Which THREE activities would be valid steps during the development of the test strategy?2 credits (2 out of 3 correct 1 credit)
Which of the following would be the TWO most appropriate examples of entry criteria documented in the system integration test plan? 2 credits
Given is the following defect removal chart reported at the end of system testing - showing total defects detected and closed defects (fixed and successfully retested). A number of open defects are classified as critical. All tests have been executed.
Based on the chart above, what is the most appropriate next test phase? 1 credit
Continuing with the Scenario described in the previous question, which of the following topics would you need to address in detail in the master test plan? 3 credits
A bank is developing a new service that will be delivered via the web. The user interactions are defined as a set of use cases and the service is designed to be available continuously 24/7. In view of the challenging characteristics of the service the test manager has decided that the code should be thoroughly tested at component level.
Which of the following test types will be required during the development? [K2]
What would be a test approach regarding the test design techniques to be applied that would fit an item with the highest risk? 2 credits
Instead of having an independent test team within the company, the company is considering to outsource testing. What are THREE key challenges that are typical for outsourcing? 1 credit
In addition to risk, identify TWO other components of a testing strategy. 1 credit
You have been asked to write a testing strategy for the company. Which statement best explains how risk can be addressed within the testing strategy? 1 credit
Part of the testing strategy indicates that you are going to be using systematic test design techniques. Your manager has asked that you present the main advantages of using these techniques at the next board meeting. Identify THREE main benefits of using systematic test design techniques within this company. 2 credits (for 2 out of 3 correct 1 credit)
In general, why is it NOT a good idea to estimate the testing effort based only on a percentage of development effort? Identify THREE valid reasons. 1 credit
Identify THREE items that would be part of the work-breakdown structure showing the key testing activities for the acceptance test project. 2 credits (for 2 out of 3 correct 1 credit)
Which one of the following estimation approaches is appropriate at this stage of the project? 2 credits
Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:
a. Any deviation from the procedures described in the test
b. strategy document
c. The overall estimated costs, timescales and resource
d. requirements
e. A detailed schedule of testing activities
f. The development deliverables to be tested
g. Which test staff members (names) will be involved and when
h. Level of requirements coverage achieved
Which TWO of the above mentioned characteristics relate to the phase test plan? 1 credit
You are considering involving users during test execution. In general, what is the main reason for involving users during test execution? 1 credit
Evaluate the status of the project against the defined exit criteria. Which of the following options shows the correct status? 2 credits
Since the system is in the medical domain and therefore in the safety critical area, testing needs to be rigorous and evidence is required that the system has been adequately tested. Identify THREE measures that would typically be part of the test approach in this domain and which are not always applicable in other domains! 1 credit
You are about to release a test progress report to a senior manager, who is not a test specialist. Which of the following topics should NOT be included in the test progress report? 1 credit
Regarding the process described above, what is the most important recommendation you would make using IEEE 1044 as a guide? 2 credits
Why might a RAD approach be a better option for the test manager rather than a sequential development? 2 credits
As a result of the RAD based development approach, the test manager has decided to change the risk mitigation approach. Which test technique might be most appropriate to use? 2 credits
The business has asked for a weekly progress report. Which of the following would be appropriate as a measure of test coverage? 2 credits
Risks should be constantly reviewed. Given the current situation, which one of the following factors is most likely to lead to a revised view of product risk? 3 credits
Which of the following would be the most significant input to estimating the time to carry out the specified testing tasks? 3 credits
Which of the following would you expect to see in the master test plan? 1 credit
Which of the following team roles would be most appropriate to enhance the team and why? 2 credits
Which of the following would you least expect to form part of the analysis of initial tool costs? 1 credit
Select THREE issues from the options provided that should at least be raised. 1 credit
Debugging and Testing are key activities in the software development lifecycle.
Which of the following are 'Debugging' activities?
a) Identifying, a failure
b) Locating the cause of failure
c) Fixing the defect
d) Checking the fix has resolved the failure
Testing effort can depend on a number of factors, which one of following is MOST likely to impact the amount of effort required?
A booking system for a city bus service prices its fares according to the time of travel:
• Peak-time tariff starts at 0600 and finishes at 1000 am
• Off-peak tariff applies during all other times of service
• The bus service does not operate between 2300 and the start of the next day’s peak service
Note that all times mentioned are inclusive.
When applying the equivalence partitioning test design technique, which of the following options, shows test case inputs that each fall into a different equivalence partition?
A test assessment has been carried out using the selected model as a reference framework. A number of recommendations have been identified and you are asked to prioritize them. Based on your knowledge of the project, you are expecting severe resistance to change. Which of the following would be the most important selection criterion for defining the priority of the recommendations? 2 credits
The development manager is managing the review of the responses received from bidders, and has asked the in-house test manager to provide a review checklist for the test management aspects of the responses. Which of the following checkpoints would be appropriate? 2 credits
Which of the following product risks would be most effectively addressed just by static testing? 3 credits
Given the following figures for the testing on a project, and assuming the failure rate for initial tests remains constant and that all retests pass, what number of tests remain to be run? 3 credits
You have investigated different possibilities and selected four of them to present to IT management. Which of the proposals will you most likely give your highest recommendations? 3 credits