Summer Sale - Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dpt65

PDM_2002001060 Questions and Answers

Note! Following PDM_2002001060 Exam is Retired now. Please select the alternative replacement for your Exam Certification.

PDM_2002001060 Questions and Answers

Question # 6

What is the purpose of the WBS?

A.

To show which work elements have been assigned to organizational units.

B.

To ensure that all work within a project is identified and defined within a common framework.

C.

To show the organizational structure of a program.

D.

To schedule the project work elements.

Full Access
Question # 7

Nokia orders the I&C from a subcontractor. The subcon, not completely familiar with this new equipment, requires a Nokia technician to complete the service. What is the correct way to proceed?

A.

The technician is immediately provided to properly support our subcontractor and quickly complete the service and enable customer acceptance and invoicing.

B.

The technician will support the subcontractor only after the newly created change request is approved.

C.

A new change request is created and approved by the project manager then the technician is provided to support the subcontractor; an outgoing claim to the subcontractor is applied just after the service is completed and then the internal acceptance is provided.

D.

A new change request is created and approved by project manager, then the technician is provided to support the subcon; however an internal acceptance is not provided because of the incomplete service from the subcontractor.

Full Access
Question # 8

What is the relationship between sales items (SI's) and service orders in the care contract?

A.

An SvO can have multiple SI's, but an SI line in the care contract can have only one SvO.

B.

There is no relationship or connection between SIs and SvOs in the care contract.

C.

An SvO can have only one SI, and an SI line in the care contract can have only one SvO.

D.

An SvO can have only one SI, but an SI line in the care contract can have multiple SvOs.

Full Access
Question # 9

Which inputs best support the resource demand plan update for a project?

A.

Project organization chart, rollout schedule and project ID.

B.

Project organization chart, required headcount, and required timeframe.

C.

Rollout schedule, required headcount, project ID, required competences and required timeframe.

D.

Material list, Rollout Schedule, WBS Code, and required timeframe.

Full Access
Question # 10

What are the key elements that must be monitored constantly over the entire project life cycle?

A.

Quality and subcontractor performance.

B.

Contract conditions and project deliverables.

C.

Cost, time and scope.

D.

Financial reports and schedule.

Full Access
Question # 11

What is NOT included in a basic project cost report?

A.

Total project cost baseline.

B.

Total project estimate at completion.

C.

Total actual costs.

D.

Year to date costs of goods sold.

Full Access
Question # 12

What is the correct approach when handling extra costs of which the customer is deemed responsible and the relevant purchase order has been received?

A.

Cost baseline updated.

B.

Update estimate to completion (ETC) and update materialized costs in cost baseline.

C.

Update estimate to completion (ETC) and update ordered works in cost baseline.

D.

Estimate to completion updated.

Full Access
Question # 13

Which process is NOT included in project cost management?

A.

Resource planning.

B.

Cost planning.

C.

Cost control.

D.

Resource allocation.

Full Access
Question # 14

What is NCC in Nokia?

A.

Any cost overruns.

B.

All subcontractor extra work costs.

C.

Materialized risks.

D.

All extra site visit costs.

Full Access
Question # 15

In which situation is it required to update/change the cost baseline?

A.

Roll-out delays affecting the original cost plan.

B.

Change in subcontractor prices.

C.

Scope changes supported by a legal binding document.

D.

When a risk has materialized.

Full Access
Question # 16

In which project management process is the detailed project budget created?

A.

Initiating.

B.

Closure.

C.

Planning.

D.

Executing.

Full Access
Question # 17

Which of the following is NOT classified as NCC?

A.

Unplanned costs for replacement of products not under warranty.

B.

Unplanned costs from mistakes made by incompetent resources.

C.

Use of resources with higher SPC rates than planned.

D.

Unplanned work due to a hardware failure which has impacted network statistics and KPIs.

Full Access
Question # 18

Which of the following is not chargeable work?

A.

Project management.

B.

Construction works.

C.

Site logistics.

D.

Account management.

Full Access
Question # 19

What is the duration of short term planning (STP) period?

A.

1 month.

B.

6 months.

C.

3 months.

D.

12 months.

Full Access
Question # 20

Which of the following examples will cause a decline in project cost adherence (PCA)?

A.

Additional scope of work ordered by customer.

B.

Additional service effort caused by site unavailability for which the customer is liable.

C.

Delay in equipment delivery.

D.

Penalties paid to the customer.

Full Access
Question # 21

The __________ identifies the project elements that cost will be allocated to:

A.

work breakdown structure.

B.

default work packages.

C.

earned value.

D.

order of magnitude estimate.

Full Access
Question # 22

Company A is working on a project. The project‘s budget is €10,000. The planned value as of date X is €4,000. The project has an earned value of €3,500 and actual costs of €4,500. What is the cost variance of the project?

A.

€-1,000.

B.

€500.

C.

€-500.

D.

€1,000.

Full Access
Question # 23

In an NI rollout project, when is a purchase order sent to the services subcontractor?

A.

When the supplier contract is signed by the project procurement manager.

B.

After the first site has been internally accepted by the Nokia project manager in IPM.

C.

In a timely fashion before any services are to be executed by the supplier, in order to be SOX compliant.

D.

After the first site has been accepted by the customer and the invoice has been sent to the customer.

Full Access
Question # 24

The formula EV - PV provides the:

A.

cost difference.

B.

schedule variance.

C.

schedule difference.

D.

cost variance.

Full Access
Question # 25

For which of the following reasons can the cost baseline be updated?

A.

Due to cost savings.

B.

Due to delays in project execution.

C.

Due to customer driven scope change.

D.

Due to subcontractor's price change.

Full Access
Question # 26

At a given point in time, a project has a CPI = 0.7 and SV = €1,000. The project is:

A.

over budget and ahead of schedule.

B.

over budget and behind schedule.

C.

below budget and ahead of schedule.

D.

below budget and behind schedule.

Full Access
Question # 27

When is LoA approval required to take place for a claim?

A.

Before any commercial agreement with the contract party.

B.

Before the financial impact of the claim is booked.

C.

Not later than 30 days after the claim is settled.

D.

As soon as an incoming claim is received.

Full Access
Question # 28

What is a Project WBS?

A.

Division of the project into cost centers for proper cost allocation.

B.

Definition of the GICs which will be applicable to the project scope.

C.

Division of the project scope into hierarchical and manageable packages of work.

D.

A structure showing the product configurations.

Full Access
Question # 29

Project "A" has experienced difficulties in the deliveries of one of its key suppliers. It has been estimated by the project team that, if the supplier is one week late for the next scheduled delivery, it will cost €10,000. The probability of the supplier being late is 50 %, based on the fact that this has happened before on the project. It is decided not to take any risk mitigation actions. What is the TERC for this risk?

A.

€3,500.

B.

€7,500.

C.

€5,000.

D.

€10,000.

Full Access
Question # 30

When should lessons learned be performed?

A.

During the project execution and at the conclusion of the project.

B.

Only at the end of the project, during project closing.

C.

After the end of the project, at the project post-mortem meeting.

D.

Only when there is time available as project managers have other priorities.

Full Access
Question # 31

What are key components of EVM methodology?

A.

Planned value, earned value and actual cost.

B.

Planned cost, revenue and gross margin.

C.

Baseline costs, estimate at completion and estimate to complete.

D.

As sold cost estimates, baseline and EAC.

Full Access