Jayon has been asked to explain the gap analysis process to a new colleague. Which THREE of the following SHOULD Jayon cover?
An airline has agreed that the following Key performance indicator (KPI) will help measure one of the airline’s Critical Success Factors (CSFs) –customer service. The KPI is the percentage of customers rating our service as excellent in an independently administrator customer survey.
In the current year, the performance objective associated with KPI is 70%. The airline, therefore, aims for at least 70% of customers rating its service as excellent.
Which of the following activities in a Business Activity Model would establish whether the KPI and its associated performance objective is being achieved?
A large consultancy organization has assigned its BA. Girby, to a client called MetalCor, a manufacture of component for washing machines and fridge freezers. The management team of MetalCor need some help in understanding the problems they are experiencing with their production line. Recently. Reproduction has dipped to a record low and more parts are being return as fully.
Production line staff blame each other and the more staff Girby speaker to, the more issue she identifies. She having difficulty keeping track of the arising themes and how they relate to each other.
Which of the following would enable Girby to model the arising themes and how they relate to each other?
Efua is planning to use Design Thinking to improve the m-store customer experience She has asked you to suggest good techniques to help with the different stages.
Looking at the list of techniques and stages below which THREE combinations SHOULD be of benefit to Efua?
At a recent Board Meeting the Directors of an office fitting company ratified the company's mission as:
To meet or undercut all our competitors' prices'
Which of the following is MOST LIKELY to be the company's vision?
You have been discussing Paurs recent project with him He explained that he had needed to spend considerable time interviewing stakeholders and was now behind plan You asked him why he didn't use a workshop to avoid delays.
Which of the following MIGHT Paul reply'? Select the THREE that apply
A Business Analyst and a project Manager are producing a business case for an initiative, which aims to improve the cyber defense of a large financial services provider.
They met recently to review progress, and made the following notes for the next draft:
The benefits of cyber will be describes in quantitative terms, so we will need to describe these
Qualitatively.
We need to make it clear that we have fully explored the solution market, and we have considered a range of approaches to meeting the objectives of this project.
The threat posed to the organization from cyber attack, and therefore the justification for the project, needs to be clearly articulated.
Which of the following sets of elements of a business case will cover ALL of these points?
A business case contains the following in its management summary:
'The recommended option meets the new regulatory requirements. It will ensure our products remain in the marketplace and be the first to receive compliance certification, which will enhance our reputation as the market leader
New business policies and processes will be introduced, which may temporarily reduce productivity. The action plan will be communicated to all staff at the next monthly meeting?
Which TWO categories of costs and benefits are described in this extract?
A large retail company has asked a business analyst to investigate a problem with declining sales
Which of the following techniques is the business analyst MOST LIKLEY to use to identify underlying causes of this problem?
A company produces kitchens to order. Customers specify the design of the kitchen by using a computer-aided design tool, provided on the company’s website. The tool allows customers to select products, such as cabinets and cookers, and place them into a floor plan of the kitchen that they have specified.
Once the customer confirms the design, an order is placed and the customer is given a planned installation date for the kitchen. The company orders the raw materials for the kitchen and the kitchen is built by its skilled carpenters The customer can track the progress of the build on the Internet. If the kitchen Is likely to be delivered later than originally promised, a control action is taken to bring it back on schedule
A Business Activity Model (BAM) developed for the company has 'sell bespoke kitchens' as its doing activity.
Which of the following activities would be directly linked by a logical dependency arrow to or from this doing activity?
A business analyst has been carrying out investigations into a problem situation However, it is clear to the business analyst that, even after a number of interviews with individual stakeholders, some stakeholder s views still conflict.
Which investigation technique SHOULD be used to resolve the conflict and gain a consensus?
A business analyst is reviewing the stakeholder management strategy for a high profile Human Resources (HR) project Following an organisational restructure, Harvey's role has changed from Director of Operations to Director of HR and he has inherited sponsorship of the project Harvey was previously involved in the project, but had little interest because his focus was on the Operational Projects that he sponsored.
Which of the following sets of stakeholder management strategies represent appropriate approaches for Harvey; firstly, for when the project started and secondly now that his role has changed?
End users in one business area are unwilling to adopt a new finance management system (recently introduced by the innovation team), as they perceive that it is unnecessarily complicated and not useful. One of the end users in this business area has been very vocal and has been relying support from others since posting about it on the company’s intranet homepage.
The introduction finance system was initially supported by senior managers, but now users in other business area are also beginning to question whether they adopt the tool and are raising the issue with their managers.
The sponsor fully supports the decision to go ahead with the now tool and has made il very cleat to senior managers that he expects them to support this Initiative.
Which stakeholder management strategy SHOULD be taken with the senior managers?
Paula is a business analyst working for a small bespoke furniture manufacturing company. The newly appointed chief executive, Beverly, has asked Paula to lead an initiative to refresh and restate (where necessary) the organization’s plan for the next financial year. Paula recently led a planning worksope with senior managers and has made the following notes about issues raised in the worshop:
The company….
a) Aims to supply 10% of the local bespoke furniture market by the end of the financial year.
b) Will Invest In local radio advertising and appoint a creative team to develop an appropriate advertisement
c) Will await the final draft of the annual accounts before considering investing in a new range of high-tech chairs.
d) Will adopt new 3D printing technologies to gain an advantage when quoting for bespoke furniture designs
e) Recognises that bespoke furniture will always be more expensive than mass-produced, standard furniture
Which of these notes will go into her MOST analysis?
Ajay works I the payroll department of his organization. Payslips for every employee are printed automatically at the each month. He is about to distribute the monthly for each employee when he receives a notification from senior management explaining that the wish to give everyone a 10% bonus, for exceptional performance in the least quarter. Ajay is pleased with the bonus, but annoyed that the needs to re-print the monthly payslips.
Which types of business events can be identified from this scenario?
The business case for project XCON has been signed off and money has been allocated. The business analyst on the project wants to understand who the stakeholders are. how much authority they have, and how much involvement they want in the project so that a stakeholder management plan can be created.
Which technique SHOULD the business analyst use to gain this understanding?