Nokia orders the I&C from a subcontractor. The subcon, not completely familiar with this new equipment, requires a Nokia technician to complete the service. What is the correct way to proceed?
What is the relationship between sales items (SI's) and service orders in the care contract?
What are the key elements that must be monitored constantly over the entire project life cycle?
What is the correct approach when handling extra costs of which the customer is deemed responsible and the relevant purchase order has been received?
In which project management process is the detailed project budget created?
Which of the following examples will cause a decline in project cost adherence (PCA)?
The __________ identifies the project elements that cost will be allocated to:
Company A is working on a project. The project‘s budget is €10,000. The planned value as of date X is €4,000. The project has an earned value of €3,500 and actual costs of €4,500. What is the cost variance of the project?
In an NI rollout project, when is a purchase order sent to the services subcontractor?
At a given point in time, a project has a CPI = 0.7 and SV = €1,000. The project is:
Project "A" has experienced difficulties in the deliveries of one of its key suppliers. It has been estimated by the project team that, if the supplier is one week late for the next scheduled delivery, it will cost €10,000. The probability of the supplier being late is 50 %, based on the fact that this has happened before on the project. It is decided not to take any risk mitigation actions. What is the TERC for this risk?