In regards to proper change management procedures, which of the following would be the FINAL activity?
Which of the following are components of an internal / external communication plan? (Select Two).
During the execution phase, a customer approaches the project manager demanding a change. Which of the following are the steps the project manager should take? (Select Two).
A project manager has been engaged to deliver a project in South America and does not speak Spanish. More than 50 percent of the project team will be Spanish speaking. Which of the following would be the project managers BEST option?
A stakeholder wants information on how frequently the project manager will provide a status report. Which of the following documents would be the BEST place to find this information?
Which of the following contract types places the LEAST amount of risk on the seller?
Work must be overlapped and completed in parallel rather than sequentially within the critical path in order to meet the end date of the project. Which of the following would be utilized?
A project manager is two weeks into a project when an unexpected delay occurs. Material that is needed to complete the project could be available in three business days; however, the project team believes that estimate is unrealistic and that it will take five business days for the material to arrive. The project manager was informed by another employee in the material company that it could take up to thirteen days to receive the materials. Which of the following estimates should be given to the project sponsor?
Which of the following is a representation of the difference between the planned costs of work completed compared to the actual cost at a point in time?
A qualitative analysis identified a server crash as an internal project risk with a medium probability and high adverse impact to the project. The project manager decides to manage this risk by authorizing the purchase and installation of a tape backup unit for the server, to prevent the potential loss of documents. Which of the following risk response strategies was applied in this circumstance?
The lessons-learned activity and formal acceptance documentation form part of which of the following process groups?
All of the following are part of the monitoring and controlling process group EXCEPT:
A project manager is performing activity sequencing with the project team. Each activity is written in a box with arrows linking the boxes according to their dependencies. Which of the following tools is the project manager utilizing?
A new project manager has been assigned to a high profile project. In order to determine project status, which of the following should the project manager do? (Select Two).
Which of the following shows the number of communication channels for a team with twelve stakeholders?
Which of the following components are included in a communication plan? (Select Two).
A project manager conducted a risk probability and impact assessment with the project team. In which of the following risk management processes did this occur?
Which of the following would be included in a project scope document? (Select Two).
The project team has completed phase testing. After testing, a subject matter expert (SME) notices that a component was skipped.
Which of the following should the project manager do?
The project is behind schedule. A project team member has analyzed the work performance information and has not created the weekly status update because they are uncertain when the update should be completed. Which of the following documents should the team member consult?
A company manager has turned in project objectives, and requests that the project manager start the project immediately. The project manager informs the company manager that the project cannot be started. Which of the following is an appropriate reason for not starting the project?
Communication preferences, cultural differences, and language barriers are BEST described as which of the following?
A project manager is responsible for meeting with the companys project review board to periodically evaluate the progress on a project. Which of the following is the role of the board?
Which of the following skills would be the MOST useful in assembling an effective project team in a functional organization?
Project team members are confused about their roles on a project. Which of the following is the FIRST technique the project manager can use to define their roles?
Which of the following is the BEST definition of a stakeholder? (Select Two).
Which of the following documents would be generated to solicit bids from outside vendors?
In a highway project 5 miles (8 kilometers) out of the total 15 miles (24 kilometers) have been completed. The BAC is $900,000. Which of the following represents the EV of this project?
A project sponsor has requested that the training be delivered in parallel to a project's implementation in order to ensure the project is delivered on schedule. If accepted, this request is an example of:
Faced with a complex project with many stages, which of the following is the BEST action for the project manager to take?
In which of the following situations would a risk be placed in the upper right quadrant of a risk matrix?
Which of the following can a project manager use to determine the critical path of a project? (Select Three).
Which of the following may require a modification to the project scope baseline?
The communication plan for a project is a subset of which of the following documents?
Which of the following would be contained in the problem statement within the project charter?
Which of the following tools is the BEST to measure data organized in time sequence?
Which of the following is the BEST point for a project manager to join a project?
If the EV is $3,000 and the AC is $4,000, which of the following would be the CPI for the project?
A project manager has just completed the planning of a project, but cannot start the project execution until granted permission from the project sponsor. This is an example of which of the following actions?
Which of the following is the BEST communication option for team building?
Which of the following occurs during a project kick-off meeting? (Select Two).
The project has been terminated. Which of the following should be conducted with the project team before they are released?
The project charter is an output of which of the following project phases?
Which of the following would be considered a valid strategy in response to an adverse risk?