Which of the following statements are not correct? [2017 Edition]
Choose all of the correct answers (multiple possibilities).
The procurement process of a project executed based on any FIDIC Contract model is exactly the same in terms of definitions, time and steps, which makes it universal and more easy to use worldwide. Is this statement true or false?
Which two of the following statements are correct regarding Dispute under the FIDIC Red, Yellow, and Silver Books (edition 2017)?
Choose all of the correct answers (multiple possibilities)
You are the Contract Manager in a highway project using FIDIC Red Book (edition 1999). You work for the Employer– a highway management agency. During the tender period, you are informed of a specific Commencement Date required by the directors of the agency. Which two of the following approaches to inform the tenderers of this date are clearly and unambiguously drafted?
Choose all of the correct answers (multiple possibilities).
You are the Contract Manager for the Engineer in a hospital project using FIDIC Yellow Book (edition 2017). The Employer demands perfection in the project's design and construction quality. There are many Variations initiated by the Employer during design and construction. Which one of the following is considered to be a valid Variation?
What are two differences between a notice and other communications under the FIDIC Red Book (edition 2017)? (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
Which of the following form a Contractor's entitlement, in case the Contractor does not receive an interim payment within the allocated contractual deadline for payment? (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
Which one of the following statements is NOT correct in respect of FIDIC Red Book (both editions)?
Under the FIDIC Yellow Book (both editions), the Contract is administered by the Employer (unless it appoints an Employer's Representative) who endeavours to reach agreement with the Contractor on each claim. Is this statement true or false?
Under the FIDIC Red and Yellow Books (edition 1999): if the Engineer gives an instruction which requires the Employer's prior approval, the Contractor is required to verify whether the Engineer has obtained the Employer's prior approval or not. Is this statement true or false?
The details of all the matters that have been clarified and agreed between the Employer and tenderers during the tender stage are recorded by, for instance, a memorandum of understanding. The Employer may award the contract to the tenderer through a letter of formal acceptance, signed by the Employer. This process is in compliance with which one of the following Golden Principles (GP's)?
Which one of the following documents constitutes a contract and is considered binding on both parties, when the Employer wants to award the Contract to the tenderer?
Which two statements are true under the FIDIC Red Book (edition 1999)?
(Choose all of the correct answers — multiple possibilities)
Under the FIDIC Red Book (edition 1999), if the Contractor as per Sub-Clause 14.2 has to ensure the Employer receives an Advance Payment Guarantee as per the standard model, what type of instrument should this be?
Upon review of the revised programme, submitted by the Contractor, if the Engineer (under FIDIC Red or Yellow Books) or Employer (under FIDIC Silver Book) does not give a Notice of Non-Compliance within 14 days after receiving a revised programme, then ... [complete the sentence, thereby considering FIDIC Red, Yellow, and Silver Books (edition 2017)]. (1 correct answer applies)
Which two statements reflect an INCORRECT application of a Golden Principle?
For the FIDIC Red Book (both editions), the Contractor is required to submit a progress report monthly. When does the Contractor's reporting requirement end?
You are the Contract Manager of the Engineer in a condominium project under FIDIC Yellow Book (edition 2017), with Time for Completion of 5 months.
The Contractor received a Letter of Acceptance on 1 May 2022. The Contract Agreement was signed on 1 June 2022. The Contract Agreement states that the Commencement Date shall be notified by the Engineer, but it shall be no later than 14 days after the signing of the Contract Agreement, subject to the issuance of the construction permit.
1 July 2022 is the first day the Engineer was at Site. On the same day, the Engineer issued a Notice to the Contractor that the Commencement Date shall be 15 July 2022. However, the construction permit was issued only on 1 August 2022.
The Project was completed on 1 December 2022. After completion, the Employer submitted a claim for Delay Damages. Following consultations, the Parties could not reach agreement on the Commencement Date.
What is the correct Commencement Date?
Through which two of the following documents may the Employer give information to the Contractor of a planned timetable of meetings such as management meetings, site meetings, technical meetings, and progress meetings?
Choose all of the correct answers (multiple possibilities).
Which FIDIC Book (edition 2017) should be considered first by an Employer that is an experienced employer who knows exactly what they want from a design & engineering perspective?
Which one of the following statements best describes the requirements of Time for Completion?
Towards the end of implementing a varied work (initiated originally by the Contractor as a "Value Engineering Proposal", relevant designs provided by the Contractor) it turned out, that there is some part of it not complying with the otherwise prevailing standards. Which statements are correct in this situation? [FIDIC Red Book, 2017 Edition]
Choose all of the correct answers (multiple possibilities).
Under the FIDIC Red Book (edition 1999): the Contractor submitted Final Statement in accordance with the Contract and the Contractor wants to correct it. Can the Contractor correct the Final Statement?
You are the Contract Manager of the Engineer for a contract using FIDIC Yellow Book (edition 2017). You are drafting a notice holding the Commencement Date. Which one of the following approaches has the most clear and unambiguous drafting?