Construction-Manager Questions and Answers

Question # 6

Who owns the float in a typical project critical path schedule?

A.

Construction manager

B.

Owner

C.

Project

D.

Contractor

Full Access
Question # 7

Which of the following is a key element of a safety culture?

A.

Time is of the essence

B.

Maximizing profit

C.

Prompt accident notification

D.

Ownership and management buy-in

Full Access
Question # 8

The current construction market is extremely busy, and the trade/sub-contractors are being very selective in the projects they bid on. What options do owners have when the marketplace is vastly different from when their project was a concept to when its ready to be advertised?

A.

Market conditions should not be a factor in when a project is advertised.

B.

Postpone advertising for one year.

C.

Advertise the project and award to lowest bidder.

D.

Consider the impacts of current market conditions and revise project strategy.

Full Access
Question # 9

Construction schedule coordination and enforcement means and methods techniques, and sequence of work are typically assigned to the construction manager under which delivery method?

A.

CM at Risk(CMAR)

B.

Design-Build (DB)

C.

Multi-Prime

D.

Design-Bid-Build (DBB)

Full Access
Question # 10

It is ideal for the CM to assist in mitigating potential impacts and unforeseen issues that may develop as early as the

A.

construction phase.

B.

post-construction phase.

C.

design phase.

D.

pre-design phase.

Full Access
Question # 11

A CM is managing a rebranding program that includes 120 stores with a contract value of $1,200,000. The program schedule plans the completion of 10 stores per month for a total of 12 months. At the end of month 10, the CM receives an application for payment indicating completion of 100 stores and a cumulative earned value of $1.1 million.

Which statement most accurately portrays program status?

A.

On schedule, pay application accurately reflects percentage complete.

B.

Behind schedule, pay application exceeds percentage complete.

C.

Behind schedule, pay application accurately reflects percentage complete.

D.

On schedule, pay application exceeds percentage complete.

Full Access
Question # 12

Lifecycle analysis of a project will provide the greatest impact during which of the following phases?

A.

Pre-Design

B.

Design

C.

Construction

D.

Procurement

Full Access
Question # 13

A CM's responsibility for safety on the jobsite includes

A.

no obligation for safety as it is the contractor's responsibility.

B.

a professional obligation shared with others.

C.

certifying subcontractor compliance.

D.

drafting the contractor's safety plan.

Full Access
Question # 14

Float, date, and duration are examples of

A.

schedule elements.

B.

schedule parameters.

C.

constraints.

D.

logic elements.

Full Access
Question # 15

The CM is tasked with analyzing the schedule variance of a project on a regular basis. The contractor's recent payment application includes a dramatic increase in earned hours than what was budgeted for the project. This MOST likely indicates

A.

the contractor is making more profit than anticipated.

B.

the project is ahead of schedule.

C.

the contractor will be submitting change orders.

D.

the project is behind schedule.

Full Access
Question # 16

A construction manager is responsible for the bid review and evaluation of an $85 million high school project. All bids must be submitted in person at the client's Purchasing Office by 1:00 PM EST and stamped by the CM's team. While preparing for the bid opening, the CM noticed that one of the contractor's bids was submitted a day earlier to a new clerk, but was date and time stamped after the bids were due. What should the CM do in this situation?

A.

Put the contractor's unopened bid in tight security until the bid opening has been completed.

B.

Send the bid back to the contractor and apologize for the mishap.

C.

Include the unopened bid. since it clearly was an oversight.

D.

Inform the Owner and review the instructions to bidders for guidance on how to proceed.

Full Access
Question # 17

During the design phase of a project, the owner had requested the design team develop mitigating strategies due to expected budget concerns. During the procurement process, the agency CM should advise the owner consider

A.

incorporating Time and Material Alternates into the bid documents.

B.

incorporating Add/Deduct Alternates into the bid documents.

C.

evaluating Phase Alternates in the bid documents.

D.

evaluating Schedule Alternates in the bid documents.

Full Access
Question # 18

Bid contract documents have been prepared for LEED certification, but the owner has decided not to formally register for LEED certification. The owner still requires LEED equivalency. How does the CM proceed with the bid process?

A.

Inform owner that LEED process as specified in the specifications will not be implemented.

B.

Notify bidders at prebid conference of changes in LEED registration.

C.

Instruct architect to make changes to bid documents to reflect deletion of LEED registration.

D.

Issue bid instructions that owner will not register project for LEED certification but the contract terms remain unchanged.

Full Access
Question # 19

When applying Business Intelligence (also known as data mining) to manage large volumes of construction project data, the source data must

A.

first exist in hard copy format.

B.

include advanced algorithms.

C.

first exist in digital format.

D.

include outliers and missing data.