

An output of the Perform Integrated Change Control process is:

A.

Deliverables.

B.

Validated changes.

C.

The change log.

D.

The requirements traceability matrix.

Full Access
Question # 245

On which type of project.... only after the final iteration?

On wtiich type of project lite cycle is ihe deliverable produced trough a series of ileralrons considering thai the deliverable ts completed only after the Imal iteration?

A.

Incremental life cycle

B.

Predictive life cycle

C.

Iterative life cycle

D.

Adaptive life cycle

Full Access
Question # 246

Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance index (SPI), or any performance status to stakeholders?

A.

Performance organizations

B.

Schedule baselines

C.

Work performance measurements

D.

Change requests

Full Access
Question # 247

Which of the following is provided by the critical path method?

A.

Schedule float

B.

Earned value (EV)

C.

Total float

D.

Schedule value

Full Access
Question # 248

Which quality control technique illustrates the 80/20 principle?

A.

Ishikawa diagram

B.

Control chart

C.

Run chart

D.

Pareto chart

Full Access
Question # 249

An input to the Plan Procurement Management process is:

A.

Source selection criteria.

B.

Market research.

C.

A stakeholder register.

D.

A records management system.

Full Access
Question # 250

A project manager is formalizing acceptance of the completed project deliverables. What is an input to this process?

A.

Verified deliverables

B.

Validated deliverables

C.

Accepted deliverables

D.

Completed change requests

Full Access
Question # 251

What is a tailoring consideration for the application of Project Risk Management processes?

A.

Project complexity

B.

Procurement criteria

C.

Communication technology

D.

Knowledge management

Full Access
Question # 252

Following a project planning meeting with the team, a few team members approach the project manager to follow up on actions required. How can the project manager assess the effectiveness of the meeting?

A.

Send the meeting minutes to all team members to verify that the required information is readily available.

B.

Ask the team members to provide feedback for meetings in the phase retrospective.

C.

Review the actions from the meeting with each of the project team members to ensure their understanding.

D.

Consult the communications management plan to determine the success criteria for meetings.

Full Access
Question # 253

When closing a project or phase, part of the process may require the use of which type of analysis?

A.

Reserve analysis

B.

Regression analysis

C.

Document analysis

D.

Product analysis

Full Access
Question # 254

Which is the tool or technique that is used to obtain the list of activities from the work packages?

A.

Data analysis

B.

Leads and lags

C.

Precedence diagramming method

D.

Decomposition

Full Access
Question # 255

A business analyst is evaluating solutions against the expected results and logging defects along the way. The next task is to analyze the discrepancies prior to facilitating a go/no-go decision.

Which technique should be used as a starting point to uncover problem areas?

A.

Elicitation

B.

Opportunity analysis

C.

Cost-benefit analysis

D.

Feasibility analysis

Full Access
Question # 256

An element of the modern quality management approach used to achieve compatibility with the International Organization for Standardization (ISO) is known as:

A.

Forecasting,

B.

Brainstorming.

C.

Historical databases.

D.

Cost of quality.

Full Access
Question # 257

Which cost is associated with nonconformance?

A.

Liabilities

B.

Inspections

C.

Training

D.

Equipment

Full Access
Question # 258

Which conflict resolution technique produces the most lasting results?

A.

Withdraw/avoid

B.

Smooth/accommodate

C.

Compromise/reconcile

D.

Collaborate/problem solve

Full Access
Question # 259

Which of the following is a tool or technique used in the Determine Budget process?

A.

Variance analysis

B.

Three-point estimating

C.

Bottom-up estimating

D.

Historical relationships

Full Access
Question # 260

In the Define Activities process, the schedule management plan is used to:

A.

Capture the lessons learned from other projects for comparison.

B.

Contain the standard activity list.

C.

Document and support the project change requests.

D.

Prescribe the level of detail needed to manage the work.

Full Access
Question # 261

Which of the following are outputs of the Define Scope process in Project Scope Management?

A.

Requirements documentation and requirements traceability matrix

B.

Scope management plan and requirements management plan

C.

Project scope statement and project documents updates

D.

Scope baseline and project documents updates

Full Access
Question # 262

Definitions of probability and impact, revised stakeholder tolerances, and tracking are components of which subsidiary plan?

A.

Cost management plan

B.

Quality management plan

C.

Communications management plan

D.

Risk management plan

Full Access
Question # 263

A project manager engages a highly specialized resource who is in a different location and cannot join the regular team meetings. This is leading to delays in productivity. How can the project manager assist the team to resolve the issue?

A.

Request the new resource be relocated with the rest of the team and document a change request forthe project.

B.

Ask the team to identify possible options to resolve the issue with minimal impact to the new resource.

C.

Log this issue in the issue log and escalate it to the management team, asking them to replace the new team member.

D.

Consult the communications management plan to review available options, such as special virtual meetings, with the new resource.

Full Access
Question # 264

Which of the following is a tool and technique used to monitor risk?

A.

Technical performance measurement

B.

Cost performance baseline

C.

Benchmarking

D.

Cost of quality

Full Access
Question # 265

The diagram below is an example of a:

A.

Risk breakdown structure (RBS).

B.

Project team.

C.

SWOT Analysis.

D.

Work breakdown structure (WBS).

Full Access
Question # 266

The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project has been undertaken to achieve are grouped within which Process Group?

A.

Initiating

B.

Planning

C.

Executing

D.

Monitoring and Controlling

Full Access
Question # 267

Which process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?

A.

Estimate Costs

B.

Control Costs

C.

Determine Budget

D.

Plan Cost Management

Full Access
Question # 268

A construction project is underway, and during... tasks impacted the painting work

A construction project is underway, and during the progress review the painter complained that the task could not be started because the mason has not finished the plastering job What kind ot relationship between the tasks impacted the painting work?

A.

Finish-to-Finish (FF)

B.

Start-to-Finish (SF)

C.

Finish-to-Start(FS)

D.

Start-to-Slart(SS)

Full Access
Question # 269

A project manager can choose from several techniques to resolve conflicts between team members. Which technique can result in a win-win solution?

A.

Collaborate/Problem Solve

B.

Compromise/Reconcile

C.

Smooth/Accommodate

D.

Withdraw/Avoid

Full Access
Question # 270

What behavior refers to leadership style?

A.

Do things right.

B.

Do the right things

C.

Ask how and when.

D.

Rely on control

Full Access
Question # 271

Which item is a cost of conformance?

A.

Training

B.

Liabilities

C.

Lost business

D.

Scrap

Full Access
Question # 272

In project management, a temporary project can be:

A.

Completed without planning

B.

A routine business process

C.

Long in duration

D.

Ongoing to produce goods

Full Access
Question # 273

Make-or-buy analysis is a tool and technique of which process?

A.

Conduct Procurements

B.

Plan Procurement Management

C.

Analyze Procurements

D.

Control Procurements

Full Access
Question # 274

Enterprise environmental factors are an input to which process?

A.

Control Scope

B.

Define Scope

C.

Plan Scope Management

D.

Collect Requirements

Full Access
Question # 275

A tool and technique used during the Define Scope process is:

A.

facilitated workshops.

B.

observations.

C.

questionnaires and surveys.

D.

group creativity techniques.

Full Access
Question # 276

Conflict should be best addressed in which manner?

A.

Early, in private, using a direct, collaborative approach

B.

Early, in public, using an indirect, collaborative approach

C.

Early, in private, using an indirect, cooperative approach

D.

As late as possible, in public, using a direct, confrontational approach

Full Access
Question # 277

Which of the following describes the similarities of the process groups and project life cycle?

A.

The life cycle involves three project management process groups.

B.

Both provide a basic framework to manage the project.

C.

Each project must have a life cycle and all processes in the five process groups.

D.

The project life cycle is managed by executing the processes within the five process groups.

Full Access
Question # 278

Which of the following is an example of tacit knowledge

A.

Risk register

B.

Project requirements

C.

Expert judgment

D.

Make-or-buy analysis

Full Access
Question # 279

A business analyst sent multiple meeting requests via instant message to a subject matter expert (SME) working in another country but did not receive a response. What should the business analyst do to reduce the likelihood of this occurring in the future with other stakeholders distributed across multiple locations?

A.

Ask each stakeholder for their preferred communication method.

B.

Confirm the time zone and work days in each location.

C.

Check with the IT department to see if there is a technical issue.

D.

Assume the meeting request is accepted unless declined.

Full Access
Question # 280

Which type of contract gives both the seller and the buyer flexibility to deviate from performance with financial incentives?

A.

Cost Plus Incentive Fee (CPIF)

B.

Fixed Price Incentive Fee (FPIF)

C.

Cost Pius Award Re (CPAF)

D.

Time and Material (TandM)

Full Access
Question # 281

Testing falls into which of the following categories of cost of quality?

A.

Internal failure costs

B.

Prevention costs

C.

Appraisal costs

D.

External failure costs

Full Access
Question # 282

A change log for communications can be used to communicate to the appropriate stakeholders that there are changes:

A.

To the project management plan.

B.

To the risk register.

C.

In the scope verification processes.

D.

And their impact to the project in terms of time, cost, and risk.

Full Access
Question # 283

The milestone list is an input to which process from the Planning Process Group?

A.

Define Activities

B.

Estimate Activity Durations

C.

Estimate Activity Resources

D.

Sequence Activities

Full Access
Question # 284

Outputs of the Control Communications process include:

A.

expert judgment and change requests.

B.

work performance information and change requests.

C.

organizational process asset updates and an issue log.

D.

project management plan updates and an issue log.

Full Access
Question # 285

When addressing roles and responsibilities,which item ensures that the staff has the skills required to complete project activities?

A.

Authority

B.

Role

C.

Competency

D.

Responsibility

Full Access
Question # 286

Which cost estimate technique includes contingencies to account for cost uncertainty?

A.

Vendor bid analysis

B.

Three-point estimates

C.

Parametric estimating

D.

Reserve analysis

Full Access
Question # 287

Company A has just been notified about a new legal requirement for its business operations. What is the classification of this item?

A.

Internal enterprise environmental factor

B.

Risk register database

C.

External enterprise environmental factor

D.

Organizational process asset

Full Access
Question # 288

A project team is tasked with decomposing the scope to enable detailed cost and duration estimates. What should the team do to achieve this requirement?

A.

Prepare a WBS with task sequencing and detail the duration and cost estimates.

B.

Prepare a WBS to work package level to effectively manage duration and cost estimates.

C.

Prepare a WBS for immediate tasks in the plan to work package level for duration and cost estimates.

D.

Prepare a work breakdown structure (WBS) to include each deliverable with a target duration and cost estimate.

Full Access
Question # 289

In which type of organization does the project manager have the maximum influence

A.

Centralized

B.

Composite

C.

Simple Organic

D.

Multi-divisional

Full Access
Question # 290

The scope of a project cannot be defined without some basic understanding of how to create the specified:

A.

objectives

B.

schedule

C.

product

D.

approach

Full Access
Question # 291

Which document includes the project scope, major deliverables, assumptions, and constraints?

A.

Project charter

B.

Project scope statement

C.

Scope management plan

D.

Project document updates

Full Access
Question # 292

In which process might a project manager use risk reassessment as a tool and technique?

A.

Perform Qualitative Risk Analysis

B.

Monitor and Control Risk

C.

Monitor and Control Project Work

D.

Plan Risk Responses

Full Access
Question # 293

Which process should be conducted from the project inception through completion?

A.

Monitor and Control Project Work

B.

Perform Quality Control

C.

Perform Integrated Change Control

D.

Monitor and Control Risks

Full Access
Question # 294

Which Knowledge Area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?

A.

Project Integration Management

B.

Project Communications Management

C.

Project Information Management System (PIMS)

D.

Project Scope Management

Full Access
Question # 295

Which of the following characteristics are found in a functional organizational structure?

A.

Little or no project manager authority, little or no resource availability, and the functional manager controls the project budget

B.

Limited project manager authority, limited resource availability, and a part-time project manager ' s role

C.

Low to moderate project manager authority, low to moderate resource availability, and a full-time project manager ' s role

D.

High to almost total project manager authority, high to almost total resource availability, and full-time project management administrative staff

Full Access
Question # 296

What can a project1 manager review to understand the status of project?

A.

Work breakdown structure (WBS) status

B.

Quality and technical performance measures

C.

Cost and scope baselines

D.

Business case completeness

Full Access
Question # 297

In which type of contract are the performance targets established at the onset and the final contract price determined after completion of all work based on the sellers performance?

A.

Firm-Fixed-Price (FFP)

B.

Fixed Price with Economic Price Adjustments (FP-EPA)

C.

Fixed-Price-Incentive-Fee (FPIF)

D.

Cost Plus Fixed Fee (CPFF)

Full Access
Question # 298

The process of monitoring the status of the project to update project progress and manage changes to the schedule baseline is:

A.

Control Schedule.

B.

Quality Control.

C.

Perform Integrated Change Control.

D.

Develop Schedule.

Full Access
Question # 299

Select three processes that are associated with Project Schedule Management.

A.

Define Activities

B.

Plan Resource Management

C.

Estimate Activity Durations

D.

Develop Schedule

E.

Acquire Resources

Full Access
Question # 300

The process of prioritizing risks for further analysis or action is known as:

A.

Plan Risk Management.

B.

Plan Risk Responses.

C.

Perform Qualitative Risk Analysis.

D.

Perform Quantitative Risk Analysis.

Full Access
Question # 301

A project manager was assigned to a project with high uncertainty. What is the recommended method to calculate the project budget?

A.

Detailed estimation

B.

Lightweight estimation

C.

Parametric estimation

D.

A mix of them

Full Access
Question # 302

What name(s) is (are) associated with the Plan-Do-Check-Act cycle?

A.

Pareto

B.

Ishikawa

C.

Shewhart-Deming

D.

Delphi

Full Access
Question # 303

Which of the following is a goal of the project charter?

A.

Detail requirements for the project tasks.

B.

Empower the project manager to manage the project.

C.

List all tasks the team should perform in the project.

D.

Develop a business case to support the project.

Full Access
Question # 304

What is the first step in the Stakeholder Management process?

A.

Plan Stakeholder Engagement

B.

Identify Stakeholders

C.

Manage Stakeholder Responsibility

D.

Monitor Stakeholder Activity

Full Access
Question # 305

Why is tailoring in a project necessary?

A.

Requirements keep changing.

B.

An artifact must be produced.

C.

A tool or technique is required.

D.

Each project is unique.

Full Access
Question # 306

Which three techniques can be estimate costs?

A.

Financing, bottom-up estimating, and expert judgment

B.

Cost aggregation, analogous estimating, and financing

C.

Expert judgment, financing, and cost aggregation

D.

Expert judgment, analogous estimating, and bottom-up estimating

Full Access
Question # 307

Which Process Group contains those processes performed to define a new project?

A.

Initiating

B.

Planning

C.

Executing

D.

Closing

Full Access
Question # 308

A new business analyst has joined the team in the middle of a project and the requirements traceability matrix has been updated. What should the business analyst do next?

A.

Review the project management plan.

B.

Share the requirements traceability matrix the same way it was shared previously.

C.

Consult the business analysis communications management plan.

D.

Ask the project manager to share the updated requirements traceability matrix at the next meeting.

Full Access
Question # 309

A project team is working on relocating offices to another building and providing new furniture. The new furniture was purchased from an international vendor. The price was negotiated in a foreign currency, and due to changes in the exchange rate, the cost has increased by 10%. There is no contingency in the project budget. What should the project manager do?

A.

Escalate this issue to the project management office (PMO).

B.

Escalate this issue to the chief financial officer (CFO).

C.

Escalate this issue to the procurement team.

D.

Escalate this issue to the project sponsor.

Full Access
Question # 310

Which of the following is part of the project sponsor ' s responsibility?

A.

Monitoring the business value

B.

Advocating the business value

C.

Tracking the business value

D.

Auditing the business value

Full Access
Question # 311

Which is the correct hierarchy in a project environment, from most to least Inclusive?

A.

Projects, portfolios, then programs

B.

Portfolios, programs, then projects

C.

Portfolios, projects, then programs

D.

Projects, programs, then portfolios

Full Access
Question # 312

Which process uses expert judgment to manage project resources?

A.

Plan Resource Management

B.

Estimate Activity Resources

C.

Manage Team

D.

Both A and B

Full Access
Question # 313

Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?

A.

Risk and uncertainty increase; the cost of changes increases.

B.

Risk and uncertainty increase; the cost of changes decreases,

C.

Risk and uncertainty decrease; the cost of changes increases.

D.

Risk and uncertainty decrease; the cost of changes decreases.

Full Access
Question # 314

During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?

A.

Monitor and Control Project Work

B.

Perform Quality Assurance

C.

Close Project or Phase

D.

Control Scope

Full Access
Question # 315

Which of the following is a category of organizational process assets?

A.

Government standards

B.

Organizational culture

C.

Employee capabilities

D.

Organizational knowledge bases

Full Access
Question # 316

The risk shared between the buyer and seller is determined by the:

A.

assumption log.

B.

quality checklist.

C.

risk register.

D.

contract type.

Full Access
Question # 317

Which project life cycle follows a plan reviewed and approved by the stakeholders?

A.

Predictive

B.

Adaptive

C.

Iterative

D.

Incremental

Full Access
Question # 318

The project manager is new to the company in order to effectively manage the project, which components of the organizational governance framework does the project manager need to take into account?

A.

Organizational structure type, Key stakeholders, and protect funds

B.

Rules. policies and norms

C.

Project management software, resources availability and risk checklist

D.

Governance elements, team policies, and organizational goals

Full Access
Question # 319

A team was hired to develop a next generation drone. The team created a prototype and sent it to the customer for testing. The feedback collected was used to refine the requirements. What technique is the team using?

A.

Early requirements gathering

B.

Feedback analysis

C.

Progressive elaboration

D.

Requirements documentation

Full Access
Question # 320

What is an emerging practice in stakeholder engagement?

A.

Confirming that all identified stakeholders are engaged and actually affected by the work

B.

Assuring that team leadership is primarily involved in stakeholder engagement

C.

Ensuring that stakeholders do not change after stakeholder identification

D.

Ensuring that stakeholders most affected by the work are involved as collaborative team partners

Full Access
Question # 321

In an agile and adaptive project, which scope management entity invokes stakeholder engagement?

A.

Collect Requirements

B.

Create work breakdown structure (WBS)

C.

Plan Scope Management

D.

Scope Baseline

Full Access
Question # 322

Which Control Stakeholder Engagement tool or technique allows the project manager to consolidate and facilitate distribution of reports?

A.

Information management systems

B.

Work performance reports

C.

Stakeholder analysis

D.

Data gathering and representation

Full Access
Question # 323

When should Project Risk Management be conducted?

A.

Project Planning

B.

Monitoring and Controlling

C.

Quality Planning

D.

Throughout the project lifecycle

Full Access
Question # 324

The project manager is working in the processes of Project Resource Management. Which process is the project manager developing if they are using parametric estimation?

A.

Plan Resource Management

B.

Estimate Activity Resources Communications

C.

Estimate Costs

D.

Acquire Resources

Full Access
Question # 325

Which process is engaged when a proiect learn inember makes a change to project budget with the project manager ' s approval?

A.

Manage Cost Plan

B.

Estimate Costs

C.

Determine Budget

D.

Control Costs

Full Access
Question # 326

How does planning for prevention costs assist in meeting stakeholder needs and expectations, while still providing required performance and reliability?

A.

It details product or service failures experienced by the customer

B.

It clarifies the costs associated with assessing the quality of the product or service

C.

It accounts for costs used to avoid poor quality in the product or service

D.

It communicates product or service failures discovered by the project team

Full Access
Question # 327

Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project?

A.

Project Risk Management

B.

Project Human Resource Management

C.

Project Scope Management

D.

Project Stakeholder Management

Full Access
Question # 328

Analytical techniques are a tool and technique of which process in Project Procurement Management?

A.

Plan Procurement Management

B.

Control Procurements

C.

Conduct Procurements

D.

Close Procurements

Full Access
Question # 329

An input used in developing the communications management plan is:

A.

Communication models.

B.

Enterprise environmental factors.

C.

Organizational communications,

D.

Organizational cultures and styles.

Full Access
Question # 330

A company has implemented an adaptive project management framework for a new project. When planning for an iteration, how should risks be addressed? Choose two.

A.

Risks should be considered when selecting the content of each iteration.

B.

Risks should be tailored for each iteration.

C.

Risks should be identified, analyzed, and managed during each iteration.

D.

Risks should be documented prior to each iteration.

E.

Risks should be reviewed only once during each iteration.

Full Access
Question # 331

In the business analysis aspect of a construction project, what is the purpose of the requirements validation process?

A.

Ensures a thorough unit test case coverage

B.

Ensures an accurate reflection of the stakeholders ' intentions

C.

Ensures that the business problem is solved

D.

Ensures the successful delivery of business value

Full Access
Question # 332

Through whom do project managers accomplish work?

A.

Consultants and stakeholders

B.

Stakeholders and functional managers

C.

Project team members and consultants

D.

Project team members and stakeholders

Full Access
Question # 333

A project manager is working with the project sponsor to identify the resources required for the project. They use a RACI chart to ensure that the team members know their roles and responsibilities. What are the four elements of a RACI chart?

A.

Recommend, accountable, consult, and inform

B.

Responsible, accountable, consult, and inform

C.

Recommend, approve, coordinate, and inform

D.

Responsible, accountable, coordinate, and inform

Full Access
Question # 334

An adaptive team is working on a mobile banking application. The team conducted their sprint demo, which included 12 stories that were completed. This was the last sprint before the product was to be launched in the beta phase. One of the attendees from marketing noticed that a requested enhancement to share on social media was still in the product backlog.

Why was the product still determined to be ready for delivery?

A.

The development team ran out of time and did not pull the social media story from the backlog.

B.

The development team completed all of the stories identified by the product owner as having the highest customer value.

C.

The sprint demo went smoothly and the team did not find any open issues.

D.

The social media story is a marketing priority and less important than other priorities.

Full Access
Question # 335

Which three of the following are key traits of a project leader? (Choose three)

A.

Rely on control.

B.

Focus on near-team goals.

C.

Convey trust and inspire trust in other team members.

D.

Challenge the status quo and do things differently.

E.

Focus on the horizon.

Full Access
Question # 336

A project sponsor has asked the project manager to determine how soon the project can be completed. Which of the following methods can a project manager use to find this information?

A.

Scope baseline

B.

Decomposition

C.

Critical path method (CPM)

D.

Work breakdown structure (WBS)

Full Access
Question # 337

Taking out insurance in relation to risk management is called what?

A.

Transference

B.

Avoidance

C.

Exploring

D.

Mitigation

Full Access
Question # 338

During the requirements verification process, stakeholders are finding many errors in the requirements definition. What could the business analyst have done to avoid these errors?

A.

Asked the stakeholders to write the requirements themselves

B.

Included the project manager in the elicitation sessions

C.

Confirmed the elicitation results after sessions

D.

Updated the requirements traceability matrix

Full Access
Question # 339

Which of the following can a project manager use to represent dellned team member roles in a group of tasks?

A.

Work breakdown structure (WBS)

B.

Responsibility assignment matrix (RAM)

C.

Organizational breakdown structure (OBS)

D.

Resource breakdown structure (RBS)

Full Access
Question # 340

When painting a bedroom, preparing the walls can be done while the paint is being chosen. This is an example of a:

A.

lead

B.

lag

C.

mandatory dependency

D.

internal dependency

Full Access
Question # 341

A project manager is leading a technology project that is about to enter the execution phase. The project requires the procurement of certain key components from an external vendor. The project manager has been notified that because of a government regulation, some parts can no longer be used in the country and the vendor will be unable to deliver them.

What should the project manager do?

A.

Identify the impact and follow the procurement plan.

B.

Identify the impact and follow the project management plan.

C.

Identify the impact and follow the risk management plan.

D.

Identify the impact and follow the change control plan.

Full Access
Question # 342

The ways in which the roles and responsibilities, reporting relationships, and staffing management will be addressed and structured within a project is described in the:

A.

Human resource management plan.

B.

Activity resource requirements.

C.

Personnel assessment tools,

D.

Multi-criteria decision analysis.

Full Access
Question # 343

A company is moving from a predictive to an adaptive approach. How should the company now translate the already planned work breakdown structure (WBS) to adaptive iterations?

A.

Create a product backlog with the information depicted in the WBS and prioritize the newly developed user stories into iterations.

B.

Accept this limitation and perform accordingly since the WBS can only be used in Scrum iterations.

C.

Consider reforming the structure of the company first as it is difficult for a company to transition from predictive to adaptive methods.

D.

Save the WBS in the historical data as the information can only be used for educational purposes and not as inputs for creating user stories.

Full Access
Question # 344

An adaptive team schedules 20 story points in the upcoming sprint. Historically, the team completes 25 story points on average per sprint. Each sprint is two weeks, and there is one day of float.

What is the likelihood the team will complete all 20 story points in the upcoming sprint?

A.

50-75%

B.

25-50%

C.

75-100%

D.

0-25%

Full Access
Question # 345

To which process is work performance information an input?

A.

Administer Procurements

B.

Direct and Manage Project Execution

C.

Create WBS

D.

Perform Qualitative Risk Analysis

Full Access
Question # 346

An input to the Estimate Activity Resources process is:

A.

Activity resource requirements.

B.

Published estimating data.

C.

Resource calendars.

D.

Resource breakdown structure (RBS).

Full Access
Question # 347

Which Control Scope input is compared to actual results to determine if corrective action is required for the project?

A.

Scope baseline

B.

Scope management plan

C.

Change management plan

D.

Cost baseline

Full Access
Question # 348

A project manager builds consensus and overcomes obstacles by employing which communication technique?

A.

Listening

B.

Facilitation

C.

Meeting management

D.

Presentation

Full Access
Question # 349

The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as:

A.

Plan Schedule Management.

B.

Develop Project Charter.

C.

Develop Schedule.

D.

Plan Scope Management.

Full Access
Question # 350

How can emotional intelligence (EI) be effective in project management?

A.

By preparing a project plan and managing the team members

B.

By planning for user acceptance testing

C.

By establishing project resource allocation

D.

By reducing tension and increasing cooperation among team members

Full Access
Question # 351

A practitioner organized a requirements workshop with the client ' s frontline application users. The users explained that one of the challenges of the current application is that they must click on each input before entering data, which happens thousands of times a day.

Which technique did the practitioner use to identify this pain point?

A.

System thinking

B.

User acceptance testing

C.

Decision-making

D.

Active listening

Full Access
Question # 352

The project has a current cost performance index of 0.80. Assuming this performance wi continue, the new estimate at completion is $1000. What was the original budget at completion for the project?

A.

$800

B.

$1000

C.

$1250

D.

$1800

Full Access
Question # 353

A project manager oversees a project in an adaptive environment. After each iteration, which type of meeting should the project manager conduct?

A.

Iteration planning

B.

Retrospective

C.

Backlog refinement review

D.

Daily standup

Full Access
Question # 354

Resource calendars are included in the:

A.

staffing management plan.

B.

work breakdown structure (WBS).

C.

project communications plan.

D.

project charter.

Full Access
Question # 355

How can a project manager evaluate project team development?

A.

Produce team performance assessments.

B.

Hold weekly meetings to engage every member

C.

Complete a personal skill assessment on each team member

D.

Provide recognition awards to team members

Full Access
Question # 356

Which type of diagram includes groups of information and shows relationships between factors, causes, and objectives?

A.

Affinity

B.

Scatter

C.

Fishbone

D.

Matrix

Full Access
Question # 357

A project team is evaluating criteria to determine project viability. Which of these activities will provide insight into making a go/no-go decision to start the project?

A.

Cost of quality (COQ)

B.

Lessons learned

C.

Cost-benefit analysis

D.

Benchmarking

Full Access
Question # 358

The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:

A.

recognition and rewards

B.

compliance

C.

staff acquisition

D.

training needs

Full Access
Question # 359

Organizational process assets, a lessons-learned database, and historical information are all inputs to which process?

A.

Plan Cost Management

B.

Plan Scope Management

C.

Plan Stakeholder Management

D.

Plan Schedule Management

Full Access
Question # 360

The project management plan requires the acquisition of a special part available from a supplier located abroad. Which source selection method is being used?

A.

Least cost

B.

Qualifications only

C.

Sole source

D.

Fixed budget

Full Access
Question # 361

A project manager is reviewing a few techniques that can be used to evaluate solution results. The intent is to uncover whether the solution responds properly to unintended cases.

Which evaluation technique should be used here?

A.

Exploratory testing

B.

Integration testing

C.

User acceptance testing

D.

Day-in-the-life testing

Full Access
Question # 362

In which phase of team building activities do team members begin to work together and adjust their work habits and behavior to support the team?

A.

Performing

B.

Storming

C.

Norming

D.

Forming

Full Access
Question # 363

One of the objectives of a quality audit is to:

A.

highlight the need for root cause analysis.

B.

share the process documentation among stakeholders.

C.

offer assistance with non-value-added activities.

D.

identify all of the gaps or shortcomings.

Full Access
Question # 364

A business analyst needs to ensure the project team understands the most critical roles and responsibilities within the requirements change process. Which responsibility is the most important?

A.

Analyzing the change

B.

Approving the change

C.

Reviewing the change

D.

Discussing the change

Full Access
Question # 365

How can a project manager represent a contingency reserve in the schedule?

A.

Additional weeks of work to account for unknown-unknowns risks

B.

Task duration estimates of the best case scenarios

C.

Addition Duration estimates in response to identified risks that have been accepted

D.

Milestones representing the completion of deliverables

Full Access
Question # 366

What conflict resolution technique involves delaying the issue or letting others resolve it?

A.

Smooth/accommodate

B.

Collaborate/problem solve

C.

Withdraw/avoid

D.

Force/direct

Full Access
Question # 367

Why is tailoring required in a project?

A.

Because a one-size-fits-all approach avoids complications and saves time.

B.

Because every project is unique and not every tool, technique, input, or output identified in the PMBOK Guide is required.

C.

Because tailoring allows us to identify the techniques, procedures, and system practices used by those in the project.

D.

Project managers should apply every process in the PMBOK Guide to the project, so tailoring is not required.

Full Access
Question # 368

Which set of activities should a project manager use as part of the Develop Team process?

A.

Training and establishing ground rules

B.

Networking activities and estimating team resources

C.

Conflict management activities and tracking team performance

D.

Recruit new team members and training

Full Access
Question # 369

A software development team is working on a project to adapt an application to new, government-established data-privacy rules. What factor led to the creation of this project?

A.

Legal requirement

B.

New technology

C.

Social need

D.

Economic change

Full Access
Question # 370

Projects are undertaken by an organization to support the:

A.

Product performance.

B.

Budget process.

C.

Collective capabilities.

D.

Organizational strategy.

Full Access
Question # 371

Which of the following are components of the project management plan?

A.

Scope management plan, scope baseline, risk management plan, and configuration managemet plan

B.

Scope management plan, issue log, risk register and project schedule network diagram

C.

Scope management plan, schedule baseline, milestone list, and assumption log

D.

Scope management plan, cost estimates, duration estimates, and resource calenders

Full Access
Question # 372

Typical outcomes of a project include:

A.

Products, services, and improvements.

B.

Products, programs, and services.

C.

Improvements, portfolios, and services.

D.

Improvements, processes, and products.

Full Access
Question # 373

A project manager has created an issue log to document issues communicated by project team members during weekly team meetings. This is an input of:

A.

Manage Stakeholder Expectations.

B.

Monitor and Control Risks.

C.

Plan Risk Management.

D.

Report Performance.

Full Access
Question # 374

The handoff of the first version of a software application to the operational team has taken a month longer than anticipated. How could this extended transition time have been avoided?

A.

If the operation team members were trained externally

B.

If the transition process was agreed upon during the build

C.

If the end-user documentation was more thorough

D.

If the operations manager was invited to all sprint reviews

Full Access
Question # 375

Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?

A.

Project team

B.

Focus group

C.

Change control board

D.

Project stakeholders

Full Access
Question # 376

The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:

A.

Work packages.

B.

Accepted deliverables.

C.

The WBS dictionary.

D.

The scope baseline.

Full Access
Question # 377

Which of the following events would result in a baseline update?

A.

A project is behind schedule and the project manager wants the baseline to reflect estimated actual completion.

B.

A customer has approved a change request broadening the project scope and increasing the budget.

C.

One of the risks identified in the risk management plan occurs, resulting in a schedule delay.

D.

One of the key project team resources has left the team and no replacement is available.

Full Access
Question # 378

Who identifies project requirements in the early phase of the project?

A.

Business analyst, product team, and key stakeholders

B.

Project manager, business analyst, and key stakeholders

C.

Project manager, business analyst, and project sponsor

D.

Project sponsor, business analyst, and key stakeholders

Full Access
Question # 379

A project has an estimated duration of 10 months with a total budget of US$220,000. At the end of the fifth month, it is estimated that at completion, the project will incur US$250,000. If the actual cost (AC) calculated is US$150,000, what is the earned value (EV) of the project?

A.

USS-30,000

B.

US$120,000

C.

US$370,000

D.

US$400,000

Full Access
Question # 380

A project in which the scope, time, and cost of delivery are determined as early as possible is following a life cycle that is:

A.

Adaptive

B.

Predictive

C.

Incremental

D.

Iterative

Full Access
Question # 381

Which subsidiary management plan.... during the project ilfe cycle?

Which Subsidiary management plan would a project manager create to manage Information dissemination during the project life cycle?

A.

Stakeholder Engagement Plan

B.

Quality Management Plan

C.

Communications Management Plan

D.

Scope Management Plan

Full Access
Question # 382

Which are the competing constraints that project manager should address when tailoring a project?

A.

Cost, scope, schedule

B.

Sponsorship, risk, quality

C.

Schedule, sponsorship, scope

D.

Resources, Quality, Communication

Full Access
Question # 383

A functional manager is delegating a key project to a project team without a project manager. Which communication method will be most effective?

A.

Interactive

B.

Push

C.

Verbal

D.

Oral

Full Access
Question # 384

Which Collect Requirements output links the product requirements to the deliverables that satisfy them?

A.

Requirements documentation

B.

Requirements traceability matrix

C.

Project management plan updates

D.

Project documents updates

Full Access
Question # 385

What is an objective of the Develop Project Team process?

A.

Feelings of trust and improved cohesiveness

B.

Ground rules for interaction

C.

Enhanced resource availability

D.

Functional managers becoming more involved

Full Access
Question # 386

Portfolio Management is management of:

A.

a project by dividing the project into more manageable sub-projects.

B.

a project by utilizing a portfolio of general management skills such as planning, organizing, staffing, executing, and controlling.

C.

all projects undertaken by a company.

D.

a collection of projects that are grouped together to facilitate effective management and meet strategic business objectives.

Full Access
Question # 387

Which Define Activities tool or technique is used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts?

A.

Decomposition

B.

Inspection

C.

Project analysis

D.

Document analysis

Full Access
Question # 388

Which process is included in the Project Integration Management Knowledge Area?

A.

Manage Project Team

B.

Collect Requirements

C.

Sequence Activities

D.

Direct and Manage Project Work

Full Access
Question # 389

What is a tool to improve team performance?

A.

Staffing plan

B.

External feedback

C.

Performance reports

D.

Co-location

Full Access
Question # 390

What quantitative risk analysis technique is used to select the optimum course of action from a number of alternatives?

A.

Sensitivity analysis

B.

Simulation

C.

Decision tree analysis

D.

Influence diagram

Full Access
Question # 391

A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?

A.

Three weeks

B.

Four weeks

C.

Five weeks

D.

Six weeks

Full Access
Question # 392

What scenario describes when a project must be created due to market demand?

A.

A public company authorizes a project to create a new service for electric car sharing to reduce pollution.

B.

A car company authorizes a project to build more fuel-efficient cars in response to gasoline shortages.

C.

Researchers develop an autonomous car. with several new features to be commercialized in the future.

D.

Stakeholders request that raw matenais be changed due to locally high costs.

Full Access
Question # 393

A project manager is reviewing some techniques that can be used to evaluate solution results. The intent is to determine if the solution provides the functionality for typical usage by a stakeholder with in-depth business knowledge.

Which evaluation technique is most effective for this situation?

A.

Day-in-the-life testing

B.

Exploratory testing

C.

User acceptance testing

D.

Integration testing

Full Access
Question # 394

In project management, which document is used to start the initial risk identification?

A.

Assumption log

B.

Risk management plan

C.

Risk register

D.

Issue log

Full Access
Question # 395

How can you describe the role of the project.... of influence concept?

A.

The proiect manager proactivnly interacfS with other project managers creating a positive influence Km fulfilling project needs, working with other managers and sponsor to address internal political and strategic issues and ensunng that the project managemenl plan aligns with the portfolio or program plan

B.

The project manager leads the team, performs communication roles between stakeholders, and uses interpersonal sills to balance conflicting goals

C.

The proiect manager stays informed about current technology developments lakes into account new quality management standards, and uses relevant technical support tools

D.

The proiect manager participates in project management trainings, contributes to the organization professional community sharing knowledge, and maintains subied matter expertise

Full Access
Question # 396

For a 10-day project, activity B ' s duration is three days, and activity C’s duration is two days What is the duration of activity A if activities B and C are performed in parallel?

A.

3 days

B.

5 days

C.

7 daysD .10 days

Full Access