Big Halloween Sale - Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70dumps

PSP Questions and Answers

Question # 6

How many workdays occur from the start of the Product Testing to the Product Available milestone?

A.

70

B.

100

C.

60

D.

90

Full Access
Question # 7

In the normal schedule, excluding Activity 1000. what activity(s) are concurrent with Activity 3001?

A.

4001, 5001, and 6001

B.

2003 and 7001

C.

4001 and 5001

D.

2004, 4001. and 5001

Full Access
Question # 8

Project delays are best analyzed

A.

After either the contractor or the owner acknowledges ^responsibility for the delay.

B.

Contemporaneously with the delay.

C.

By an expert after the project is finished when complete records are available and the impact is known.

D.

Late in the project.

Full Access
Question # 9

Select the most appropriate explanation for use of a winter/wet weather seasonal calendar for use in this project?

A.

to highlight a time when there are more holidays and work therefore will be slower and there will be more absenteeism

B.

to denote a time during which work may not progress as fast as planned and cost and risk may be elevated

C.

to provide a key to co-a weather for safety meetings

D.

to show a difference in the calendar year

Full Access
Question # 10

Who can define KPls?

A.

The client and the performing/contracting entity

B.

Environmental regulators

C.

The subcontractors and suppliers

D.

Accounting and Finance

Full Access
Question # 11

The Scope of Work divides the major deliverables into smaller more manageable components for all of the following EXCEPT to:

A.

improve the accuracy of cost, time, and resource estimates

B.

facilitate clear responsibility assignments

C.

define a baseline for performance measurement and control

D.

establish the Performance Measurement Baseline values

Full Access
Question # 12

The Work Breakdown Structure (WBS) is established to reflect the:

A.

lowest level of the project estimate

B.

lowest level reporting back to the program WBS

C.

lowest level of effort scope

D.

lowest level where the work is managed

Full Access
Question # 13

Which of the following is not an internal stakeholder?

A.

Owner

B.

installer

C.

Subcontractor

D.

Prime Contractor

Full Access
Question # 14

Which of the following is NOT true?

A.

Remaining durations can exceed original durations.

B.

Constraints can interfere with the longest path calculation.

C.

Multiple calendars can affect the total float calculation.

D.

A network must contain only one Critical Path.

Full Access
Question # 15

Which activity is drawn in the incorrect position?

A.

Activity G.

B.

Activity E.

C.

Activity C.

D.

Activity D.

Full Access
Question # 16

Should activities be coded with the EBS value?

A.

Yes. the project coding should roll up to EBS values

B.

No. only a few EBS values exist at the activity level

C.

No. the EBS Is much higher than activity coding

D.

Yes. the EBS is the most important project coding level

Full Access
Question # 17

Which letter of the alphabet best approximates the graphical shape of a project's cumulative cost baseline, or budgeted cost of work scheduled?

A.

C.

B.

B.

C.

S.

D.

W.

Full Access
Question # 18

What is the cycle time?

A.

5 minutes

B.

17 minutes

C.

14 minutes

D.

6 minutes

Full Access
Question # 19

Constructability is NOT intended to:

A.

optimize engineering and procurement

B.

correct deficiencies in the project design

C.

balance project and environment goals

D.

integrate construction knowledge into the design

Full Access
Question # 20

In an earned value-based system, a schedule performance index of less than one for the project indicates the project is:

A.

ahead of schedule

B.

on schedule

C.

complete

D.

behind schedule

Full Access
Question # 21

Value engineering is:

A.

targeted at the design itself

B.

intended to provide the least life-cycle cost

C.

established to provide the greatest value

D.

intended to determine if the project will be completed economically

Full Access
Question # 22

Total float is defined as the amount of time an activity can be delayed without impacting

A.

The overall project completion

B.

The buoyancy of a successor activity

C.

The next activity

D.

The end of that activity

Full Access
Question # 23

Scenario: You are providing construction management services for a small office building project. Your duties include reviewing and approving the contractor's baseline schedule. The contractor has submitted the first baseline schedule for the project.

The contractor subsequently submits a CPM schedule for its baseline schedule submittal. As part of your review, you look at the durations for each activity in the schedule. How do you determine if a duration of 10 work days for drywall installation is accurate?

A.

The duration for drywall installation should De proportional to how critical the activity is

B.

Review the drywall quantity, methods and location with the project superintendent to determine a reasonable duration

C.

Review the location of drywall work in the contract drawings

D.

Divide the quantity of drywall by the construction crew's dairy production rate for this work

Full Access
Question # 24

EBS is an acronym for:

A.

Elongated Budget Synopsis

B.

European Basic Schedule

C.

Enterprise Breakdown Structure

D.

Eventual Base Structure

Full Access
Question # 25

Based on the stated costs, what percentage of the total cost comes from the 2000 series of activities?

A.

3.3%

B.

2.2%

C.

23%

D.

2 4%

Full Access
Question # 26

The schedule or budget at completion less the estimate at completion is___________.

A.

the schedule variance

B.

the variance at completion

C.

the cost variance

D.

the profit or loss for the project

Full Access
Question # 27

When are KPIs defined?

A.

At project initiation

B.

At NTP

C.

At the start of the Construction Phase

D.

After the Bidding Phase

Full Access
Question # 28

As a change to the network for the current update, activity 6002 is required to begin ten days after the beginning of activity 6001. Which is the simplest logic organization?

A.

A start-to-start relationship with a ten-day lag assigned to activity 6001; activity 6002 will be dependent on activity 6001

B.

A start-to-start to relationship for both activities 6001 and 6002 with a ten-day lag assigned to activity 6002.

C.

A start-to-finish relationship with both activities 6001 and 6002 having a ten-day lag

D.

A finish-to-start relationship with a ten-day lag assigned to activity 6002; activity 6001 will be dependent on activity 6002

Full Access
Question # 29

What changes to logic would eliminate Activity B from the critical path?

A.

Replace the relationship from Activity B to Activity C with SSO

B.

Reduce the lag value of the relationship from Activity A to Activity B from 5 to 0

C.

Add a SS 15 relationship from Activity A to Activity B and replace the relationship from Activity A to Activity B with FFO

D.

Replace the relationship from Activity A to Activity B with FFO and add an FSO relationship from Activity A to Activity C

Full Access
Question # 30

Activity C is a

A.

Contentious activity.

B.

Continuous activity.

C.

1-day activity.

D.

Milestone.

Full Access
Question # 31

What portion of Activity B is on the critical path?

A.

Last half of the activity

B.

None of it

C.

First half of the activity

D.

The whole activity

Full Access
Question # 32

In a "crashed" schedule, which is a chain of activities that precede activity 2004?

A.

1001, 2001, 2002, 2003

B.

2001, 2002, 2003, 2007

C.

1001, 2002, 2003

D.

1001, 2002, 2002, 2003, 3001

Full Access
Question # 33

A KPI is an acronym for:

A.

Key Planning Index

B.

Known Planning Impediments

C.

Keep Parameter Integrity

D.

Key Performance Indicator

Full Access
Question # 34

Identify the minimum project duration.

A.

20 months.

B.

16 months.

C.

19 months.

D.

21 months.

Full Access
Question # 35

Why does activity 1001 have two successor activities?

A.

Because the late finish of 1001 and the late start of 7001 require two successors

B.

Because the problem could not effectively work with only one successor

C.

Because there are two defined logic paths for the work

D.

Because the duration of activities 2001, 2002 and 200.f require two successors

Full Access
Question # 36

Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?

A.

15 days.

B.

0 days.

C.

5 days.

D.

10 days.

Full Access
Question # 37

If a detailed estimate is NOT available to assist in the formulation of activity durations but unit quantities have been identified, what information can be utilized to estimate work package/activity durations?

A.

The Eichleay formula

B.

Historical production rates

C.

Time impact analysis

D.

Black-Scholes model

Full Access
Question # 38

When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT required to determine the critical path?

A.

Detailed listing of working days for each calendar used

B.

Predecessor and successor listing with logic type and lag duration, preferably sorted by activity ID

C.

Assigned party responsibility for each work task

D.

Tabular listing of activities showing duration, calendar ID, early and late dates

Full Access
Question # 39

Which of the following are NOT considerations or constraints of the planning process for construction scheduling?

A.

Consideration of all stakeholders.

B.

Value engineering.

C.

Project variables.

D.

Interest rate of owner's construction bonds.

Full Access
Question # 40

Estimate to complete (ETC) is __________________.

A.

The expected remaining cost needed to complete an activity, group of activities or the project

B.

The costs actually incurred in accomplishing the work performed

C.

The expected total cost of an activity, group of activities or the project

D.

The value of the completed work expressed in terms of the budget assigned to that work

Full Access
Question # 41

When should the project documents be reviewed to assess their impact on the organization and administration of a project?

A.

After the Award and before the NTP

B.

During the Bid Phase

C.

Before the commercial decision to Did on the project

D.

After the NTP

Full Access
Question # 42

Which of the following types of delay will NOT result in a time extension and additional compensation for a contractor?

A.

Non-excusable delay

B.

Compensable delay

C.

Non-compensable delay

D.

Excusable delay

Full Access
Question # 43

Using the "normal" schedule, what is the early finish date of activity 10002 and its total float?

A.

12-27-03 and 24 days of float

B.

12-18-03 and 4 days of float

C.

12-17-03 and 4 days of float

D.

12-18-03 and 25 days of float

Full Access
Question # 44

The characteristic of the precedence diagramming method that models construction projects differently than the arrow diagramming method is that it____________.

A.

uses arrows to signify logic in a network

B.

allows more than one critical path to be represented

C.

can be used to calculate the late start and late finish of all activities

D.

allows multiple relationship types to be associated with activities

Full Access
Question # 45

Scenario: You are providing construction management services for a small office building project. Your duties include reviewing and approving the contractor's baseline schedule. The contractor has submitted the first baseline schedule for the project.

The contractor has included several reports with its submittal, including a report that sorts all activities by total float. What is the value of this report?

A.

Allows you to review activities in the order they could start

B.

Allows you to confirm the current logical flow of the work

C.

Allows you to determine which activities will take the longest

D.

Allows you to determine which activities will be performed by the owner

Full Access
Question # 46

During proofing of the product manual, a problem was discovered requiring 15 days additional time to affect a correction. How can the date of availability be maintained?

A.

Expedite Draft Product Manual by 5 days

B.

Delay Release for Manufacture by 5 days

C.

Delay Manufacture Product by 5 days

D.

Expedite Package Product by 5 days

Full Access
Question # 47

Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?

A.

407 days

B.

362 days

C.

255 days

D.

267 days

Full Access
Question # 48

Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?

A.

Multiple calendars.

B.

Start and finish constraints.

C.

Preferential logic.

D.

Front end loading.

Full Access
Question # 49

Using the crashed schedule, if you start Activity 2002 on 12 August 2021. what is the finish date for Activity 2002?

A.

19 Sep 2021

B.

08 Sep 2021

C.

09 Sep 2021

D.

27 Aug 2021

Full Access
Question # 50

Using one crane capable of 30 lifts per day. for 3 column pours requiring 28 lifts each, plus assorted work in the area requiring an additional 150 lifts, what are the lowest planned workdays for this work?

A.

3 workdays

B.

18 workdays

C.

8 workdays

D.

7 workdays

Full Access
Question # 51

Assuming activities 2001 through 2004 comprise the same WBS element, construct a WBS summary activity for activities 2001 through 2004. Use the normal schedule, what is the cost of the activity?

A.

$289.000

B.

$321.000

C.

$193,000

D.

$327,000

Full Access
Question # 52

The addition of which of the following relationships would cause a logic loop?

A.

O H - D

B.

O C - J

C.

O F-I

D.

O l-C

Full Access
Question # 53

Using the "normal" schedule, and assuming you are billing on the last day of the month for previous month and for appropriate partial months, how many invoices will you have for this project?

A.

42.

B.

36.

C.

40.

D.

37.

Full Access
Question # 54

Using the normal schedule, what is the early finish date and total float of Activity 10002?

A.

24 Nov 2023. and 24 days of tree float

B.

24 Dec 2023. and 24 days of tree float

C.

17 Dec 2023. and 4 days of total float

D.

21 Dec 2023. and 4 days of total float

Full Access
Question # 55

What was the original planned duration for Activity A through Activity G?

A.

26.

B.

28.

C.

24.

D.

25.

Full Access
Question # 56

What day would Activity C complete if the duration of Activity A was reduced by five days?

A.

35

B.

30

C.

45

D.

40

Full Access
Question # 57

What is the result of a forward pass calculation?

A.

Value of total float for individual activities

B.

Early start and early finish date for individual activities

C.

Value of free float for individual activities

D.

Critical path

Full Access
Question # 58

If all other work proceeds according to the Baseline plan, how many times will the critical path change?

A.

2.

B.

1.

C.

Does not change.

D.

3.

Full Access
Question # 59

What is the actual duration as of the status date or data date of Activity B?

A.

7.

B.

3.

C.

0.

D.

4.

Full Access
Question # 60

You are the project manager of the AHQ project. This project is scheduled to last for six months and will require S345.000 to complete. If the project completes earlier than scheduled your organization will receive a bonus of S5 000 per day of early completion Management has asked you to develop an aggressive schedule to realize as much of the bonus as possible but management does not want you to increase the costs of the project beyond $1,000 per day of the bonus realization. Which of the following approaches will likely add costs to the project?

A.

Using the critical chain method

B.

Fast tracking

C.

Crashing

D.

Rebaseline the project

Full Access
Question # 61

The Cost Estimate is NOT developed to:

A.

quantify cost, and price the resources required by the Scope of Work

B.

predict uncertain future costs

C.

providing the basis for budgets

D.

determine the project performance goals

Full Access
Question # 62

Activity durations are normally estimated in an intuitive and subjective way. All of the following will improve duration accuracy EXCEPT

A.

Use gross building square footages. The pluses and minuses all average out.

B.

Look at each activity independently and don't follow specific logic paths when assigning activity durations.

C.

Divide activities into smaller activities. This will increase activity detail and duration estimate accuracy.

D.

Use the people responsible for performing the work as a resource to assign activity durations.

Full Access
Question # 63

Time-scaled logic diagrams are

A.

Only calculated using a computer.

B.

The same as a pure-logic diagram.

C.

Used to calculate the most probable activity duration.

D.

Logic networks that are drawn to match the calendar.

Full Access
Question # 64

Which of the following are NOT normally included in the project scope statement, either directly or by reference?

A.

Project objectives in terms of cost, schedule and quality measures

B.

Project contract between the contractor and owner

C.

Project justification

D.

Project deliverables

Full Access