Summer Sale - Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70dumps

PK0-005 Questions and Answers

Question # 6

Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?

A.

Compromising

B.

Forcing

C.

Smoothing

D.

Collaborating

Full Access
Question # 7

Which of the following can help identify opportunities for future improvement following the successful closure of a project?

A.

Contract review

B.

Archived documents

C.

Postmortem

D.

Project rewards

Full Access
Question # 8

A project is about to start; however, the client is uncertain about the desired details for the final product. Which of the following methodologies should the project manager use?

A.

Agile

B.

SDLC

C.

Waterfall

D.

PRINCE2

Full Access
Question # 9

A project team is determining how an application will be moved to production, who the users will be, and what training is needed. Which of the following best describes what is being developed?

A.

Contingency plan

B.

Scope statement

C.

Transition plan

D.

Communication plan

Full Access
Question # 10

Given the following chart showing committed work (orange) vs. actual work completed (blue) across 10 sprints:

Question # 10

Which of the following best describes the team ' s performance?

A.

The team needs to adjust the planned work based on results.

B.

The team’s velocity is getting better.

C.

The team understands its velocity and is planning in an accurate manner.

D.

The team is doing more work than planned.

Full Access
Question # 11

The PM is concerned with multiple copies of the same file causing confusion. Which of the following would prevent this issue?

A.

Print media

B.

Knowledge base

C.

Ticketing system

D.

Collaboration tool

Full Access
Question # 12

Which of the following is an intended outcome of a stand-up meeting?

A.

To identify team members for next tasks

B.

To identify future tasks

C.

To identify stakeholders for next tasks

D.

To identify blocking tasks

Full Access
Question # 13

A PM wants to add a chart to the monthly status report to show major accomplishments for key events. Which of the following is the best chart to use?

A.

Milestone

B.

Gantt

C.

Burndown

D.

PERT

Full Access
Question # 14

A project sponsor tells the project manager that new regulatory environment changes are coming in the next month. Which of the following should the project manager do next?

A.

Register the issue in the issue log.

B.

Provide the change to the CCB.

C.

Implement a work-around.

D.

Add risk into the risk register.

Full Access
Question # 15

While working with a contractor, the project manager identified a communication conflict. The contractor did not agree that there was an issue. Which of the following should the project manager and contractor review?

A.

Scope of work

B.

Request for proposal

C.

Vendor rules of engagement

D.

Project schedule

Full Access
Question # 16

While a team was in a work session developing the QA plan for a project, the project manager realized that the team lacks the skills required for proper quality assurance. Which of the following steps should the project manager take next?

A.

Reassess the resource pool.

B.

Review the QA plan from a similar project.

C.

Check on available resources for additional team members.

D.

Escalate the issue to the project sponsor.

Full Access
Question # 17

A project manager would like to add external engineers to the current team. Engineers will participate in specific tasks only during the testing phase. Which of the following contracts would the project manager most likely use in this situation?

A.

Time and material

B.

Fixed-price

C.

Warranty

D.

Cost-plus

Full Access
Question # 18

A project manager is leading the implementation of a new service for a well-known, global company for which brand image is most important. The project will rely on contracted services. As part of the request for proposal process, the project team has identified a short list of vendors to submit proposals. Which of the following items should the project team consider as a primary factor to remove a vendor from consideration?

A.

The vendor ' s proposed schedule does not align with the desired schedule.

B.

The vendor is new and not well established in the market.

C.

The vendor has been linked to ESG concerns within the past month

D.

The vendor ' s quote was the highest of all the proposals.

Full Access
Question # 19

A project manager is beginning a new project that will include a high number of complex deliverables. Which of the following is the best to use to track deliverables that are yet to be completed?

A.

Resource management system

B.

Issue log

C.

Ticketing system

D.

Backlog

Full Access
Question # 20

A PM received feedback from the project sponsor that the resources involved in the project are unsure of their daily activities. Which of the following is the MOST effective step for the PM to take to ensure clarity within the team?

A.

Create a list of tasks and share it with the team.

B.

Resend the scope of work to the team.

C.

Review the Gantt chart weekly with the team.

D.

Have the project sponsor meet with the team.

Full Access
Question # 21

The PMO wants to streamline the routing and approval of project activities to provide up-to-date visibility of the status. Which of the following collaboration tools would be most appropriate to use?

A.

Real-time, multi-authoring tool

B.

Wiki knowledge base and search engine

C.

Workflow and e-signature platform

D.

File-sharing platform and storage system

Full Access
Question # 22

Which of the following would be best to utilize when managing communications for project teams across multiple time zones?

A.

Business collaboration tool

B.

Email

C.

Virtual meetings

D.

Enterprise CMS

Full Access
Question # 23

Given the information in the chart,

Question # 23

which of the following techniques should the project manager use to improve the project schedule in Sprint 1?

A.

Validating

B.

Crashing

C.

Training

D.

Avoiding

Full Access
Question # 24

Which of the following activities should a project manager perform during the closing phase? (Select three).

A.

Lessons learned

B.

Risk analysis

C.

Removing resources

D.

Acquiring resources

E.

Statement of work sign-off

F.

Stakeholder analysis

G.

Removing access

Full Access
Question # 25

A PM wants to provide a visual representation of how a project is organized into tasks and how the tasks relate to each other. Which of the following can the PM use?

A.

Milestone chart

B.

Gantt chart

C.

PERT chart

D.

WBS

Full Access
Question # 26

Which of the following is the most important activity for the project manager during the closure of a project?

A.

Obtain project sign-off.

B.

Capture lessons learned.

C.

Document historical information.

D.

Release resources.

Full Access
Question # 27

Hackers are attempting to extract large amounts of data to sell on the dark web. Which of the following steps should a project manager take next to mitigate this risk?

A.

Update the issue log.

B.

Apply the contingency plan.

C.

Transfer the risk.

D.

Submit a change request.

Full Access
Question # 28

The project team identifies a risk of delayed materials on a project in a remote location. Which of the following actions can the team take to transfer the risk?

A.

Determine alternative supplies to use.

B.

Source materials locally from other vendors.

C.

Move procurement under the general contractor.

D.

Schedule deliveries earlier to ensure availability.

Full Access
Question # 29

A project manager is assigned to a multinational project with team members from different continents. Which of the following is the MOST important aspect for the project manager to consider?

A.

Resource allocation

B.

Communication security

C.

Technological factors

D.

Cultural differences

Full Access
Question # 30

The project manager is creating the baseline schedule. Which of the following would be most helpful when completing this task?

A.

WBS

B.

CMS

C.

SOW

D.

RFP

Full Access
Question # 31

Due to multiple changes, the sign-off for the project scope baseline is delayed. The project sponsor has restricted the budget for this project. Which of the following should the project manager MOST likely do to move forward?

A.

Communicate with the affected stakeholders.

B.

Initiate a formal change request to modify the cost

C.

Adjust the scope to stay within the cost.

D.

Set a new cost using a lightweight estimation method.

Full Access
Question # 32

A project manager provided the team with a summary Gantt chart for the project. The team, however, has expressed interest in seeing the sequencing between all of the tasks. Which of the following should the project manager provide?

A.

Project network diagram

B.

Fishbone diagram

C.

Burndown chart

D.

Milestone chart

Full Access
Question # 33

Which of the following is a typical characteristic of Scrum?

A.

Large teams

B.

Low-risk scope

C.

Self-organized team

D.

Well-defined scope

Full Access
Question # 34

Stakeholders ask the PM to provide an updated budget. Which of the following is the most important reason to update a project ' s budget during the execution phase?

A.

Evaluate the project ' s communication plan.

B.

Track and manage the project’s financial condition.

C.

Report the project’s risks and issues.

D.

Distribute resources to the project.

Full Access
Question # 35

An IT infrastructure change request needs to be implemented in the production environment. Which of the following elements are the most important prerequisites? (Select two).

A.

Rollback plans

B.

Project management plan

C.

Deployment plan

D.

Asset management plan

E.

Communication plan

F.

Resource management plan

Full Access
Question # 36

Which of the following should a product manager choose in order to enable collaboration between team members located in different regions? (Select two).

A.

Real-time surveys/polling

B.

Wiki knowledge base

C.

Spreadsheets

D.

Meetings/face-to-face

E.

Real-time, multiauthoring editing software

F.

Charting/diagramming

Full Access
Question # 37

Which of the following should a project manager consult when deciding how to send updates regarding deliverables?

A.

Dashboard

B.

Status report

C.

Meeting minutes

D.

Communication plan

Full Access
Question # 38

A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality. Which of the following should the project manager do in response to the request?

A.

Decline because it is not included in the project scope.

B.

Assess the impact of the request and create a change request

C.

Create new functional and non-functional requirements for mobile devices.

D.

Revise the baseline of the project plan by adding the new requirements.

Full Access
Question # 39

A software development team completed the development and testing of a new accounting software system for a client. Which of the following should the team do next?

A.

User acceptance testing

B.

Unit testing

C.

Performance testing

D.

Audits and inspections

Full Access
Question # 40

A utility company issued a directive stating that projects impacting operating systems will not be executed during hurricane season. Which of the following is being acknowledged by this directive?

A.

Company brand value

B.

National environments

C.

Standard operating procedures

D.

Local emergency policies

Full Access
Question # 41

Question # 41

Which of the following best describes the results?

A.

No correlation exists between the extra hours worked and the number of defects in the code.

B.

A positive correlation exists between the extra hours worked and the number of defects in the code.

C.

A non-linear correlation exists between the extra hours worked and the number of defects in the code.

D.

A negative correlation exists between the extra hours worked and the number of defects in the code.

Full Access
Question # 42

A project team evaluated the performance of a new reporting system and the quantity of queries to be processed during predetermined time stamps.

Question # 42

Which of the following is the current status of the process?

A.

Based on the rule of seven, the process is under control

B.

The amount of data is insufficient to determine if quality is low.

C.

The process is out of control and should be revised.

D.

The goal should be adjusted since most of the data points are close to the lower limit.

Full Access
Question # 43

A project manager buys an extended warranty for a set of servers. Which of the following risk management strategies is the manager using?

A.

Transfer

B.

Avoid

C.

Accept

D.

Mitigate

Full Access
Question # 44

A project manager is using an agile methodology to lead the implementation of several features that should be developed concurrently. Which of the following items should the project manager view as a concern?

A.

Each feature will have a different owner.

B.

The majority of the team can only meet on a weekly basis.

C.

The stakeholders have provided a specific deadline to meet.

D.

Each feature has a specific budget allocation.

Full Access
Question # 45

An external developer working on a project at an hourly rate provides an invoice at the end of a month for 80 hours spent on a project. The project manager realizes that there were no tasks assigned to this developer last month. Which of the following actions should the project manager take first?

A.

Consult other developers.

B.

Escalate the issue to the project steering committee.

C.

Request the developer provide justification.

D.

Decline the invoice.

Full Access
Question # 46

Which of the following project types is best managed as a waterfall project?

A.

Data analytics

B.

Research

C.

Software development

D.

Real property

Full Access
Question # 47

Several months after a project has ended, a project team member is still charging time to the project and is unable to charge time to new projects. Which of the following did the project manager neglect to do?

A.

Remove the team member ' s access.

B.

Release the project resources.

C.

Collect the stakeholders’ feedback.

D.

Have the closeout report approved.

Full Access
Question # 48

A new project manager was assigned to a project during the execution phase. The project manager discovers a lot of potential areas that may prevent the project from completing deliverables Which of the following should the project manager do first?

A.

Review the project risk register.

B.

Update the defect tracker.

C.

Meet with stakeholders to discuss concerns.

D.

Add the potential blockers to the issues list.

Full Access
Question # 49

A key stakeholder recommends to a senior developer that a new feature be added. The new feature is not part of the current requirement documentation. Which of the following is MOST likely happening?

A.

Scope creep

B.

Collecting requirements

C.

Decision-making

D.

Project change

Full Access
Question # 50

After determining the appropriate maintenance window, which of the following should occur NEXT in the operational infrastructure change process?

A.

Implement the change.

B.

Approve the test plan.

C.

Notify customers.

D.

Develop a rollback plan.

Full Access
Question # 51

A project manager is assigned to a project that has contracted with vendors. Which of the following actions should the project manager most frequently take? (Select two).

A.

Update the issue log

B.

Create a project charter

C.

Validate the status report

D.

Monitor performance

E.

Approve deliverables

F.

Baseline the project schedule

Full Access
Question # 52

A new project manager takes over a project midway through the schedule. Which of the following should the project manager do first before continuing the project?

A.

Access project artifacts.

B.

Arrange a brainstorming session.

C.

Conduct a kickoff meeting.

D.

Establish communication channels.

Full Access
Question # 53

Functional managers are reluctant to provide a project manager with resources for a project because they think the project should include a certain scope. The project manager reviews the project documentation and confirms the items the functional managers wanted to include were out of scope. Which of the following would be the best course of action for the project manager to take?

A.

Satisfy the functional managers by agreeing with their point of view in order to get the necessary resources.

B.

Advise the functional managers to submit a change request, record the issue in the issue log. and escalate the issue to the project sponsor

C.

Schedule a team meeting to discuss creative ways to incorporate the scope without having to formally submit a scope change request.

D.

Inform the functional managers that the project will produce only what has been approved and project modifications cannot be made at this point.

Full Access
Question # 54

A project is running over budget, and due to new legislation in the country, the company needs to release all its contractors on the project or hire them as full-time employees. Which of the following should the PM do next to comply with the new legislation?

A.

Use only full-time employees even if the project is delayed.

B.

Hire all team members to avoid any delay in the project.

C.

Close the contract and pay the contractors cash for the remainder of the project.

D.

Look for an overseas vendor to finalize the project work.

Full Access
Question # 55

Due to budgetary and time constraints, a PM scheduled a meeting with all stakeholders during the planning phase to review the requirements and come to an agreement on the minimum viable product that would be acceptable. Which of the following would be used to document this input?

A.

Project change management plan

B.

Project management plan

C.

Project transition plan

D.

Project communication plan

Full Access
Question # 56

During the initiation phase, a stakeholder and the project manager discuss the business reasons and benefits of the project. The stakeholder requests these items be documented for approval. Which of the following should be used to document this information?

A.

Statement of work

B.

Business case

C.

Requirements document

D.

Work breakdown structure

Full Access
Question # 57

Which of the following contract types in project procurement has the highest risk for the buyer?

A.

Time and material

B.

Cost-plus

C.

Fixed-price

D.

Unit price

Full Access
Question # 58

A few weeks before a project is scheduled to be completed, the client asks to add a new feature to the product that is being developed. The project manager analyzes the project schedule and determines the feature can be implemented quite easily without affecting the completion date. Which of the following should the project manager do first?

A.

Escalate the change to the CCB.

B.

Review the requested change.

C.

Document the change recommendations.

D.

Validate the implementation of the requested change.

Full Access
Question # 59

Which of the following is the best example of a breach of physical security?

A.

System user IDs being used by multiple individuals

B.

Printers that do not request user authentication

C.

Developers having full access to both development and production environments

D.

Project documentation that is only kept on a removable device

Full Access
Question # 60

An enhancement is set to be released into production, and availability issues need to be avoided. Before the release, which of the following should be the most important consideration?

A.

System downtime

B.

Risk assessment

C.

Cost

D.

Customer experience

Full Access
Question # 61

Which of the following is a reason to use a SOW on a project?

A.

To find out the contact information for the vendors

B.

To review the list of stakeholders

C.

To ensure the team stays within the scope of the contract

D.

To give explicit instruction on how to execute the work

Full Access
Question # 62

A project manager must determine how ideas from the organization and results from the review committee should move through the enterprise for a new project. Which of the following does the project manager need to do?

A.

Establish communication channels

B.

Plan a kickoff meeting

C.

Develop a responsibility assignment matrix

D.

Identify the stakeholders

Full Access
Question # 63

Which of the following best describes the difference between the current state and the desired future state in project management?

A.

The current state is a high-level view of the project scope, and the desired state is what is happening right now.

B.

The current state is where the business is now, and the desired state is where the project is going to take the business.

C.

The current state is a high-level view of the project scope, and the desired future state is the specific outcome the business wants.

D.

The current state defines the specific outcome the business wants, and the desired state documents what is happening now that prevents it.

Full Access
Question # 64

Which of the following best describes a manufacturer ' s obligation to repair or change, without extra costs, any part of a product that is not functioning?

A.

Service-level agreement

B.

Functional testing

C.

Warranty period

D.

Audit

Full Access
Question # 65

Following a successful release, a project manager sent a survey to all stakeholders to gain an understanding of opportunity areas for the team. Which of the following can use the survey results as an input?

A.

Daily stand-up

B.

Project momentum

C.

Performance feedback

D.

Meeting minutes

Full Access
Question # 66

A project sponsor is struggling to provide the latest project status information on a weekly executive call. Which of the following should be reviewed?

A.

Meeting cadence

B.

Gap analysis

C.

Dashboard

D.

Adoption training

Full Access
Question # 67

Which of the following BEST illustrates how team members with different roles should interact on the team?

A.

SOW

B.

WBS

C.

RACI

D.

PERT

Full Access
Question # 68

Two project team members are assigned to set up new work areas and are disagreeing about the placement of hardware and peripherals at the end users ' desks. The requirements do not specify where to place the items, just what is needed in each space. Which of the following should the project manager do to resolve the conflict?

A.

Send out a survey to the potential end users to gather information about the best functional setup for work productivity.

B.

Provide clear instructions based on personal preference and aesthetics for setup of the work areas.

C.

Explain to team members that the placement of the items is not too important, as long as everything is connected and working.

D.

Facilitate a meeting between team members to review the pros and cons of the different configurations so as to encourage an amicable solution.

Full Access
Question # 69

Project team members enter their time sheets into a system that also displays incurred project cost. Which of the following systems can perform this task?

A.

EDRMS

B.

CRM

C.

CMS

D.

ERP

Full Access
Question # 70

During a project closure meeting, stakeholders did not agree that the project achieved the expected results. Which of the following documents should the project manager consult?

A.

Work breakdown structure

B.

Project charter

C.

Quality plan

D.

Solution design

Full Access
Question # 71

A PM is working on a strategy to store records. Which of the following dements must be included in this plan? (Select TWO)

A.

Data management

B.

Issue management

C.

Work breakdown structure

D.

Document management

E.

Communication management

F.

Risk management

Full Access
Question # 72

During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?

A.

Issue log

B.

Defect log

C.

Change log

D.

Task board

Full Access
Question # 73

Which of the following BEST identifies the intent and purpose of a project closeout report?

A.

To provide documentation of lessons learned

B.

To document variances from the initial project baseline

C.

To validate that a project has been successfully completed

D.

To release resources and terminate all access rights

Full Access
Question # 74

During the project initiation phase, a project team has been identified. Which of the following is the NEXT step for the project manager?

A.

Determine budget constraints.

B.

Validate the business case.

C.

Update the project charter.

D.

Create a project schedule

Full Access
Question # 75

A meeting agenda included the following items:

. Review the goals of the project.

. Review the progress of the project.

. Discuss if the project is ready to move forward.

Which of the following best describes this type of meeting?

A.

Stand-up

B.

Monthly status

C.

Gap analysis

D.

Gate review

Full Access
Question # 76

A stakeholder raises a concern with a project manager because of the number of emails that have been received before a coding release. Which of the following actions should the project manager take next?

A.

Inform the CCB to stop communication.

B.

Establish a RACI matrix.

C.

Escalate the communication issues.

D.

Revise the communication plan.

Full Access
Question # 77

While managing a project, a PM is assigned to work on a second project. The second project becomes more complex and monopolizes the PM ' s time. The PM learns that a similarly time-consuming project was executed previously in the organization. Which of the following actions should the PM take?

A.

Perform a root cause analysis.

B.

Organize a stakeholder meeting

C.

Escalate the issue to the CCB

D.

Contact the PMO for assistance.

Full Access
Question # 78

A project manager receives an escalation from an external group reporting that an expected deliverable should have been available some time ago. After analysis, the project team realizes the deliverable was provided on time. Which of the following should the project manager do next?

A.

Request a change control ticket.

B.

Review the schedule plan.

C.

Refine the project documentation.

D.

Revise the communication plan.

Full Access
Question # 79

A project is moving into the user acceptance testing phase. Several resources will be needed to execute different steps in the testing plan. Which of the following would be the best tool to allow the resources to remain at their desks and only react when needed?

A.

Ticketing system

B.

Videoconference

C.

Simple messaging system

D.

Corporate social media

Full Access
Question # 80

A client continues to present the project team with additional changes. To help with agreeing upon an expected delivery date, the project manager sets up a meeting with stakeholders. Which of the following should this meeting identify?

A.

Project scope

B.

Project communication

C.

Project budget

D.

Project objectives

Full Access
Question # 81

A critical business initiative introduced new processes and technology to the organization. Which of the following approaches should be used to ensure the deliverables are increasingly adopted and leveraged by the organization over time?

A.

Creation of a social news forum

B.

Management directives to use the new system

C.

New user kickoff meeting

D.

Monthly feedback and training sessions

Full Access
Question # 82

A project sponsor has asked for a log listing all the bugs identified within a specific project. Which of the following tools should the project manager provide to the sponsor?

A.

Change log

B.

Issue log

C.

Risk register

D.

Defect log

Full Access
Question # 83

A project manager is organizing and running a project closure meeting. Which of the following best describes the objective of this meeting?

A.

To move the system to a production environment

B.

To obtain project sign-off

C.

To formalize the end of the contract

D.

To release resources

Full Access
Question # 84

Which of the following requires the MOST availability from the business team?

A.

SDLC

B.

Scrum

C.

PRINCE2

D.

Waterfall

Full Access
Question # 85

During an agile project, a team member checked the project artifacts in order to anticipate when all the work should have been completed. Which of the following charts was the team member most likely consulting?

A.

Pareto chart

B.

Milestone chart

C.

Burndown chart

D.

Gantt chart

Full Access
Question # 86

During a brainstorming meeting, a project manager identifies multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals. Which of the following plans is the project manager creating?

A.

Procurement

B.

Communication

C.

Quality assurance

D.

Risk

Full Access
Question # 87

Project members are based in three countries and each work remotely Which of the following would a project manager use to improve internal project communication?

A.

Progress reporting

B.

Meeting minutes

C.

Team touch points

D.

Change management

Full Access
Question # 88

A company is adapting its strategy almost every quarter, and the product might be different at the end of the project. Which of the following is the best methodology for the project manager to use?

A.

Scrum

B.

Extreme programming

C.

Waterfall

D.

Kanban

Full Access
Question # 89

A project manager notices a resource is overloaded and not completing tasks on time. After reviewing the Gantt chart, the project manager notices the resource has multiple simultaneous tasks that could be executed independently. Which of the following should the project manager do next?

A.

Change the precedence of the tasks to " finish-to-start " .

B.

Evaluate and modify the schedule with a burndown chart

C.

Assign additional resources to prevent overwork.

D.

Perform critical path analysis

Full Access
Question # 90

While developing a project charter, a PM discovers that some of the legal requirements have not been addressed during the project concept preparation, which could result in significant financial penalties against the organization. The PM knows that implementation of appropriate changes is costly and will exceed the budget and scope of the project. Which of the following should the PM do FIRST?

A.

Escalate the finding to the change control board.

B.

Add a risk to the risk register for validation.

C.

Consult the RACI matrix to identify ownership of the risk.

D.

Have a meeting with the project sponsor and main stakeholders.

Full Access
Question # 91

Project team members are leaving the company due to a stressful work environment. The project manager needs to capture this concern about potentially losing team members again. Which of the following logs should the project manager use?

A.

Risk

B.

Change

C.

Defect

D.

Issue

Full Access
Question # 92

A project manager is unclear about the budget and timeline prior to the start of a project. Which of the following best describes what type of meeting needs to take place?

A.

Kickoff

B.

Demo

C.

Stand-up

D.

Status call

Full Access
Question # 93

As a result of lessons learned, a project manager convenes a meeting to understand the poor quality of the project documentation. During the meeting, project team members provide insights from their perspectives and discussions with group members. Which of the following is the project team doing?

A.

Executing the approved contingency plan

B.

Constructing an Ishikawa diagram to determine the root cause

C.

Using a Pareto chart to prioritize the different causes

D.

Engaging the senior management team in regard to the issue

Full Access
Question # 94

Several stakeholders have asked about how the requirements are being covered by the deliverables and the progress of each requirement Which of the following would be the best tool the project manager can use to provide this information to the stakeholders?

A.

Risk register

B.

Change log

C.

Traceability matrix

D.

Project status report

Full Access
Question # 95

A team found a deficiency in an application and is proposing improvements, but the sponsor requests a business case. Which of the following best describes the intended objective of the business case?

A.

To identify the potential risk and issues for the project

B.

To determine the timeline and budget of the project

C.

To define the specific tasks required to create the project

D.

To specify what problem is being solved by the project

Full Access
Question # 96

A project team was instructed to refurbish old desktops. The following provides the details of the issues observed:

Question # 96

Which of the following issues should be addressed FIRST?

A.

Replace missing peripherals because this process can be easy and less costly.

B.

An old operating system issue has the most amount of occurrences.

C.

Damage to the monitor has the highest percentage.

D.

Address each issue as discovered to avoid rework.

Full Access
Question # 97

A PM is working with stakeholders in the discovery phase and comparing the cost of the project to the cost savings the project will produce when it is complete. The output of this exercise will produce the:

A.

ROI.

B.

SOW.

C.

RFI.

D.

RPR

Full Access
Question # 98

A customer requests some changes to a product, and those changes are approved by the CCB. Which of the following should be changed first?

A.

ROI

B.

KPI

C.

RACI

D.

SOW

Full Access
Question # 99

In order to complete a major project deliverable, very specialized resources are required for some tasks. The PM failed to take into consideration during planning that the required resources would be available for fewer hours than required. Which of the following should the PM do first to make schedule changes?

A.

Add a new risk.

B.

Perform an impact analysis.

C.

Escalate to the sponsor.

D.

Raise a change request.

Full Access
Question # 100

A project manager is receiving reports of the actual project expenditures and, based on this information, is making adjustments to the budget. In which of the following phases does this occur?

A.

Planning

B.

Closure

C.

Initiation

D.

Execution

Full Access
Question # 101

After a product is released for production, a tester performs a test to ensure its basic functionality is working as expected. Which of the following is the tester performing?

A.

Smoke test

B.

Stress test

C.

Penetration test

D.

Regression test

Full Access
Question # 102

A project team wants to compare two potential vendors ' costs and risks for completing project tasks. Which of the following visualizations will best facilitate this analysis?

A.

Scatter diagram

B.

Decision tree

C.

Pareto chart

D.

Histogram

Full Access
Question # 103

Which of the following considers factors such as reliability, scalability, security, and cost-effectiveness within project goals and objectives?

A.

DevOps architecture

B.

Computing services

C.

Data warehouse

D.

Networking and connectivity

Full Access
Question # 104

Which of the following describes three-tier architecture?

A.

Conceptual, design, and implementation stages

B.

Presentation, application, and data processing

C.

Network, software, and security

D.

Development, testing, and production environment

Full Access
Question # 105

A project manager and team are currently in the planning phase of a project. Which of the following should the team do during this phase?

A.

Identify and assess stakeholders.

B.

Hold daily status meetings.

C.

Remove access and plan the project sign-off.

D.

Review assumptions and constraints for input to the risk register.

Full Access
Question # 106

Which of the following is an activity related to operational security?

A.

Processing background screening

B.

Setting up a firewall

C.

Establishing a zone of trust

D.

Implementing multifactor authentication

Full Access
Question # 107

A project team needs a tool to store information that is captured throughout the life cycle of a project. The information should be stored in a centralized location that is easily accessible to all stakeholders and will provide search functionality. Which of the following tools should be used?

A.

Secure folder

B.

Real-time, multiauthoring editing software

C.

Digital whiteboard

D.

Wiki knowledge base

Full Access
Question # 108

A project team has implemented a new system and needs to ensure it is usable. Which of the following should be performed first?

A.

Provide end-user training.

B.

Decommission old systems.

C.

Release external consultants.

D.

Monitor performance.

Full Access
Question # 109

Which of the following contract types presents the most risk for the buyer?

A.

Cost-plus percentage of cost

B.

Cost-plus-incentive fee

C.

Cost-plus-fixed-fee

D.

Firm fixed-price

Full Access
Question # 110

A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?

A.

RFI

B.

RACI

C.

WBS

D.

SOW

Full Access
Question # 111

When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?

A.

Critical paths

B.

Resources

C.

Milestones

D.

Work breakdown structures

Full Access
Question # 112

A team member identifies a critical issue in production. Which of the following should the project manager apply?

A.

Compliance check

B.

Release plan

C.

Rollback plan

D.

Validation check

Full Access
Question # 113

As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?

A.

Update the work breakdown structure.

B.

Review the backlog.

C.

Seek baseline approval.

D.

Establish the resource pool.

Full Access
Question # 114

Which of the following is a quantitative key performance indicator?

A.

The project sponsor ranked the graphics of an application as four out of five.

B.

The project implements the application in ten different geographical regions.

C.

The workers complete tasks on average 25% faster using a new application.

D.

The use of a multimedia interface appeals more to users under the age of 21.

Full Access
Question # 115

An existing application that is highly utilized by clients is moving to a new release. Which of the following environments contains this application?

A.

Development

B.

Production

C.

Testing

D.

QA

Full Access
Question # 116

A project manager wants to be confident that the most crucial functions of a new software build work and that the software is ready for the next testing phase. Which of the following types of testing should be done?

A.

Performance

B.

Smoke

C.

Regression

D.

Unit

Full Access
Question # 117

Which of the following artifacts should project team members use if they want to identify who to communicate with and at what level?

A.

Concept of operations

B.

WBS

C.

Integrated master schedule

D.

RACI

Full Access
Question # 118

While working in a collaborative, online brainstorming session, team members send private messages to the facilitator about challenges understanding others when they are speaking due to accents and background noises. Which of the following should the facilitator do to overcome the challenges?

A.

Instruct the team members to set their speakers to maximum volume and mute their microphones.

B.

Require everyone to turn on their cameras and use the same background filter.

C.

Encourage the use of the chat and use plain language when speaking.

D.

Allow one person to speak at a time after receiving acknowledgment from the facilitator.

Full Access
Question # 119

After a release, the project sponsor received an escalation from an executive about the extension of the downtime after the scheduled window. Which of the following should be added to the issue log?

A.

Continuous integration

B.

Rollback plan

C.

Customer notification

D.

Automated testing

Full Access
Question # 120

A software engineer notices that the newest update to the reporting software includes many new features that were not defined in the requirements document. Which of the following steps should the engineer take next?

A.

Seek approval before continuing

B.

Edit the requirements document

C.

Disregard the update

D.

Notify the users of the new features

Full Access
Question # 121

A project manager has decided to outsource portions of a project and will conduct a separate procurement. In which of the following phases does this task occur?

A.

Planning

B.

Initiating

C.

Controlling

D.

Executing

Full Access
Question # 122

A developer recommends modifying an existing portion of code that is not part of the scope and is causing low performance on the current solution. Which of the following actions should the project manager most likely take?

A.

Ask a developer to create a change request.

B.

Do nothing because recommendation is scope creep.

C.

Ask a developer to implement the recommendation.

D.

Communicate the change status.

Full Access
Question # 123

A project team is developing an application that will allocate a building ' s parking spaces. The building owner does not agree with using corporate colors in the application and has blocked

the release of the beta version for testing. Which of the following best describes what the project manager should have done in the initiation phase to prevent this issue?

A.

Review of existing artifacts

B.

Development of an issue log

C.

Identification and assessment of stakeholders

D.

Establishment of accepted communication channels

Full Access
Question # 124

Which of the following would help a project manager identify that project goals have been reached?

A.

Audit report

B.

Key performance indicators

C.

Backlog

D.

Lessons learned

Full Access
Question # 125

A PM is responsible for implementing a new customer relationship management system and has learned that the sales organization is reluctant to utilize the new system. The organization ' s reluctance could jeopardize the success of the project. Which of the following steps should be taken to understand the adoption issues and gain organizational acceptance of the initiative? (Select TWO).

A.

Train users on the proper use of the system.

B.

Escalate the issue to the CCB

C.

Hold sessions to understand user challenges.

D.

Track system usage and report user activity.

E.

Log the issue in the project risk register.

F.

Create a memorandum of acceptable use.

Full Access
Question # 126

In the initiation phase, a PM is reviewing the objectives, the high-level requirements, the success criteria, and the budget resources. Which of the following action items will benefit from this analysis?

A.

Developing a RACI

B.

Identifying and assessing stakeholders

C.

Assigning project resources

D.

Establishing communication channels

Full Access
Question # 127

A project manager is comparing the documentation attached to invoices from main vendors with the requirements described in the SOW in order to decide if all are correct. Which of the following best describes what is being performed?

A.

Approving deliverables

B.

Enforcing vendor rules of engagement

C.

Reporting overall process

D.

Scheduling team touch points

Full Access
Question # 128

A project manager is meeting with business stakeholders to define the time frame for a go-live to occur without impacting business operations. Which of the following is the project manager working on?

A.

Validation check

B.

Downtime window schedule

C.

Customer notifications

D.

Risk analysis

Full Access
Question # 129

Which of the following statements best describes Kanban?

A.

A workflow management method to maximize efficiency and enable continuous improvement.

B.

A board representing the different stages of a software solution.

C.

A dashboard used to facilitate scope alignment with the project team.

D.

A spreadsheet representing development tasks and how they relate to the business process being improved.

Full Access
Question # 130

The project team determines that software installation can only begin after the desktops have been installed and can be powered on. Which of the following dependencies does this represent?

A.

External

B.

Internal

C.

Mandatory

D.

Discretionary

Full Access
Question # 131

A visual that displays team progress was created for stand-up meetings. Which of the following BEST describes what is being represented on the visual?

A.

Decision board

B.

Whiteboard

C.

Task board

D.

Dashboard

Full Access
Question # 132

A project manager is coordinating multiple teams of six people that will each provide feedback for a new product. The teams are recording their opinions, which may be used to define the final product that is sent to mass production. Which of the following best describes this technique?

A.

Demonstration

B.

Workshop

C.

Brainstorming

D.

Focus group

Full Access
Question # 133

A project manager provided details regarding the completion of the following tasks:

Vendor selection took less time than planned.

Equipment procurement took less time than estimated.

Equipment installation went according to schedule.

Which of the following should the project manager update?

A.

Change log

B.

Project Gantt

C.

Issue log

D.

Requirements traceability matrix

Full Access
Question # 134

Which of the following is the best example of CapEx?

A.

Taxes

B.

Vehicles

C.

Salaries

D.

Utilities

Full Access
Question # 135

During the project initiation phase, a project manager needs to assign individual roles and responsibilities to various team members. Which of the following would best enable them to do so?

A.

ERP

B.

RAM

C.

JAR

D.

CCB

Full Access
Question # 136

Which of the following contract types would be most beneficial to both parties in cases in which the scope of the project has a large number of unknowns?

A.

Variable costs

B.

Fixed costs

C.

Front-loaded

D.

Time and materials

Full Access
Question # 137

Which of the following provides the best justification for undertaking a project?

A.

Scope statement

B.

Business case

C.

Sponsor request

D.

Project charter

Full Access
Question # 138

Which of the following pieces of data are examples of Pll?

A.

Medical record and test result values

B.

IP address and email address

C.

Name and year of birth

D.

X-ray and blood type

Full Access