Summer Sale - Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dpt65

C2010-570 Questions and Answers

Note! Following C2010-570 Exam is Retired now. Please select the alternative replacement for your Exam Certification.

C2010-570 Questions and Answers

Question # 6

Safety plans are used on which two IBM Maximo Asset Management V7.5 applications? (Choose two.)

A.

Assets

B.

Job Plans

C.

Work Orders

D.

Service Requests

E.

Preventive Maintenance

Full Access
Question # 7

Preventive Maintenance (PM) work orders can be triggered by which two criteria? (Choose two.)

A.

Meter-based PMs based on asset meter readings

B.

Time-based PMs based on elapsed time since previous work

C.

Unit measure-based PMs based on the threshold of the Unit of Measure application

D.

Asset-based PMs based on the status of the asset when it is moved in the maintenance storeroom

E.

Item Master-based PMs based on the status of the item when it is moved in the maintenance storeroom

Full Access
Question # 8

What is the definition of a work package?

A.

It groups existing work orders under a new parent work order.

B.

It is a preventive maintenance work order hierarchy that has been created from a route.

C.

It is a work order linked to all the originating services requests for the work order and is created from the Related Records tab.

D.

It is a group of work orders in Waiting to be Scheduled status that are the responsibility of one person and is created in the Assignment Manager application.

Full Access
Question # 9

In the Work Order Tracking application, which two actions create a value in the related records table? (Choose two.)

A.

Select Action > Create > Work Order

B.

Select Action > Duplicate Work Order

C.

Select Action > Create Work Package

D.

Select Action > Create > Communication

E.

Select Action > Create > Service Request

Full Access
Question # 10

A customer wants an escalation to automatically close work orders that have been in a complete status for more than 30 days. Which statement is true for this escalation?

A.

The escalation point should be set to repeat.

B.

The escalation point should have an elapsed time interval of 720.

C.

The escalation should have a condition that monitors work order status.

D.

The escalation should have a condition that monitors work order status and change date.

Full Access
Question # 11

Which IBM Maximo Asset Management location status is necessary to associate a location with a system?

A.

Active

B.

Ready

C.

Operating

D.

Decommissioned

Full Access
Question # 12

When a work order is created from a preventive maintenance record that references a route, the route stops will become child work orders with a common job plan. From which record will the resulting parent work order description be created?

A.

It will be the same as the route description.

B.

It will be the same as the job plan description.

C.

It will be null, to be updated with a description specific to the job.

D.

It will be the same as the preventive maintenance record description.

Full Access
Question # 13

What is required to create an escalation?

A.

Site

B.

Schedule

C.

Condition

D.

Description

Full Access
Question # 14

Which contract type defines the agreement to maintain one or more assets with an outside service provider for a fee or a scheduled set of payments?

A.

Service Contract

B.

Warranty Contract

C.

Purchase Contract

D.

Labor Rate Contract

Full Access
Question # 15

What is the purpose of commodity codes?

A.

To group like items for issue

B.

To group like items for purchasing

C.

To group like items for classification

D.

To group like items for asset bill of material

Full Access
Question # 16

Which three statements are true regarding returning assets to a vendor? (Choose three.)

A.

Rotating assets cannot be returned to a vendor.

B.

A direct issue item can be returned if it is moved.

C.

A direct issue item cannot be returned if it is moved.

D.

Assets must be returned from the receiving storeroom.

E.

An asset's inventory cost must equal the reversing line cost.

F.

An asset's inventory cost must not equal the reversing line cost.

Full Access
Question # 17

Where is authorization for changing general ledger component types done?

A.

Organizations application

B.

Security Groups application

C.

Chart of Accounts application

D.

Database Configuration application

Full Access
Question # 18

How can a document be included in an e-mail sent from a communication template?

A.

On the Attachment Folders tab, check the Include box

B.

On the Create Communication dialog, select attachments to send

C.

On the Linked Documents tab, check the Send with Communication box

D.

On the Communication Template tab, click Attachments and select a document

Full Access
Question # 19

If the Integrity Checker utility reports that some indexes are missing, which application should be used to fix this issue?

A.

Asset application

B.

Migration Manager application

C.

Database Designer application

D.

Database Configuration application

Full Access
Question # 20

Which data is required to apply an Item Assembly Structure (IAS) to an operating location in the Locations applications?

A.

Meter Group

B.

Failure Class

C.

Rotating Item

D.

Non-rotating Item

Full Access
Question # 21

Which three options are available to set the reservation type on the Work Order Materials sub-tab? (Choose three.)

A.

SOFT

B.

HARD

C.

URGENT

D.

REQUIRED

E.

RESERVED

F.

AUTOMATIC

Full Access
Question # 22

Which IBM Maximo Asset Management V7.5 application can view labor that applies to specific requirements, or view work order requirements that fit the craft, skill level, vendor, contract, calendar availability, or shift of displayed labor?

A.

Job Plans

B.

Quick Reporting

C.

Assignment Manager

D.

Preventive Maintenance

Full Access
Question # 23

How can a preventive maintenance (PM) record be excluded from a PM forecast in the Preventive Maintenance application?

A.

Change the status of the PM to NONSCHED

B.

Select the option: Exclude this PM in the Forecast

C.

Deselect the option: Include this PM in the Forecast

D.

Select Delete Forecast from the Select Action menu

Full Access
Question # 24

When creating new Business Intelligence and Reporting Tool (BIRT) reports for use by the various IBM Maximo Asset Management applications, which step correctly describes a part of the process to add a new report?

A.

Before design files are imported, any associated library files must be imported

B.

Using the system configuration option, choose the report designer files to import

C.

Using the BIRT Report Designer Workstation, select the menu item to import the new report

D.

Before design files are imported, the location files that specify the location of the images and report files must be populated

Full Access
Question # 25

In inventory terms a hard reservation is a request for materials that is defined by the need for what?

A.

An item from a specific vendor

B.

An item within a specific timeframe

C.

An item based on the current balance

D.

An item based on the work order priority

Full Access
Question # 26

A work order has three hours of labor charged but only one hour is reflected in the View Costs table. What is a valid explanation for this?

A.

Only one hour is an approved labor transaction

B.

Outside labor hours are not reflected in the View Costs table

C.

Two of the hours were worked by an outside contractor so those hours are reflected as a Service

D.

The view actuals date filter is set for 30 days and two of the hours were recorded greater than 30 days ago

Full Access
Question # 27

An asset is created and measurement points are associated. Which IBM Maximo Asset Management V7.5 application sets Upper Limit and Lower Limit Job Plans?

A.

Meters

B.

Assets

C.

Condition Monitoring

D.

Work Order Tracking

Full Access
Question # 28

Which option attaches an image to an item master record in the Item Master application?

A.

Clicking on the Image icon

B.

Clicking on the Attachments icon

C.

Select Action > Add/Modify Image

D.

Select Action > Attachment/Library Folders

Full Access
Question # 29

Which IBM Maximo Asset Management V7.5 application can create and display problem, cause, and remedy in a three level hierarchy?

A.

Meter Groups

B.

Failure Codes

C.

Failure Classes

D.

Condition Monitoring

Full Access
Question # 30

A forecast for a preventive maintenance record has been generated. How can the forecast date be adjusted from the Preventive Maintenance application?

A.

From the Forecast tab, select a forecast row, enter a value in the New Date field, click Save

B.

From the Select Action menu, select Generate Forecast, enter a value in the Forecast Days field, click OK

C.

From the Frequency tab, select the Time Based Frequency tab, enter a value in the Frequency field, click Save

D.

From the Frequency tab, select the Time Based Frequency tab, enter a value in the Extended Date field, click Save

Full Access
Question # 31

A company has deployed IBM Maximo Asset Management V7.5 (Maximo) to manage the company assets and the purchasing process. The company's purchasing process does not require an approved purchase request (PR) in order to generate a new purchase order (PO) but the buyer reported this problem when trying to create a new PO from an unapproved PR:

Where can this validation be turned off in Maximo?

A.

Organizations application

B.

Purchase Orders application

C.

System Properties application

D.

Database Configuration application

Full Access