Which one of the following statements is NOT correct in respect of FIDIC Red Book (both editions)?
(The Employer is a leading company in the hospital and medical care sector who wishes to build a new hospital. The Employer is considering approaching a financial institute to secure most of the funds; therefore, he requires clarity and stability in terms of the Project ' s budget and time for completion. Which book do you recommend?)
Under the FIDIC Red and Yellow Books (edition 2017), which two of the following elements shall form part of the initial time Programme?
Which FIDIC Book (edition 2017) should be considered first by an Employer that is an experienced employer who knows exactly what they want from a design & engineering perspective?
(Under the FIDIC Red Book, which of the following statements are correct? [2017 Edition] (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).)
Regarding FIDIC Yellow and Silver Books (edition 1999) the Contractor has submitted its design proposal through the Contractor ' s Proposal. Which two of the following statements are true in this respect, after it has been submitted?
Choose all of the correct answers (multiple possibilities).
You are the Contract Manager of the Engineer and person Y is the Contract Manager of the Employer in a construction project under FIDIC 2017 Red Book. The project is late in schedule and Y has issued Employer ' s claim on Delay Damages. You have asked Y to consider whether the Contractor ' s delay to completion is a reflection of cash-flow shortfall from interim payments before making deductions to the Contractor ' s payment. Y replied that even if the Contractor pays Delay Damages to the Employer, the Contractor is still obliged to complete the Works and is not relieved from its duties and obligations. You warned Y of the risks of further reduction of cash-flow by the deduction of Delay Damages from payments. As this could worsen the situation of the Contractor, leading to further delays to the completion of the Works. Who is right?
(You are the Contract Manager of the Employer ' s Representative for a project using FIDIC Silver Book (edition 1999). The Contract Agreement does not define the Commencement Date. The Contract has been legally effective for 4 weeks. You are writing a letter urging the Employer to issue a Notice of Commencement Date. Why is this important? (2 correct answers apply))
(Upon review of the revised programme, submitted by the Contractor, if the Engineer (under FIDIC Red or Yellow Books) or Employer (under FIDIC Silver Book) does not give a Notice of Non-Compliance within 14 days after receiving a revised programme, then… [complete the sentence, thereby considering FIDIC Red, Yellow, and Silver Books (edition 2017)]. (1 correct answer applies))
(Which of the following two statements are correct regarding subcontractors under FIDIC Red, Yellow, and Silver Books (edition 2017)?
Choose all of the correct answers (multiple possibilities).)
You are the Contract Manager of the Engineer in a hotel project. In May 2020, the Employer and the Contractor signed a Contract based on the FIDIC Yellow Book (edition 2017), as per which the Contractor will design and build a hotel project with Contract Price of 5,100,000 USD. The Time for Completion for this project is 12 months (May 2021). The Contract also named a nominated Subcontractor (as referred to in Sub-Clause 4.5) who provides mechanical, electrical, and plumbing services for the project (including the fire fighting system), which was accepted by the Contractor without any discussions.
The Project was delayed due to issues with the fire fighting system, and you issued the Taking-Over Certificate in June 2022.
The Employer sent a Notice of Claim to the Contractor on Delay Damages with a maximum value equal to 10% of Contract Price (510,000 USD). The Employer also gave a Notice to the Contractor stating that the Contractor has failed to submit the evidence of payment to the nominated Subcontractor as well as the reason for withholding payment to the nominated Subcontractor. Therefore, the Employer has paid the nominated Subcontractor directly the entire amount due, coming to 100,000 USD. The Employer intends to include this amount as a deduction in the Final Payment to the Contractor.
As Contract Manager of the Engineer, you are tasked to make a fair determination of the Notices of the Employer. In your " Notice of the Engineer ' s determination " , what is your determination for the deduction of the next Interim Payment to the Contractor in relation to the amount directly paid to the nominated Subcontractor?
(Under the FIDIC Red, Yellow, and Silver Books (edition 1999), which of the following entitlements of the Employer can result in a deduction of the Contract Price and Payment Certificates subject to Sub-Clause 2.5? (2 correct answers apply))
Which one of the following documents constitutes a contract and is considered binding on both parties, when the Employer wants to award the Contract to the tenderer?
Which of the following documents form part of a FIDIC Construction Contract [ " Red Book " (1999)], hence, to be drafted and included among the Tender Documents? (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
You are the Contract Manager of the Employer ' s Representative in a Thermal Power Plant Project. The Contract for this project is EPC Turnkey Contract using the FIDIC Silver Book (edition 2017) with a Contract Price of 28 million USD. The Employer ' s Requirements require that: " the Contractor design in accordance with international and national technical regulations, and standards, [etc.] " .
For piling works, the Employer ' s Requirements state that the Contractor will design according to a specific national standard for piling works NTS-PW-01. After all piles for the jetty have been installed, a pile load test on lateral bearing capacity shows that actual lateral bearing capacity is much lower than the calculated lateral bearing capacity. It was later revealed by the Technical Standard Committee that there was a typo mistake during preparation of the NTS-PW-01 (translated from a foreign standard). The lateral bearing capacity of installed piles had been substantially overestimated as a result of this typo. Contractor submits a claim for 200,000 USD regarding extra costs for installing additional piles as a result of errors in the Employer ' s Requirements.
In the hydrological information of Site Data provided by the Employer, the annual high water level is 4.0m. However, during the design stage, with updated data from local stations along the rivers, the Contractor found out there was a mistake in the calculation. The annual high water level should be 4.5m. As a result, the Contractor has to design and build additional flood walls along the river to protect the Plant from flooding. The Contractor claims an amount of 300,000 USD to construct the flood wall, based on Unforeseeable difficulties.
As the Employer ' s Representative, after you have consulted with both Parties but failed to reach agreement, you will make a fair determination of the Claims of the Contractor.
In your " Notice of the Employer ' s Representative ' s determination " , what is your determination for the Contractor?
Through which two of the following documents may the Employer give information to the Contractor of a planned timetable of meetings such as management meetings, site meetings, technical meetings, and progress meetings?
Choose all of the correct answers (multiple possibilities).
(Sub-Clause 12.3(a) of FIDIC Red Book (edition 1999) specifies four criteria which are applicable without reference to Clause 13. A new rate shall only be appropriate if all four criteria are satisfied. Is this statement true or false?)
You are the Contract Manager in a highway project using FIDIC Red Book (edition 1999). You work for the Employer – a highway management agency. During the tender period, you are informed of a specific Commencement Date required by the directors of the agency. Which two of the following approaches to inform the tenderers of this date are clearly and unambiguously drafted?
Choose all of the correct answers (multiple possibilities).
A new important feature of the FIDIC Yellow and Silver Books (edition 2017) is the inclusion of the default position that the Works or relevant part of the Works designed by the Contractor shall be fit for their ordinary purposes. Is this statement true or false?
You are the Contract Manager of the Engineer in a condominium project under FIDIC Yellow Book (edition 2017), with Time for Completion of 5 months.
The Contractor received a Letter of Acceptance on 1 May 2022. The Contract Agreement was signed on 1 June 2022. The Contract Agreement states that the Commencement Date shall be notified by the Engineer, but it shall be no later than 14 days after the signing of the Contract Agreement, subject to the issuance of the construction permit.
1 July 2022 is the first day the Engineer was at Site. On the same day, the Engineer issued a Notice to the Contractor that the Commencement Date shall be 15 July 2022. However, the construction permit was issued only on 1 August 2022.
The Project was completed on 1 December 2022. After completion, the Employer submitted a claim for Delay Damages. Following consultations, the Parties could not reach agreement on the Commencement Date.
What is the correct Commencement Date?
In case a Variation is initiated by the Engineer for prompt implementation ...... [FIDIC Red, and Yellow Books, 2017 Editions]
Choose all of the correct answers (multiple possibilities).
(Under the FIDIC Red, Yellow, and Silver Books (both editions), the Contractor has a contractual obligation to give notice to the Employer if it discovers errors or defects of a technical nature. Is this statement true or false?)
Which of the following situations form legally binding contracts? (2 correct answers apply)
Choose all of the correct answers (multiple possibilities)
Choose which one statement consists of an example of an unclear and ambiguously drafted Particular Conditions.
Which of the following cases will allow the Employer to claim under the Performance Security? [2017 Edition] (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
FIDIC Red, Yellow, and Silver Books (both editions) contain a provision for the Engineer or Employer to instruct the Contractor to employ a subcontractor, thereby also permitting the Contractor to refuse to employ such proposed subcontractor on the basis of a reasonable objection by a notice. Is this statement true or false?
(Which one of the following statements is correct regarding the Employer ' s Representative under the FIDIC Silver Book (edition 1999)?)
The Employer has prepared a contract for a waste-to-energy project based on the FIDIC Yellow Book (edition 1999). You are preparing negotiations on behalf of one of the Subcontractors with the Contractor. The main Contractor will manage the design and build of the Works, whereby the Subcontractor will deliver critical systems regarding power generation and cooling. The Contractor intends to contract the main Contract back-to-back with the Subcontractor. In the proposed back-to-back subcontract, the following amendment is proposed through Particular Conditions:
" Sub-Clause 4.4. The following paragraph is added: The Subcontractor is required to scrutinize the Employer ' s Requirements in a manner identical to the obligations of the Contractor as stated in Sub-Clause 5.1 of the Main Contract. The Subcontractor will indemnify and hold harmless (up to the maximum liability of the Subcontractor) the Contractor with regard to any error, fault or other defect found in the Employer ' s Requirements, its items of reference or Contractor ' s design of the Works for the scope part for which Subcontractor is contracted. "
What is your advice to the Subcontractor (SC) in regard to entering this proposed subcontract?
(In a region experiencing civil unrest and armed conflict under a FIDIC Red Book 1999 Contract, violence escalates into an insurrection, forcing the Contractor to stop work and retreat to a secured compound. The Contractor issues a notice claiming this is an Employer’s Risk under Sub-Clause 17.3 (a) and (b), requesting Extension of Time and Cost. What is the most appropriate position for the Engineer at this stage?)
Under the FIDIC Red Book (edition 1999): the Contractor submitted Final Statement in accordance with the Contract and the Contractor wants to correct it. Can the Contractor correct the Final Statement?
Which one of the following statements regarding drafting contracts based on FIDIC Books is correct?
Under the FIDIC Red Book (edition 2017), the Engineer has suspended works to come to a change of the design of a part of the Works. After expiry of 84 days of suspension, the Contractor gave notice thereof. Following this notice, the suspension was not lifted within 28 days. What two statements are correct in such a situation?
(Golden Principle 2 states that " The Particular Conditions must be drafted clearly and unambiguously. " Which statement best underlines this Golden Principle in relation to the FIDIC Red, Yellow, and Silver Books (both editions)?)
Which two of the following statements are correct regarding the dayworks under FIDIC Red, Yellow, and Silver Books (both editions)?
Choose all of the correct answers (multiple possibilities).
Towards the end of implementing a varied work (initiated originally by the Contractor as a " Value Engineering Proposal " , relevant designs provided by the Contractor) it turned out, that there is some part of it not complying with the otherwise prevailing standards. Which statements are correct in this situation? [FIDIC Red Book, 2017 Edition]
Choose all of the correct answers (multiple possibilities).
You are the Contract Manager of the Engineer for a contract using FIDIC Yellow Book (edition 2017). You are drafting a notice holding the Commencement Date. Which one of the following approaches has the most clear and unambiguous drafting?
(Based on Clause 8 in both FIDIC Yellow and Silver Books (edition 1999), is the Contractor allowed to start the design of the Works before the Commencement Date? (1 correct answer applies))