Winter Sale - Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dpt65

CDT Questions and Answers

Question # 6

Which team member is actively involved and interested in all phases of the project?

A.

Contractors

B.

Owners

C.

Architects/engineers

D.

Manufacturers/suppliers

Full Access
Question # 7

What does the term “specifications” in the project manual apply to?

A.

All written construction documents

B.

All written and drawn construction documents

C.

Qualitative requirements for products, materials, and workmanship

D.

Quantitative requirements for products, materials, and workmanship

Full Access
Question # 8

Which member of the project team initiates the project, assumes the risk, controls and manages the design and construction process, and provides the funding?

A.

Contractor

B.

Designer

C.

Supplier

D.

Owner

Full Access
Question # 9

Modifications to the contract documents after execution of the owner–contractor agreement include which of the following?

A.

Change order, construction change directive, and field order

B.

Field order, construction change directive, and request for information

C.

Addendum, change order, and request for information

D.

Supplemental instructions, work change directive, and addendum

Full Access
Question # 10

Which term or word is appropriate to use in specification text?

A.

Any

B.

As per

C.

As required

D.

Work

Full Access
Question # 11

What determines the responsibilities of the participants on the project team?

A.

Size of the project

B.

Nature of the project

C.

Cost of construction

D.

Project delivery type

Full Access
Question # 12

When developing an operation and maintenance (O&M) budget for a facility, what should form the basis for budget decisions?

A.

The architect/engineer’s projected operating costs

B.

The construction manager’s life cycle analysis

C.

The estimator’s preliminary project description

D.

The facility manager’s historical record of actual costs

Full Access
Question # 13

Which type of warranty is used to provide a remedy to the owner for material defects or failures after completion and acceptance of construction?

A.

Warranty of title

B.

Implied warranty of merchantability

C.

Purchase warranty

D.

Extended warranty

Full Access
Question # 14

Standards for sustainable facilities, products, and fundamental approaches emphasize the needs of what?

A.

Architect, supplier, and contractor

B.

Owner, stakeholders, and participants

C.

Public, private, and environmental health

D.

Owner team, contractor team, and design team

Full Access
Question # 15

To obtain progress payments, the contractor must submit an application for payment itemized in accordance with what?

A.

The construction schedule

B.

The subcontractor’s invoices

C.

The schedule of values

D.

The percentage of completion

Full Access
Question # 16

Which of the following terms describes the process of allocating resources for the continued performance of a building’s intended function?

A.

Budgeting

B.

Commissioning

C.

Facility management

D.

Project closeout

Full Access
Question # 17

Where can you typically find requirements for temporary toilet facilities?

A.

Supplementary Conditions

B.

Division 22 – Plumbing

C.

The Owner–Contractor Agreement

D.

Division 01 – General Requirements

Full Access
Question # 18

When is decommissioning required for a facility?

A.

When the entire building is going to be demolished

B.

When the facility is no longer needed for operations

C.

When the facility will not be used again in the future

D.

When the building changes owners

Full Access
Question # 19

Which bid form component ensures equal consideration, transparency, and flexibility while awarding a contract, but also manages cost during execution for undefined and unforeseen construction conditions?

A.

Bid security and substitution

B.

Add and deduct alternatives

C.

Allowances and unit prices

D.

Liquidated damages and combined bids

Full Access
Question # 20

Which of the following is LEAST important to log when documenting the decision-making process?

A.

Date, time, and location of the meeting

B.

List of attendees and who they represent

C.

Length of time each attendee spent speaking

D.

Action items with responsibilities assigned and date to accomplish

Full Access
Question # 21

Which of the following is a format that standardizes the way text is arranged in specification pages so that it is best suited for easy reading and rapid reference?

A.

SectionFormat®

B.

PageFormat

C.

MasterFormat®

D.

UniFormat®

Full Access
Question # 22

When does a project reach substantial completion?

A.

When the project is sufficiently complete to allow its intended use

B.

When the project receives final inspections from the authorities having jurisdiction

C.

When the contractor's final application for payment is approved

D.

When all of the close-out documents have been reviewed and approved

Full Access
Question # 23

According to standard general conditions, which of the following is true about shop drawings?

A.

They are contract documents.

B.

They illustrate some portion of the work.

C.

They are reviewed only by the architect/engineer.

D.

They include performance charts, instructions, and brochures.

Full Access
Question # 24

Why should project closeout meetings be held?

A.

To set substantial completion

B.

To resolve subcontractor disputes

C.

To commission the project for occupancy

D.

To review handover procedures and activities

Full Access
Question # 25

A facility manager needs to replace a broken insulated glazing unit in an existing facility. Which source would be most appropriate for determining where and how to order the new unit?

A.

Record drawings

B.

Manufacturer's representative

C.

Project manual

D.

Record submittals

Full Access
Question # 26

Where are the limits of the work of each alternate defined?

A.

Agreement

B.

Bid Form

C.

Division 01

D.

Sections in Divisions 02–49

Full Access
Question # 27

The names of the project, owner, architect/engineer and consultants, and the general project data such as a location map are normally included in which of the following?

A.

Sheet index

B.

Cover sheet

C.

General notes

D.

Building code summary

Full Access
Question # 28

The three types of commissioning include systems and equipment commissioning, building envelope commissioning, and what other process?

A.

Mechanical commissioning

B.

Facility commissioning

C.

Process commissioning

D.

Total project commissioning

Full Access
Question # 29

What activity helps the owner assess the viability of a project, evaluate financial resources, and understand the project's potential impact on the community?

A.

Schematic programming

B.

Site selection

C.

Due diligence investigation

D.

Master planning

Full Access
Question # 30

To avoid miscommunication problems during construction, which best practice should the design professional use?

A.

Develop a good working relationship for verbally addressing problems as they arise

B.

Mark emails and electronic communications as "Urgent!" to ensure they are read right away

C.

Distribute meeting minutes to all attendees and concerned parties documenting key decisions and action items resulting from the meeting

D.

Leave detailed voicemail messages describing everything that needs to be done so there is a record of the direction

Full Access
Question # 31

When a public works project utilizes design-bid-build, which option would NOT minimize the risk of bid shopping?

A.

The architect/engineer/owner team can consider bid listing and bid depository provisions.

B.

Require bidders to provide a list of their intended subcontractors along with their bid.

C.

The subcontractor can withhold their prices from the bidder until the final moments before the deadline.

D.

The bidder can ask the subcontractor to reevaluate their prices to find a lower price after the subcontractor has submitted their price.

Full Access
Question # 32

Which is the reference document that includes guidelines and tools for the organization and presentation of design and construction drawings?

A.

AIA CAD Layer Guidelines

B.

National Institute of Building Sciences

C.

National BIM Standard – United States

D.

U.S. National CAD Standard

Full Access
Question # 33

What does Divisions 02-49 of the construction project manual address?

A.

Procurement instructions

B.

Distinct work results areas

C.

Temporary facilities and controls

D.

Life cycle activities

Full Access
Question # 34

What could a reference standard specification be based upon?

A.

Project manual for similar project

B.

Design intent

C.

Trade association standard

D.

Manufacturer's specification section

Full Access
Question # 35

The architect/engineer reviews submittals for which of the following reasons?

A.

To correct or change the design

B.

To monitor design conformance

C.

To review installation procedures

D.

To review substitution requests

Full Access
Question # 36

Which of the following is an example of preconstruction submittals?

A.

Product data

B.

Shop drawings

C.

Schedule of values

D.

Warranty documentations

Full Access