Regarding the process described above, what is the most important recommendation you would make using IEEE 1044 as a guide? 2 credits
According to the ISTQB Glossary, regression testing is required for what purpose?
Which of the following is an example of testing as part of the requirements specification phase? 1 credit
What is the main reason why reviews are especially beneficial in the above-mentioned scenario? 2 credits
Relying only on the information provided in the scenario, select the TWO items and/or features for which sufficient information is available to proceed with test design. 2 credits
IEEE 1028 also defines “management review” as a type of review. What is the main purpose of a management review? 1 credit
Considerable attention will be given in this project to defining exit criteria and on reporting back on their status. Which combination of TWO exit criteria from the list would be best to use? 1 credit
I. Total number of defects found
II. Percentage of test cases executed
III. Total test effort planned versus total actual test effort spent
IV. Defect trend (number of defects found per test run over time
Which of the following product risks would be most effectively addressed just by static testing? 3 credits
Why might a RAD approach be a better option for the test manager rather than a sequential development? 2 credits
Which one of the following estimation approaches is appropriate at this stage of the project? 2 credits
Identify THREE items that would be part of the work-breakdown structure showing the key testing activities for the acceptance test project. 2 credits (for 2 out of 3 correct 1 credit)
In general, why is it NOT a good idea to estimate the testing effort based only on a percentage of development effort? Identify THREE valid reasons. 1 credit
In general which part of the testing activity is most difficult to estimate? 1 credit
Which of the following would be the most significant input to estimating the time to carry out the specified testing tasks? 3 credits
Which of the following is a characteristic of good testing in any life cycle model? 1 credit
Given is the following defect removal chart reported at the end of system testing - showing total defects detected and closed defects (fixed and successfully retested). A number of open defects are classified as critical. All tests have been executed.
Based on the chart above, what is the most appropriate next test phase? 1 credit
Evaluate the status of the project against the defined exit criteria. Which of the following options shows the correct status? 2 credits
Given the following figures for the testing on a project, and assuming the failure rate for initial tests remains constant and that all retests pass, what number of tests remain to be run? 3 credits
Model characteristics:
Which THREE of the below mentioned characteristics relate to TMMi? 1 credit
Which of the following would you least expect to form part of the analysis of initial tool costs? 1 credit
Select THREE issues from the options provided that should at least be raised. 1 credit
In addition to risk, identify TWO other components of a testing strategy. 1 credit
What would be a test approach regarding the test design techniques to be applied that would fit an item with the highest risk? 2 credits
Part of the testing strategy indicates that you are going to be using systematic test design techniques. Your manager has asked that you present the main advantages of using these techniques at the next board meeting. Identify THREE main benefits of using systematic test design techniques within this company. 2 credits (for 2 out of 3 correct 1 credit)
Which of the following team roles would be most appropriate to enhance the team and why? 2 credits
A number of options have been suggested for the level of independence to be employed for the testing on the next project, and are shown below.
i. External test specialists perform non-functional testing.
ii. Testing is outsourced.
iii. Testing is carried out by the developer.
iv. A separate test team carries out the testing.
v. Testing is performed by the business.
vi. Testing is performed by a different developer.
Which of the following orders the above in a correct order of independence? 1 credit