Question # 6

Which of the following communicates in-transit inventories to a warehouse?

A.

Bill of distribution

B.

Master schedule

C.

Order acknowledgment to warehouse

D.

Distribution requirements planning

Full Access
Question # 7

From a management perspective, the choice of transportation mode and routing primarily will affect the:

A.

forecasted demand.

B.

safety stock level.

C.

manufacturing system.

D.

planning horizon.

Full Access
Question # 8

Which of the following criteria is the most meaningful measure when evaluating the effectiveness of distribution systems in fulfilling customer needs?

A.

Order-fill rate

B.

Cash-to-cash cycle time

C.

Performance to budget

D.

The level of inventory

Full Access
Question # 9

Which of the following goals is the primary outcome of distribution requirements planning?

A.

Accurately feed the gross requirements into the master production schedule

B.

Decouple the distribution plan from the production plan

C.

Deliver products in the quantities requested by the customer

D.

Maintain an appropriate inventory level at all locations

Full Access
Question # 10

Production is being planned to emphasize the utilization of a critical and very expensive piece of capital equipment. Which of the following production planning strategies should be used?

A.

Chase

B.

Level

C.

Cost-based

D.

Combination

Full Access
Question # 11

If the master production schedule is overstated, which of the following short-term actions is most appropriate?

A.

The demand time fence should be moved out.

B.

Lot sizes should be decreased.

C.

Safety stocks should be decreased.

D.

Firm planned orders should be rescheduled.

Full Access
Question # 12

Which of the following factors typically has the largest effect on the schedule developed by an advanced production scheduling (APS) system?

A.

Amount of past due work

B.

Performance measures used

C.

Precision of the capacity data

D.

Priorities of the master schedule items

Full Access
Question # 13

A Canadian-based company has a long-term contract with a US-based supplier. The Canadian company has been experiencing short shipments and variations of the supply lead time with the US supplier for a few months. Which of the following is the most appropriate action for the master production scheduler in this situation?

A.

Ask the purchasing manager to work with the supplier to improve their shipping quantity accuracy and lead time stability.

B.

Ask the purchasing manager to terminate the contract with this supplier, and look for a better supplier.

C.

Apply safety stock and safety lead time while planning the master production schedule.

D.

Apply safety lead time according to the target service level while planning the master production schedule.

Full Access
Question # 14

A forecasting method that responds slowly to changes in demand would be most appropriate when the historical demand pattern shows a major:

A.

seasonal component.

B.

random component.

C.

trend component.

D.

cyclical component.

Full Access
Question # 15

Which of the following is typically an output of the master scheduling process?

A.

Sales forecasts

B.

Resource requirements plans

C.

Interplant demands

D.

Projected available balances

Full Access