Question # 6

Which is an objective of the Closing a Project process?

A.

Review and approve the plan for project closure

B.

Review the performance of the project against its baseline

C.

Perform any post-project reviews

D.

Create a Benefits Review Plan

Full Access
Question # 7

What process aims to ensure accurate progress information is provided to the Project Manager?

A.

Starting up a Project

B.

Managing a Stage Boundary

C.

Managing Product Delivery

D.

Directing a Project

Full Access
Question # 8

Which is a purpose of a Project Product Description?

A.

Records the costs and timescales for delivery of the project's final product

B.

Shows the dependencies between the project's products to aid planning

C.

Provides a list of all the products to be delivered by the project

D.

Defines what theproject must deliver in order to gain acceptance

Full Access
Question # 9

Which is a responsibility of a risk owner?

A.

Identify risks to the project that might occur in their department

B.

Own and authorize theuse of the risk budget to fund risk responses

C.

Manage, monitor and control all aspects of an assigned risk

D.

Determine project risk appetite

Full Access
Question # 10

Which is a purpose of a Risk Register?

A.

Capture risks that may occur during the project

B.

Record how risk management activities will be undertaken on the project

C.

Record the risk tolerance for the project

D.

Capture issues which are impacting on the delivery of the project objectives

Full Access
Question # 11

Which of the following statements about quality assurance and Project Assurance is true?

A.

Project Assurance is the responsibility of the corporate organization; quality assurance is the responsibility of the Project Board

B.

Project Assurance is independent of the Project; qualityassurance is only independent of the Project Manager

C.

Project Assurance may be delegated within a project; quality assurance must be undertaken by the Project Board

D.

Project Assurance ensures compliance to standards within the project environment; quality assurance ensures compliance across the organization

Full Access
Question # 12

How many tasks does the product-based planning technique describe?

A.

One

B.

Two

C.

Three

D.

Four

Full Access
Question # 13

Which may be funded from a risk budget?

A.

Corrections due to off-specifications

B.

Impact analysis of requests for change

C.

Implementation of a fallback plan

D.

Preparation of the Risk Management Strategy

Full Access
Question # 14

Which of the following describes a use of a Configuration Item Record?

A.

Define the identification scheme to be applied to the project

B.

Identify the techniques and procedures required within the Work Package

C.

Record the change in a product's status

D.

Record the reporting requirements for theWork Package

Full Access
Question # 15

Which describes the 'Identify Risks' step within the recommended risk management procedure?

A.

Identify responses to risks documented in the Business Case

B.

Gather information about the project environment and objectives

C.

Identify the roles to be involved in risk management activities

D.

Identify uncertainties that may impact on the delivery of the project objectives

Full Access
Question # 16

Which is a purpose of the Risk theme?

A.

Establish a procedure to ensure every change is agreed by the relevant authority before it takes place

B.

Establish a cost-effective procedure to identify, assess and control uncertainty

C.

Establish mechanisms to control any unacceptable deviations from plan

D.

Establish mechanisms to manage risks at the corporate or programme level of an organization

Full Access
Question # 17

Which statement describes the Implement' step within the recommended risk management procedure?

A.

Take planned action to respond to a risk

B.

Implement the responsibilities for risks defined in the Risk Management Strategy

C.

Assess the proximity of a risk

D.

Identify the level of risks that can be tolerated by the project

Full Access
Question # 18

Which is a type of issue?

A.

A lesson

B.

A request for change

C.

An Exception Report

D.

A risk with an estimated high impact

Full Access
Question # 19

Identify the missing word in the following sentence. The [?] theme defines that the Project Board is responsible for the overall direction and management of the project,

A.

Progress

B.

Plans

C.

Organization

D.

Business Case

Full Access
Question # 20

Where should an off-specification be recorded?

A.

Risk Register

B.

Issue Register

C.

Work Package

D.

Configuration Management Strategy

Full Access
Question # 21

Why is a Project Brief produced?

A.

To act as a trigger for the Starting up a Project process

B.

To record the strategies andmanagement controls to be used by a project

C.

To provide a full and firm foundation for the initiation of a project

D.

To be used by the Project Board as a basis for reviewing the progress of a project

Full Access
Question # 22

Which is part of quality control?

A.

Document the project's acceptance criteria in the Project Product Description

B.

Define the quality responsibilities of those involved in the production of the products

C.

Produce quality records to show that the planned quality activities have been carried out

D.

Maintain the corporate organization's quality management system

Full Access
Question # 23

Which is a purpose of the Closing a Project process?

A.

Authorize the final stage of the project

B.

Confirm that all benefits defined in the Business Casehave been achieved

C.

Recognize whether objectives set out in the original Project Initiation Documentation have been achieved

D.

Delegate day-to-day management of the end of the project to the Project Manager

Full Access
Question # 24

Which is NOT a purpose of the Initiating a Project process?

A.

Enable a Project Boarddecision about the commitment of resources to a project

B.

Enable an organization to understand the work that needs to be done to deliver a project's products before a project is approved

C.

Establish solid foundations for a project

D.

Enable the Project Board to decide whether it is worthwhile to initiate a project

Full Access
Question # 25

Which is a true statement about PRINCE2 event-driven controls

A.

Event-driven controls take place at predefined periodicintervals

B.

Event-driven controls are produced at the frequency defined in a Work Package

C.

Event-driven controls are used for decision making

D.

Checkpoint Reports are event-driven controls

Full Access
Question # 26

How many roles make up the Project Board?

A.

One

B.

Two

C.

Three

D.

Four

Full Access
Question # 27

What plan is created, and submitted for approval, during the Managing a Stage Boundary process?

A.

Team Plan

B.

Stage Plan

C.

Benefits Review Plan

D.

Project Plan

Full Access
Question # 28

What theme estimates the cost of delivering the project?

A.

Business Case

B.

Change

C.

Plans

D.

Progress

Full Access
Question # 29

Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?

A.

Create a separate Project Board to manage the supplier elements of the project

B.

Create multiple smaller Project Boards during the process of Starting up a Project, one for each of the project's stages.

C.

Create user and supplier groups

D.

Appoint corporate quality assurance to perform the Project Assurance role for all members of the Project Board

Full Access
Question # 30

Which is a purpose of the Directing a Project process?

A.

Create and authorize the project mandate

B.

Ensure that work on products allocated to the team is authorized and agreed

C.

Control the day-to-day running of the project

D.

Delegate day-to-day management of the project to the Project Manager

Full Access
Question # 31

What needs to be in place to ensure effective issue and change control?

A.

Configuration management system

B.

Manage by exception

C.

Quality planning

D.

Information needs for stakeholders

Full Access
Question # 32

Which is a purpose of an End Project Report?

A.

Identify individuals or groups that need to be told that the project is coming to an end

B.

Review how well the project performed against the Project Initiation Documentation used to authorize it

C.

Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed

D.

Ensure that key project information is archived and made secure

Full Access
Question # 33

Which statement about the Directing a Project process is true?

A.

Provides a mechanism for the Project Board to assure that there is continuedbusiness justification

B.

Covers the day-to-day activities of the Project Manager

C.

Ensures there are regular progress meetings

D.

Begins on completion of the Initiating a Project process

Full Access
Question # 34

Which is a purpose of a Lessons Log?

A.

Note any lessons that are raised in Checkpoint Reports

B.

Record that corrective action is being taken

C.

Escalate lessons to the Project Board

D.

Raise improvements with Project Assurance

Full Access
Question # 35

Which role is responsible for creating Checkpoint Reports?

A.

Senior Supplier

B.

Team Manager

C.

Change Authority

D.

Project Support

Full Access
Question # 36

Which is a purpose of an Issue Report?

A.

Provide the status of all issues in a Work Package

B.

Document an issue that needs to be handled formally

C.

Provide the status of all the issues in a stage

D.

Notify the Project Manager of all new issues in a Work Package

Full Access
Question # 37

What is used to identify any organization or interested party who needs to be informed of project closure?

A.

Configuration Management Strategy

B.

Project management team structure

C.

Communication Management Strategy

D.

Project Brief

Full Access
Question # 38

Which PRINCE2 principle helps to address a concern that the project team may NOT have worked on a similar project?

A.

Defined roles and responsibilities

B.

Learn from experience

C.

Manage by exception

D.

Focus on products

Full Access
Question # 39

Where should the names of those who are to approve a product be recorded?

A.

Product Status Account

B.

Product Description

C.

Configuration Item Record

D.

Checkpoint Report

Full Access
Question # 40

Which statement applies to Stage Plans?

A.

Always have the same duration as the Project Plan

B.

Are produced at the same time as the Project Initiation Documentation

C.

Assist the Project Manager inthe day-to-day running and control of the project

D.

Provide a baseline against which the Project Board monitor overall progress

Full Access
Question # 41

Which is an objective of the Managing a Stage Boundary process?

A.

Understand what has gone well and what can help the next stage

B.

Review and approve the next Stage Plan

C.

Assure the Project Board that all project products have been completed and approved

D.

Prepare an Exception Report to advise the Project Board of aforecast deviation from tolerance

Full Access
Question # 42

Which is a purpose of the Controlling a Stage process?

A.

Assign work to be done and take corrective action to ensure that the stage remains within tolerance

B.

Provide a fixed reference point at which acceptance for the project product is confirmed

C.

Enable the Project Board to be provided with sufficient information to authorize the next stage

D.

Enable the organization to understand the work that needs to be done to deliver the project's products

Full Access
Question # 43

Which is a purpose of the Risk theme?

A.

Establish a method for the implementation of continuous improvement during the project

B.

Identify, assess and control problemsthat have occurred

C.

Provide the Project Board with a time-driven control to capture all project risks

D.

Establish a cost-effective procedure to identify, assess and control risks