Pre-Summer Sale - Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70dumps

IAM-Certificate Questions and Answers

Question # 6

The purpose of an Asset Information Strategy is to:

A.

Collate the standards which define the collection, storage and use of asset information

B.

Provide the overall framework and plan for asset information which will deliver the organisation’s asset information requirements

C.

Specify the requirements for procuring the organisation’s asset information system

D.

Calculating the lowest cost options for the entire commercial life of a building

Full Access
Question # 7

Who should demonstrate leadership in ensuring adequate, periodic review of the suitability, adequacy and effectiveness of the Asset Management System?

A.

The Senior Engineer

B.

The Head of Asset Management

C.

The Board Audit Committee

D.

The Top Management Team

E.

An Independent Auditor

Full Access
Question # 8

The contents of an asset management policy can include...

A.

the requirements of the key stakeholders of the organisation, high level asset management roles and responsibilities, the asset management principles for the organisation, a framework for the setting of the asset management strategy and objectives and a review frequency

B.

the mandated requirements of the organisation, high level asset management roles and responsibilities, the key departments involved in asset management, a framework for the setting of the asset management strategy and objectives and review frequency

C.

the mandated requirements of the organisation, high level asset management roles and responsibilities, the asset management principles for the organisation, a framework for the setting of the asset management strategy and objectives and details of the asset management plan

D.

the mandated requirements of the organisation, the asset management principles for the organisation, high level asset management roles and responsibilities, a framework for the setting of the asset management strategy and objectives and a commitment to continuous improvement

E.

the mandated requirements of the organisation, the asset management principles for the organisation, high level asset management roles and responsibilities, key risks for the organisation and a review frequency

Full Access
Question # 9

During the design phase the predicted life of an asset was determined to be 50 years. This life was applied as the asset’s depreciation life in the Fixed Asset Register. You have just completed an investment post project review and found the benefits have not been fully delivered, and never will be. You now believe asset’s useful life will be 30 years, what will you do with this information?

A.

Feedback the new information for future modelling, project design, and build phases. Update the Asset Management Plan. Tell Top Management so they can start an investigation to find who was at fault

B.

Feedback the new information for future modelling, project design, and build phases. Update the Asset Management Plan. Tell the maintenance team to reduce maintenance to help recover some of the costs

C.

Feedback the new information for future modelling, project design, and build phases. Update the Asset Management Plan. Inform Finance so they can make any necessary adjustments to the asset’s value

D.

Feedback the new information for future modelling, project design, and build phases. Update the Asset Management Plan. Inform Asset Management colleagues to start planning for a replacement

E.

Feedback the new information for future modelling, project design, and build phases. Update the Asset Management Plan. Inform nobody else as this information will have no short to medium term effect

Full Access
Question # 10

There are 4 fundamentals in asset management, including ....

A.

Value, Alignment, Leadership and Assurance

B.

Value, Alignment, Leadership and Insurance

C.

Value, Competitif, Leadership and Assurance

D.

Value, Alignment, Proggresive and Assurance

Full Access
Question # 11

How is risk best quantified within an ISO 55001 compliant Asset Management System?

A.

Risk is quantified as a product of asset criticality and unavailability

B.

Risk is quantified by defining boundaries of acceptable risk

C.

Risk is quantified by multiplying event probability by event consequences

D.

Risk identification processes quantify risk

E.

It is not possible to quantify risk

Full Access
Question # 12

A change of maintenance contractor for an operational system is being proposed. Which of the following processes should be applied?

A.

Maintenance Planning Process

B.

Reliability Engineering Process

C.

Change Request Process

D.

Contingency Planning Process

E.

Spares Provisioning Process

Full Access
Question # 13

Asset Management is explicitly focused on helping organisations to achieve their defined objectives and to determine the optimal blend of activities based on these objectives.

A.

True

B.

False

Full Access
Question # 14

A public transportation company has a fleet of 150 trams. Type A (25 years old), Type B (19 years), Type C (2 years). Expected lifetime is 30 years. Type A and B perform sufficiently but suffer obsolescence and spare parts issues.

What would be a feasible action now?

A.

Prepare to phase out type A as they are near the end of life

B.

Start an asset rationalisation study on type A (and maybe B) to determine the possible end-of-life options

C.

Replace type A and B with 80 new type C trams to standardize fleet

D.

Prepare an overhaul for type A and B

E.

Modify type A and B to maintain service and solve obsolescence

Full Access
Question # 15

How many roles are there in the IAM Competences Framework?

A.

Five

B.

Six

C.

Seven

D.

Three

Full Access
Question # 16

Successful delivery of the asset management plan(s) relies on integration with other organisational plans in both the development and delivery phases.

A.

False

B.

True

Full Access
Question # 17

To successfully establish, operate and improve asset management within an organisation, it is essential that leadership, and commitment, is demonstrated by all levels of management – from senior executives to supervisors.

A.

False

B.

True

Full Access
Question # 18

You are presenting an 'Introduction lo good Asset Management' workshop. A member of the audience asks you to draw a simple diagram that best describes the three main parameters Involved in good practice Risk Management. Which of the following diagrams are you most likely to draw?

A)

B)

C)

D)

E)

A.

Option A

B.

Option B

C.

Option C

D.

Option D

E.

Option E

Full Access
Question # 19

A significant risk of asset failure that will impact service to customers is identified by an asset operator and reported to his line manager. When is the right time to add the risk to the risk register?

A.

When the risk is identified to the line manager

B.

Before the next scheduled risk review meeting

C.

When the owner of the risk register asks for emerging risks

D.

After the asset has failed and the cause has been investigated

E.

When budget has been allocated to mitigate the risk

Full Access
Question # 20

Which of the following is NOT normally an input to an asset management plan?

A.

Maintenance schedules

B.

Asset knowledge

C.

Demand forecast

D.

Organizational objectives

E.

Asset Management Objectives

Full Access
Question # 21

ISO 55000 is ......

A.

The international reference standard to sets out the criteria for a quality management system

B.

The international reference standard for the optimal management of physical assets.

C.

The international reference standard that provides the overview of information security management systems

D.

The international reference standard to sets out the criteria for an environmental management system

Full Access
Question # 22

Where can a standardized Risk Matrix be found for use within Asset Management Systems aligned to ISO 55000?

A.

A standard Risk Matrix is available in ISO 55002

B.

Each organization’s risk appetite and asset portfolio are unique, so no standard Risk Matrix applies

C.

A standard Risk Matrix exists in the GFMAM’s Asset Management Landscape

D.

A standard Risk Matrix is available in ISO 31000

E.

Standard Risk Matrices for assets are widely available online

Full Access
Question # 23

Where would an organization record the agreed criteria for risk management and decision-making that are used for risk analyses to determine the optimum asset interventions?

A.

The Asset Risk Management Policy

B.

The Asset Risk Register

C.

The Audit and Compliance Manual

D.

The Asset Information Strategy

E.

The Strategic Asset Management Plan (SAMP)

Full Access
Question # 24

Which of the following would you consider to be a strategic asset management requirement?

A.

The cost of consultants to support the creation of strategies

B.

The cost of tools and equipment to deliver the maintenance regime

C.

The number of capital projects

D.

The implications of current and forecast asset condition

E.

The location of capital projects

Full Access
Question # 25

Capital Investment Decision-Making comprises the processes to .....

A.

Evaluate and analyse options for the creation of new assets

B.

Decreasing the capability of assets

C.

The replacement of modal at the end of their useful life

D.

All false

Full Access
Question # 26

Which of the following describes the most appropriate maintenance regime?

A.

A risk based regime where every asset has a planned preventive programme

B.

A condition based regime where all assets are fitted with remote condition monitoring

C.

A risk based regime that combines preventive, predictive and corrective techniques

D.

A risk based regime where manufacturers' maintenance recommendations are followed

E.

A condition based regime where maintenance procedures are based on failure data

Full Access
Question # 27

What is a cost-effective maintenance task for a failure mode which is considered by the business as 'low risk'?

A.

A ‘scheduled discard’ task (scheduled replacement)

B.

A ‘fix-on-failure’ task

C.

A ‘redesign’ task

D.

A ‘scheduled discard’ task (scheduled replacement) in combination with predictive maintenance strategies

E.

A ‘scheduled restoration’ task (scheduled overhaul)

Full Access
Question # 28

What are the three fundamental considerations of life cycle decision making which enable asset optimisation?

A.

Reliability, performance and cost

B.

Specifications, cost and functionality

C.

Asset life, age and costs

D.

Performance, cost, risk

E.

Criticality, risk and reliability

Full Access
Question # 29

The concept of ‘line of sight’ means .....

A.

Asset Manager involved in asset management

B.

Top Management involved in asset management

C.

Stakeholders involved in asset management

D.

Everyone who touches or influences what happens to an asset is involved in asset management

Full Access
Question # 30

Risk is best described as:

A.

The effect of uncertainty on an organisation's objectives

B.

An organisation's tolerance to uncertainty

C.

An organisation's appetite to uncertainty

D.

The effect of meeting an organisation's objectives

E.

The impact of uncertainty

Full Access
Question # 31

There are many factors that can drive the decommissioning of assets, except :

A.

Obsolete technology

B.

Compliance with changes in legislation

C.

Excess of service capacity

D.

Cost of retaining in service

Full Access
Question # 32

The asset management strategy will:

A.

Consider what customers want and how to limit change

B.

Consider how to discourage future demand growth

C.

Consider how to encourage customer demand

D.

Consider how and why current and future customer requirements are assessed

E.

Focus on historical customer requirements for forecasting

Full Access
Question # 33

Which of the following is the LEAST important factor when considering the decommissioning of assets?

A.

Changes in performance levels to deliver the objectives for the organization

B.

Obsolescence and lack of spare parts

C.

Reduction in demand

D.

New technology in the market place

E.

Changes to legislation

Full Access
Question # 34

In the context of Asset Management, and the ‘line of sight’ through the organisation, it is important that a project business case and evaluation process connect with:

A.

The Risk Management Strategy

B.

The Capital Budget

C.

The Operational Budget

D.

The Resourcing Strategy

E.

The Asset Management Objectives

Full Access
Question # 35

Which of these statements is UNTRUE?

A.

Asset information is always worth collecting regardless of cost

B.

Asset information has maintenance costs as well as collection costs

C.

Asset information can be treated as an asset in its own right

Full Access
Question # 36

Two widely used approaches to conceptualising value in an organisation are:

A.

The Value Net and Delivery

B.

The Value Stream and Delivery

C.

The Value Net and Chain

D.

The Value Stream and Chain

Full Access