Question # 6

An architect is assembling a solution for a customer that has three sites, a small central team, a requirement for each site to keep operating independently during a link failure, and a wish to see the whole estate reported on in one place. Which elements must the assembled solution include? (Choose two.)

A.

Processing and data at each site sufficient for it to run on its own during an outage.

B.

A central store holding every site's data in full, from which reports are produced.

C.

A means of collecting each site's summarised results centrally for reporting.

D.

Identical hardware at all three sites, so spares are interchangeable and stocked once.

E.

A dedicated connection between each pair of sites.

Full Access
Question # 7

A private cloud offers a defined catalogue of environments teams may request. What does the customer give up in exchange for the speed this provides?

A.

Some freedom for teams to specify environments that differ from the catalogue.

B.

Being able to see how much each of the teams is using across the whole of it.

C.

The option to expand capacity as demand grows over time.

D.

The ability to enforce security policy across the environments teams obtain.

Full Access
Question # 8

What does a solution handover need to leave the customer with?

A.

A schedule of the maintenance tasks due in the first year.

B.

A complete record of every decision taken during the build.

C.

The ability to operate what has been built.

D.

Contact details for the engineers who performed the work.

Full Access
Question # 9

Which inputs shape which offering is recommended to a customer? (Choose three.)

A.

The requirements the customer has stated.

B.

What sells most frequently in the customer's region.

C.

The customer's existing deployed estate.

D.

The offering with the longest published support lifecycle.

E.

The constraints the customer operates under.

Full Access
Question # 10

A customer is considering expanding a solution that was justified two years ago on a business case they approved. How should the expansion proposal treat that original case?

A.

Set it aside, since the expansion must be justified on its own merits.

B.

Restate it, since the reasons for the original investment still apply.

C.

Replace it, since two years of operation have made the original assumptions obsolete.

D.

Show what it delivered, and build the new request on that record.

Full Access
Question # 11

During discovery, a customer's operations lead says any new system must use the monitoring tooling already in place. Its security lead says all new systems must be monitored through a separate platform the security team has just adopted, instead of the existing tooling. Neither is aware of the other's statement. How should the architect handle this? (Choose two.)

A.

Design to satisfy both, so that neither lead has to change position.

B.

Adopt the security requirement, since security constraints usually take precedence.

C.

Record both requirements rather than choosing between them privately.

D.

Adopt the operations requirement, since the existing tooling is already paid for.

E.

Bring the two leads together, so that the conflict is resolved by the customer rather than the supplier.

Full Access
Question # 12

Why does an architect consider the alliance partner ecosystem when positioning a solution?

A.

Because partner components are usually less expensive than the equivalent alternatives available elsewhere.

B.

Because the customer's workloads usually depend on components from more than one supplier.

C.

Because a solution must include at least one partner component to be supportable.

D.

Because partner components remove the need to assess the customer's existing estate.

Full Access
Question # 13

A customer asks for a proposal to replace the environment an established workload runs on today. Which facts about the current arrangement most need establishing first? (Choose two.)

A.

Which other systems the workload exchanges data with in its current environment.

B.

How many years the present setup has been running.

C.

The workload's real consumption in its current environment, rather than what was provisioned.

D.

Which supplier provided the environment being replaced.

E.

What was originally paid for the equipment now in use.

Full Access
Question # 14

A customer's stated need is partly met by one offering and partly by another. How should the architect position them?

A.

As one solution, showing which part of the need each element answers.

B.

Beginning with the offering that covers the larger share of the need.

C.

As a single combined item, so the customer is not asked to weigh two purchases.

D.

As two options, so that the customer can choose which part of the need to address first.

Full Access
Question # 15

At handover, every requirement in a customer's brief has been demonstrated except one: failover to a second site, which cannot be shown until that site is built next quarter. How should the architect handle the handover?

A.

Hand over what is demonstrated, and agree the failover test with the customer as an open acceptance item.

B.

Declare the solution complete, since the failover design was reviewed and approved during the design stage.

C.

Withhold the whole handover until the second site is built and failover has been shown.

D.

Show failover between two systems within the first site instead, and record the requirement as met.

Full Access
Question # 16

A review of a customer's design produces five observations: a requirement about recovery time is unmet, the naming convention is inconsistent, one assumption about network capacity is unconfirmed, a component is a generation behind the current release, and installation is planned to be carried out by the customer's own team. Which observations should be raised as findings requiring action before commitment? (Choose two.)

A.

The naming inconsistency, since it will outlast the project and shape every later change.

B.

The unconfirmed capacity assumption, because the design must be reworked if it proves wrong.

C.

The component a generation behind, because newer options are available.

D.

The unmet recovery-time requirement, because the design does not do what was asked.

E.

The installation by the customer's own team, since mistakes during the build would delay go-live.

Full Access
Question # 17

A healthcare provider is replacing an ageing patient-records platform. It tells the architect that records must stay under its own governance, that clinicians need the system available during a network outage at any single site, and that its IT team has no capacity to take on a new operating model this year. Which characteristics must the positioned offering demonstrate? (Choose three.)

A.

The new operating model is documented in full so the IT team can adopt it when capacity allows.

B.

It can be run within the practices the team already follows.

C.

Custody of the data does not pass to a third party.

D.

Clinicians at a site whose connection has failed continue working through a second data centre.

E.

Each location holds enough locally to keep operating on its own.

Full Access
Question # 18

What should the output of a solution review be?

A.

A costed comparison against the alternatives that were not selected.

B.

A revised design incorporating and applying the reviewer's own preferred approach throughout.

C.

A decision on whether the solution should proceed to implementation as it currently stands.

D.

Findings that state where the solution does and does not meet the customer's requirements.

Full Access
Question # 19

A customer asks for a recommendation to support a seasonal workload that runs heavily for two months and is close to idle for the rest of the year. A colleague proposes the offering the team most often sells, on the grounds that it is well proven with other customers. What is the weakness in that reasoning?

A.

It assumes the seasonal workload will continue to follow the same pattern next year.

B.

It positions an offering before the customer has confirmed a budget for the work.

C.

It answers from what is familiar rather than from what this customer's demand pattern requires.

D.

It relies on references from other customers, which cannot be shared while a proposal is still being prepared.

Full Access
Question # 20

An architect intends to include a component from an alliance partner in a customer solution. What should be established before it appears in the proposal?

A.

That the combination has been proven to work as the solution will use it.

B.

That the partner's component is the market leader in its category.

C.

That the partner will price the component more keenly if it is ordered with the rest.

D.

That the customer has no existing relationship with a competing supplier.

Full Access
Question # 21

Adding a partner component to a solution introduces something the customer's operations team must account for. What is it?

A.

A requirement to retrain the team on an entirely new discipline.

B.

A separate management network that must be built alongside the existing one.

C.

Another element with its own lifecycle, updates and support route.

D.

An obligation to hold spare units of that component on site, and to keep track of them.

Full Access
Question # 22

A customer states two requirements that pull against each other: everything must be recoverable within a very short window after a failure, and the total spend must stay inside a fixed cap that will not cover full duplication. How should the architect proceed?

A.

Ask the customer to raise the cap, since the two requirements cannot both be satisfied as stated.

B.

Establish with the customer which workloads genuinely need the short recovery window, and protect those.

C.

Design to the recovery requirement and present the resulting figure to the customer, since availability outranks cost.

D.

Design to the cost cap and note that the recovery window will not be met across the estate.

Full Access
Question # 23

A customer is standing up a new analytics workload and has told the architect that its networking estate is being refreshed at the same time, that its analytics team already works with a specific software vendor, and that whatever is proposed has to be supportable by the customer's existing operations process. Which considerations belong in positioning the workload alongside the wider ecosystem? (Choose two.)

A.

Whether the analytics results must be retained under the customer’s existing data policy.

B.

How the proposed solution and the refreshed networking are supported together rather than separately.

C.

Whether the analytics workload could be deferred, and restarted, after the refresh.

D.

Whether the analytics workload could be hosted by the incumbent software vendor directly.

E.

Whether the analytics team's existing software choice is accommodated by what is proposed.

Full Access
Question # 24

A customer’s private cloud has reached the limit of its available capacity, and a development team’s request cannot be met. What does this tell the customer?

A.

The pool needs replenishing, since self-service cannot issue what does not exist.

B.

The requesting team exceeded its entitlement and should be asked to justify the request.

C.

Workloads should be moved to public capacity until the private environment is expanded.

D.

The self-service mechanism has failed and should be investigated as a defect.

Full Access
Question # 25

Which of these is a technical requirement?

A.

The solution must reduce the cost of running the current estate.

B.

The programme must be delivered before the end of the financial year.

C.

The board must be able to report progress to shareholders each quarter.

D.

The service must remain available if one site loses power.

Full Access
Question # 26

What does a customer most need a proposal to make clear about an expansion?

A.

What each of the added parts is rated to do, and where all of that has been written down for them.

B.

How things will be different for them once it is done, and what it will take to get there.

C.

The alternatives considered, and the reasons each was set aside during design.

D.

The vendor roadmap for these offerings, over the next three years.

Full Access
Question # 27

A customer is attracted by managing its whole estate consistently but has not considered what adopting it involves. What should the architect tell them it will require? (Choose two.)

A.

A single supplier for the equipment deployed at every location.

B.

An operations team large enough to cover all locations during working hours.

C.

The locations being brought into scope rather than managed as they are now.

D.

Agreement on how things will be done, where locations currently differ.

E.

The estate being consolidated into a smaller number of locations.

Full Access
Question # 28

An architect is combining elements whose refresh cycles fall in different years. Why does this matter to the customer?

A.

It determines which supplier holds responsibility, and for which element.

B.

It sets when the customer faces its next round of change and cost.

C.

It decides which component the customer should standardise on first.

D.

It fixes the order in which the components must be installed.

Full Access
Question # 29

A start-up expects its user numbers to grow substantially over two years but cannot say how quickly. It has limited capital, a small engineering team that would rather build product than run infrastructure, and no regulatory constraint on where its data sits. Which characteristics should the positioned offering demonstrate? (Choose two.)

A.

The environment is dedicated to the start-up, so no other tenant can affect it.

B.

Capacity is reserved ahead of the user numbers the start-up expects, so nothing is ever held up.

C.

Day-to-day upkeep demands very few staff hours.

D.

The engineering team can move the product elsewhere within two years without penalty.

E.

Supply expands as the load actually rises.

Full Access
Question # 30

While reviewing another team's design, an architect finds that one of the customer's stated requirements can be read in two ways, and that the design satisfies only one of them. What should the review record?

A.

That the requirement should be removed until the customer restates it unambiguously.

B.

That the requirement needs clarifying, and which reading the design assumes.

C.

That the design is non-compliant rather than ambiguous, since one valid reading of the requirement is unmet.

D.

That the design is compliant, since a defensible reading of the requirement is satisfied.

Full Access
Question # 31

A customer with workloads spread across edge sites, its data centre and a public cloud says it cannot tell where its capacity is being consumed, and wants to reduce waste. What should be addressed first?

A.

Establishing a single view of what is consumed across all three locations.

B.

Renegotiating the commercial terms at each of the three locations.

C.

Consolidating the workloads into whichever location currently has the lowest unit cost.

D.

Reducing the capacity at each location by an agreed percentage.

Full Access
Question # 32

A review finds that a design meets every requirement but leaves one low-likelihood failure unmitigated, and mitigating it would roughly double the cost. How should this be reported?

A.

It need not be reported, since the design satisfies the stated requirements.

B.

As a defect, since a residual failure mode remains in the design.

C.

As an accepted risk, described so the customer can confirm they accept it.

D.

As an item for a future phase, once budget allows.

Full Access
Question # 33

A customer opens a conversation by naming the specific offering it intends to buy, before describing any requirement. What is the appropriate response?

A.

Proceed with the named offering, since the customer has already made its decision.

B.

Understand what led them to that choice, then test it against what they need.

C.

Set the named offering aside and conduct discovery as though it had not been mentioned.

D.

Present alternatives to the named offering so the customer can compare before deciding.

Full Access
Question # 34

A customer states a requirement that cannot be met by any available arrangement within their stated budget. What is the architect's obligation?

A.

To say so plainly, and set out what could be achieved instead.

B.

To decline the opportunity, since the requirement cannot be satisfied.

C.

To propose the arrangement that meets the requirement and let the customer find the funds.

D.

To propose the closest available option without drawing attention to the shortfall.

Full Access
Question # 35

An architect wants to propose expanding a customer's deployed solution. What evidence makes the proposal most credible to the customer?

A.

Case studies from organisations of a comparable size in the same sector.

B.

A summary of the capabilities the customer has not yet adopted from across the wider portfolio.

C.

Benchmarks showing how the newer offerings perform against the deployed generation.

D.

Observations from the customer's own running solution that show where it is under pressure.

Full Access
Question # 36

A customer's proposed solution depends on a component supplied by an alliance partner, on a network refresh scheduled for the same quarter, and on a data migration the customer's own team will perform. The customer has asked what could delay the launch. Which dependencies most deserve to be called out? (Choose two.)

A.

The migration, because it relies on a team whose availability the project does not control.

B.

The network refresh, because the parts of it the solution relies on must be complete before launch.

C.

The partner component, because components from other suppliers are inherently less predictable.

D.

The customer's change process, because every element will have to pass through it.

E.

The launch date, because dates set before design completes are usually optimistic.

Full Access