Which two items are concerns for C-level executives and managerial stakeholders?
Choose two.
A large multinational financial institution has hired you to design a new full-stack wired and wireless network for its new 6-story regional office building. The lowest two floors of the facility will be retail space for a large banking branch. The upper floors will be carpeted corporate office space, with each floor measuring approximately 100,000 sq ft (9290 sq m). All data centers are offsite and are outside this project’s scope. The customer is underserved by its current L2-based network infrastructure and wants to apply modern best practices in the new design. The network must be fully resilient and fault-tolerant, with dynamic segmentation at the edge.
The retail space will provide public guest Wi-Fi access. Retail associates will use corporate tablets for customer service, and the retail floors will contain a mix of wired and wireless devices. Corporate users will primarily connect wirelessly, although several wired clients, printers, and hard VoIP phones will also be used.
The customer also plans to renovate the corporate office space to take advantage of 'smart office' technology. These enhancements will enable blue-dot wayfinding, presence analytics, and other location-based services.
The client wants to use lower-cost OS-CX switches in its wiring closets. It calculates that each closet will require a stack of qty 6 POE (AT) and qty 4 Gigabit Ethernet switches, stacked with low-cost DACs.
Which switch series should you recommend?
Which statements correctly describe the Unified Communication (UCC) and Intelligent Call Handling (ICH) capabilities available in HPE Aruba Networking AOS-10, along with their associated subscription and configuration requirements?
Choose two.
Which licenses are required to use the UXI Client on Zebra devices?
Choose two.
What is the basic difference between a main distribution framework (MDF) closet and an intermediate distribution framework (IDF) closet?
You are developing a technical proposal for a customer that plans to deploy HPE Aruba Networking Cloud Central-managed AOS-10 Access Points in a typical campus office environment. The customer has used ARM-based radio resource management successfully for many years. During their transition to AOS-10, they ask for guidance on suitable initial EIRP (Effective Isotropic Radiated Power) values for new radio profiles in HPE Aruba Networking Central.
Which EIRP configuration option should be recommended as an appropriate starting point for this office deployment?
What items should an Executive Summary include? Place the correct items in the list on the right. The order does not matter, and some options will not be used.

A customer needs integration with ServiceNow.
Which CX feature automatically creates ServiceNow tickets from network events?
A global cruise line company needs to modernize its existing fleet. It will refresh the ship’s “insides” to improve cost-effectiveness and sustainability, replacing all WLAN/LAN hardware. During this refresh, the company will retain its existing security requirements. The CIO also wants to minimize unused switch ports. Any future expansion will always involve a hardware refresh. The project begins with the smallest ship, which has a maximum of 800 guests.
Each ship has a LAN infrastructure comprising two core switches, up to 10 redundant distribution switches, and up to 500 access switches (400 cabins and 100 technical rooms). The core switches are in the ship’s MDF, and the distribution switches are in the IDFs. Every cabin and technical room receives one access switch.
The ship’s cabling structure will remain unchanged. Each IDF connects to the MDF through SMF, with two pairs available for the interconnect between core and distribution. The SMF distance between MDF and IDF is under 300 meters (980 ft), and it is OS1. Each cabin connects to the IDF through a single OM2 pair, with a maximum distance of 60 meters (200 ft). Each technical room connects to the IDF through a single OM2 pair, with distances from 100 to 150 meters (320 to 500 ft).
For every cabin and technical room, the customer wants to replace the existing fan-less 2530/2540 switches without changing requirements, except that the uplink to the distribution switch must be upgraded to 10GbE to accommodate increased network traffic, and technical rooms require redundant power.
The WLAN infrastructure will be refreshed 1:1, with no new cabling or AP locations. It uses 200/300 series indoor and outdoor APs running InstantOS (fewer than 300 APs), and the customer has no WLAN requirement changes.
The cruise line company will replace its existing Internet connection before the LAN/WLAN refresh. The new Internet connection will provide 99.8% uptime, needed to keep paid guest Wi-Fi operational. With this new Internet connection, the CIO wants to base the design on Aruba’s ESP architecture because the Internet connection is guaranteed.
Based on best practices, what optic type should be recommended for the connection between the IDF and the cabins?
Manufacturing A.B.C. is an international, mid-sized company that specializes in manufacturing industrial equipment. It has operated in the market for more than two decades and has become a reputable player in its industry. However, rapid technological advances have left its present network infrastructure outdated and unable to keep pace with modern manufacturing-process demands.
Manufacturing A.B.C.'s network combines multi-vendor legacy wired and wireless components, resulting in frequent downtime and reduced production efficiency. Its aging equipment causes slow data-transfer rates, unreliable connectivity, and greater exposure to cyber threats. Fiber cabling should also be upgraded because OM2 is used for the most part.
Further compounding the network problems, the recent departure of the CTO has left the company without a clear course for the network-refresh project. The management team lacks consensus on the upgrade's scope, budget, and timeline.
The manufacturing customer's primary objectives are:
Improve network performance and reliability to improve production processes and minimize downtime.
Strengthen network security to safeguard sensitive data and intellectual property.
Streamline communication and collaboration among the organization's different departments.
Provide scalability for future growth and technological advances.
Manufacturing A.B.C. wants a comprehensive network refresh that includes:
Upgrading the wired infrastructure with high-speed Ethernet switches to support higher data-transfer rates and lower latency.
Deploying a robust wireless solution using enterprise-grade access points to provide seamless connectivity throughout the manufacturing facility.
Centralized network-management tools to simplify network administration and monitoring.
Expectations:
The customer expects the network-refresh project to be completed efficiently, with minimal disruption to ongoing operations. They want a reliable, experienced network-solutions provider that understands their distinctive manufacturing requirements and can deliver a tailored solution that meets their budget constraints. Given the recent CTO change, the manufacturing customer is eager to receive clear project proposals and decision-making support.
As the network-solutions provider, your role is to address these concerns, provide expert guidance, and present a clearly defined plan that effectively meets their objectives.
Assume that the current network infrastructure has no wireless shadow-IT equipment operating across the different floors/production sites, but you want to confirm this. How can you determine whether wireless shadow-IT equipment is currently in operation?
A large multinational financial institution has engaged you to design a new full-stack wired and wireless network for its new 6-story regional office building. The facility’s bottom two floors will be retail space for a large banking branch. The upper floors will be carpeted corporate office space, with each floor approximately 100,000 sq ft (9290 sq m). All data centers are offsite and outside this project’s scope. The customer is underserved by its existing L2-based network infrastructure and wants to use modern best practices in the new design. The network must be fully resilient and fault-tolerant, with dynamic segmentation at the edge.
The retail space will provide public guest Wi-Fi access. Retail associates will use corporate tablets for customer service, and a mixture of wired and wireless devices will be deployed throughout the retail floors. Corporate users will mainly use wireless connectivity, although several wired clients, printers, and hard VoIP phones will be used.
The customer also plans to renovate the corporate office space to take advantage of 'smart office' technology. These enhancements will enable blue-dot wayfinding, presence analytics, and other location-based services.
The client chose to authenticate wired headless devices using Mac Authentication, with RADIUS attributes returned to the NAD to assign VLAN and port-access parameters to the authentication session on the switch port.
What would be critical to making this a successful deployment?
Choose two.
A global cruise-line company needs to modernize its existing fleet. To make the ships more cost-effective and sustainable, it will refresh the ship “insides” and replace all WLAN/LAN hardware. This refresh will not change the company’s current security requirements. The CIO also wants to minimize unused switch ports. Any future expansion will always require a hardware refresh. The effort begins with the smallest ship, which supports a maximum of 800 guests.
Each ship has a LAN infrastructure comprising two core switches, up to 10 redundant distribution switches, and up to 500 access switches (400 cabins and 100 technical rooms). The core switches are in the ship’s MDF, and the distribution switches are in the IDFs. Every cabin and technical room receives one access switch.
The ship’s cabling structure will remain unchanged. Each IDF connects to the MDF through SMF, with two pairs available for the core-to-distribution interconnect. The SM fiber between the MDF and IDF is under 300 meters (980 ft) and is OS1. Each cabin connects to the IDF through one OM2 pair, at a maximum length of 60 meters (200 ft). Each technical room connects to the IDF through one OM2 pair, with lengths from 100 to 150 meters (320 to 500 ft).
For every cabin and technical room, the customer wants to replace the existing fan-less 2530/2540 switches without altering requirements, except that the uplink to the distribution switch must be upgraded to 10GbE to accommodate increased network traffic, and technical rooms require redundant power.
The WLAN infrastructure will be refreshed 1:1, with no new cabling or AP locations. It is based on 200/300-series indoor and outdoor APs running InstantOS (fewer than 300 APs), and the customer has no WLAN requirement changes.
The cruise-line company will replace its current Internet connection before the LAN/WLAN refresh. The new connection will deliver 99.8% uptime, needed to keep paid guest Wi-Fi continuously operational. Because this Internet connection is guaranteed, the CIO wants the design based on Aruba’s ESP architecture.
Based on best practices, which switch model is the most cost-effective choice for the distribution layer?
Before starting the design for HPE Aruba Networking Cloud Authentication at a distributed enterprise, you must collect information about the customer’s current identity infrastructure and endpoint capabilities. The customer has indicated interest in a cloud-native authentication solution, but details about its identity infrastructure or endpoint capabilities still need to be gathered.
As the network architect, you must proceed with initial planning by recording reasonable assumptions about the existing environment and its readiness to support cloud-native authentication.
Which assumptions are appropriate to include at this point to guide the design process?
Choose two.
XYZ Regional Hospital is an integrated healthcare system comprising hospitals, neighborhood health centers, and small doctor offices. XYZ Regional Hospital recently merged with 4x neighborhood health centers and 125 doctor branch offices. Its wireless, wired-access, and AAA solutions are outdated and must be replaced.
XYZ Regional Hospital wants to future-proof and improve efficiency at every site by enhancing wired and wireless access and moving to centralized, unified wired/wireless and policy management that provides uninterrupted availability for all systems.
Locations:
XYZ Regional Hospital is located in New York City.
Dila Health Center is located in City A.
Mount Health Center is located in City B.
Rock Health Center is located in City C.
Branch clinics are located at different locations across the United States.
Requirements:
Provide, through management software, a single pane of glass to manage wired and wireless LANs and VPNs across campus, branch, and remote locations through a web/cloud architecture that provides near-real-time insight, troubleshooting tools, and Service Level performance reporting.
Seamless integration across wired, wireless, WAN, SD-Branch, and IoT.
Provide secure wireless access for all Regional Hospital employees and partners, as well as wireless Internet access for medical citizens when they visit the facilities.
All access points must support these features and specifications: 802.11 ax (Wi-Fi 6E Certified).
Security options including WP2/WPA3 and 802.1X with Radius secure authentication.
Identify and authenticate every wireless and wired device.
End-to-end role-based security.
Seamless mobility across the hospital for medical teams, patients, and visitors.
Reduce Wi-Fi deployment time from days to hours and enable Zero-Touch deployments across the site.
Establish a resilient, future-ready network infrastructure with the intelligence, scalability, and intuitive toolsets to address emerging needs.
Fully redundant branch solution with dynamic path selection to the hospital.
XYZ Regional Hospital is concerned about the performance of new latency-sensitive applications that will be introduced when connected wirelessly. Which solution addresses this concern?
You meet with a customer to update the network after the prior network manager has left the company for another role.
Which methods can validate the current network state when the available network documentation is invalid?
Choose two.
During the stakeholder interview, an agenda is created to clarify customer expectations. The customer is concerned about future business requirements, with network scalability and flexibility being key.
Which expectations should be considered to solve upcoming business problems?
Choose two.
Which documentation resources can be used to find validated information about HPE Aruba Networking products that helps the architect build the solution design?
Choose three.
Mark the layer at which Dynamic Multicast Optimization should be activated.
HPE campus multicast network diagram showing services aggregation, standalone core, access aggregation, access layer and wireless access

You are working with a large enterprise customer preparing to deploy HPE Aruba Networking ClearPass Policy Manager (CPPM) across multiple campus locations. They have asked that ClearPass Insight be included in the technical proposal so they can use its historical reporting and analytics capabilities.
As part of the design consultation, the customer specifically wants to understand:
Whether Insight needs additional licensing or subscriptions.
How enabling Insight affects the size and structure of their CPPM cluster.
Which best practices they should follow to enable Insight resiliently and at scale.
Confirm which statements about HPE Aruba Networking ClearPass Insight are accurate so they can plan the correct number of nodes and licensing in the IRIS-generated Bill of Materials.
Choose two.
A large multinational financial institution has hired you to design a new full-stack wired and wireless network for its new 6-story regional office building. The bottom two floors of the facility will provide retail space for a large banking branch. The upper floors will be carpeted corporate office space, with each floor measuring approximately 100,000 sq ft (9290 sq m). All data centers are offsite and are out of scope for this project. The customer is underserved by its existing L2-based network infrastructure and wants to use modern best practices in the new design. The network must be fully resilient and fault-tolerant, with dynamic segmentation at the edge.
The retail space will provide public guest Wi-Fi access. Retail associates will use corporate tablets for customer service, and the retail floors will contain a mix of wired and wireless devices. Corporate users will primarily connect wirelessly, but several wired clients, printers, and hard VoIP phones will also be used.
The customer also plans to renovate the corporate office space to take advantage of 'smart office' technology. These improvements will enable blue-dot wayfinding, presence analytics, and other location-based services.
The client has decided that the more critical switch stacks supporting Contact Center resources must support greater than 600W of CL4 PoE and redundant power supplies. These stacks will have approximately six members.
What is the most economical switch series choice that meets these requirements?