Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?
In what process is the authorization to deliver the project's products given?
Who should act as the communication channel between a project and corporate or programme management?
Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?
Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?
Which of the following statements about the Closing a Project process are true?
1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage.
2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.
Which plan provides the Business Case with costs during the Initiating a Project process?
Identify the missing word in the following sentence. The guiding obligations and good practices which determine whether the project is genuinely being managed using PRINCE2 form the [ ? ] of the method.
Which product documents the information needed to demonstrate continued business justification?
Which is assumed to be a customer's responsibility in the PRINCE2 customer/supplier environment?
Identify the missing words in the following sentence.
Project assurance personnel [ ? ] the project manager.
What should the 'managing product delivery' process ensure?
1. That the planned products meet their quality criteria
2. That the stage plan is kept up to date
3. That the project board is provided with progress information
4. That the planned products are delivered within tolerance
Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?
To meet the minimum requirements for applying the progress theme, when must the business justification be reviewed?
Identify the missing word(s) in the following sentence. The Quality theme provides a set of rules and procedures which ensure that the [ ? ] created meet(s) the needs of the business.
How does the project plan help to support the 'manage by stages' principle?
Which statement describes the 'Implement' step within the recommended risk management procedure?
According to the ‘continued business justification’ principle, what should happen to the funds when a project can no longer be justified?
How should the "managing a stage boundary' process be used towards the end of a project's final delivery stage?
Which report must be used to inform the project board of a predicted deviation from agreed stage limits?
How does PRINCE2 ensure that the specific management needs of an organization are met?
What must be produced to meet the minimum requirements when applying the change theme?