Which 2 actions should the Team Leader take to implement the new Must
Have requirement?
An external web developer is to be contracted to create the new coffee bar
insurance area on the existing web site. The chosen web developer will only
agree to work on a ' fixed price for a fixed specification ' contract.
What action should the Project Manager take?
A difference of opinion on the outcome of an earlier project has created a
' them and us ' culture between the Sales Department and the Operations
Department.
What action should the Project Manager take to resolve this?
Time is running short and the Must Have requirements for the data entry screen
of the web page, as recorded in the Prioritised Requirements List, are not going
to be completed on time.
What action should the Project Manager take?
Which item is MOST likely to be considered as a pain point for a ‘Sales team member’ stakeholder?
Xan Insurance Company operates from one location - a large, open-plan
office in the centre of a city. Those employees that will be working within the
Solution Development Team are all based in this office but work at different
ends of the office in separate departments.
What action should the Project Manager suggest to ensure the most effective
collaboration of the Solution Development Team?
Which 2 statements represent appropriate entries for the Development
Approach Definition?
Answer the following questions about the contents of the DSDM
products.
Each of the following questions includes true statements about the project
but only two statements are appropriate entries for the DSDM product
identified.
Remember to limit your answers to the number of selections requested in
each question.
Which 2 statements represent appropriate entries for the Business Case?
Which 2 actions should the Technical Coordinator take to implement the new
Must Have requirement?
The Customer Services Director has announced the new structure at a large presentation for all Customer Services staff. The scale and design of the change have surprised many of the staff.
In the weeks immediately following the Customer Services Director’s initial presentation, there have been rumors of the Help Desk staff talking unhappily in small groups, with blame directed at " the management " for a recent period of poor performance of the department.
Which approach is the MOST appropriate way for the Customer Services Director to create early involvement in the change?
Using the information provided in the additional information, answer the following question on building a change analytics strategy.
Are the measures and source data to be monitored by the Human Resources and Facilities Manager likely to have any of the limitations of data analytics?
The Marketing Director has insisted that detailed requirements for the new
coffee bar insurance web pages should be clearly defined in the early phases
of the project.
What action should the Project Manager take?
Answer the following question about Schein ' s concept of survival and learning
anxieties.
Column 1 is a list of messages about the change given to Sales staff. For each
message in Column 1, select from Column 2 the appropriate element of
Schein ' s concept of survival and learning anxieties. Each selection from
Column 2 can be used once, more than once or not at all.


When receiving instruction on practical skills, which approach is MOST valuable to the learner?
Answer the following question about the agile change practices that are being
used by the Change Manager.
Column 1 lists statements made by the change team. For each statement in
Column 1, select from Column 2 the relevant agile change practice being
used.
Each selection from Column 2 can be used once, more than once or not at all.
Column 1
A new company logo, which
maintains features of the
existing UniCo logo, but also
represents expertise in
innovative solutions and mobile
applications, is needed as a
high priority for the rebranding
of UniCo.
Next time we work with the
Sales Team we will need to
schedule the fast-track training
of the Sales staff more carefully
as taking a member of staff
away from the sales work
caused operational issues.
3. Gaining access rights to make
amendments to UniCo ' s new
finance system is currently
causing issues and holding up
the updates to enable the
system to work with the new
processes.
The company procedures for
delivering large-scale computer
systems will need to be revised
to reflect the new processes for
mobile applications, taking an
estimated 60 days of effort.


The change management team is creating the change analytics strategy for the change programme.
Below is an extract of recipients, measures and source data that have been proposed.
Answer the following question about the sources of conflict in change
situations.
Column 1 is a list of statements about sources of conflict in change situations.
Column 2 contains the names of the eight sources of conflict identified by Art
Bell and Brett Hart. For each statement in Column 1, select from Column 2 the
source of conflict to which it MOST relates. Each selection from Column 2 can
be used once, more than once or not at all.



The Change Manager has mapped stakeholders onto a Power-Interest
Matrix, with the aim of identifying suitable actions for managing these
stakeholders.
The mapping below shows the current assessment made by the Change Manager.
The ' Interest in your change ' axis indicates a combination of the
stakeholders ' levels of active engagement and their buy-in for the Change
Programme.

Using the Scenario and the additional information provided for this question in the Scenario Booklet, answer the
following question about Stakeholder mapping and strategy.
Lines 1 to 4 in the table below consist of an assertion statement and a reason statement. For each line identify the
appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.



The Change Manager is discussing the relocation of the Selco staff to the UniCo office with the Operations Director. They are using the SCARF framework of people ' s social experience to guide management actions. Answer the following questions about the use of David Rock ' s SCARF framework to increase the motivation for change.
Some of the employees of UniCo are unhappy that they have been given no choice in losing additional leisure space to accommodate the transferred Selco employees. The Change Manager has arranged for affected members to meet with the Selco employees at a social lunch.
Is this an appropriate approach to reward the brain in the need for ' autonomy, ' and why?
To ensure that the UniCo change programme is successful, the Chief Executive Officer (CEO) knows that correctly assigning the key change roles will be essential.
Which 2 statements BEST explain why the CEO is appropriate for the role of Sponsor for the Change Programme?
The Change Manager has read Goleman ' s articles on the Hay-McBer six dimension model of organization climate. This gives leaders practical ways that
leadership style can improve organizational culture and performance as measured by staff surveys.
Answer the following question about recommendations a change manager could make to the CEO applying these six dimensions to improve climate across the
organization.
Column 1 is a list of recommendations the Change Manager has made to the CEO seeking to initiate or support a change in the organizational culture. For each
recommendation in Column 1, select from Column 2 the ' dimension ' in organizational climate MOST likely to improve as a result. Each selection from Column 2 can be
used once, more than once or not at all.


Towards the end of the Foundations phase of Project Increment 4, with the high-level requirements agreed, Hira, has asked the Developers to estimate the work required to deliver the Eco spa solution.

(Sukra Aroon has noticed that the Developers are spending excessive time creating their estimates. He has also observed that the document capturing their assumptions behind these estimates is nearly 20 pages long.
Based on his observation, what advice should he offer to the Developers?)
As Sprint 5 comes to an end, the Infrastructure Delivery Team is facing delays due to:
. Heavy rainfall affecting the Wellness Garden.
. Local supplier issues causing material delivery delays.
· Dependency on external contractors for hydrotherapy equipment.
The Operations Delivery Team is unable to finalize details of the hydrotherapy treatments without testing them in the
context of the facilities being constructed. The marketing materials cannot be generated until this work is complete.
In addition to the Developers, the teams include:

(Sarah Lark asks Mira Bachar how Spa treatments will remain aligned with the demands of guests post-launch. Mira explained that the Operations Delivery Team will address this in the final Sprint.
Is this approach aligned with AgilePM?)
Using the information provided in the additional information, answer the following question on building a change analytics strategy.
Do the measures to be monitored by the CEO represent appropriate ‘leading’, result-oriented measures for the effectiveness of the change interventions?
(Brinda believes that a meditation garden is essential for the holistic wellness experience, but Sukra, the Solution Architect, warns of risk associated with cultivating and maintaining the required plants.
How should Hira resolve this?)
(In the Ecolodge Panthera Resort (EPR) Project, answer the following questions about risk management.
In addition to the Developers, the teams include:
Mira Bachar (Guest Services Manager) – Product Owner for both Delivery Teams
Lee Tan (General Manager) – Business Advisor
Brinda Vyas – Business Visionary
Hira – Project Manager
Sukra Aroon – Solutions Architect
Wanida Anong – Regulatory Compliance Manager
Sarah Lark – Business Sponsor
Priya – Business Advisor
Select 2 answers to each question.
Which 2 statements describe the application of AgilePM ' s approach to managing risk?)
Which 2 statements explain why the Architecture Angels ' Marketing Director would be an appropriate Business Visionary?
When preparing for the workshop, which 2 items should the Workshop Facilitator be provided with?
Which 2 individuals would be suitable for the role of Workshop Facilitator?
During Timebox B, the ' Hoy for Hoy Hall ' Action Group disagreed about the planned outcome of the Timebox. The Project Manager organised a Facilitated Workshop to re-
engage this group and explore discrepancies in understanding.
Is this an appropriate application of Agile Project Management for this project?
Which 2 statements explain why the Contract Architect would be an appropriate Technical Co-ordinator?
Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about applying
controls to the end of Development Timebox C.
What action should the Project Manager take when considering the End of Timebox Review?
Using the project timeline given in the Project Scenario, answer the following question about application of Timeboxing on the Hoy Hall project.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.
Each option can be used once, more than once or not at all.

Assertion :
1. All internal works to be assigned to Timber Tigers throughout the project should be consolidated into one Structured Timebox.
BECAUSE
The Investigation step within each Structured Timebox requires everyone working within the team to jointly agree how the requirements of the Timebox will be met.
2. Acceptance criteria for the front rooms to be developed in Timebox A should be described in detail and agreed during the Timebox Kick-Off
BECAUSE
The aim of the Investigation step within each Timebox is to complete as much of
the development work as possible.
3. It is appropriate that both the Evolutionary Development phase and Deployment phase are shown in the first Project Increment.
BECAUSE
Each Timebox should comprise an Evolutionary Development phase and
Deployment phase.
4. It is appropriate that the outputs of Timebox C are scheduled for deployment at the end of the first Project Increment.
BECAUSE
A typical Timebox Plan should provide a schedule of high-level activities for the
imminent Project Increment.
5. It is appropriate that Earth Excavations create a detailed plan of activities they will complete during Timebox C.
Reason
BECAUSE
The Solution Development Team is responsible for planning the detail of all the
work of each Timebox.


During Refinement in Timebox B, a Review Session was scheduled for the Business Visionary to review the products completed during this Timebox, and to agree what
needed to be done before these would be acceptable.
Is this an appropriate application of Agile Project Management for this project?
There are several tests planned throughout the project to ensure the solution is fit for purpose and to validate the business solution as
it evolves.
Column 1 is a list of tests. For each test in Column 1, select from Column 2 the testing concept that it represents. Each selection from Column 2
can be used once, more than once or not at all.
Column 1
1) In order to get an objective
view, the financial transaction
function is to be tested by
someone from Finance who
has had no involvement in its
development.
2) Before the developer works on
the printing function for the
policy documents, the Sales
Manager will review a prototype
of the online application form
for the new coffee shop
insurance product with the
solution tester.
3) Security test scripts have been
provided by the company ' s
bank. These scripts will be used
to test the link from the
company ' s website to the
banking system, which is to be
developed specifically to achieve these tests
4.
The addition of the new coffee
shop insurance product may
threaten the stability of the
existing website. As a primary
route to market this is
unacceptable. The website ' s
capacity to run additional pages
is to be verified before any
other tests are performed.
5.
The Must Have and Should
Have requirements are to be
tested before the Could Have
requirements.
Column 2
Collaborative Testing
Repeatable Testing
Independent Testing
Prioritised Testing
Test-Driven Development

Answer the following questions about the acceptance criteria within the project.
Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.
The objective of Solution Development Timebox B is to ensure that the front and east wings are finished and approved. The Project Manager has pointed out that acceptance criteria for this part of the solution need to be agreed.
Is this an appropriate action related to acceptance criteria?
The project is now in the second week of Timebox C. This is the final Timebox of Project Increment 1 and is scheduled to take one month. The plan is to open
Hoy Hall to the public at the end of this Increment. A Must Have requirement of Timebox C is the implementation of a hotel reservation system.
At the Daily Stand-up, the Software Developer working on the reservation system reported that the framework for the system is now complete and ready for content.
However, this work cannot progress further due to a disagreement over the content. The Marketing Director insists the system is to hold professional photos and video
tours of the facilities and grounds. These require a lot of storage space and regular updates. The IT Operations Manager insists the system is to take less than 5GB of
storage space on the company server and require minimal maintenance.
The Team Leader has arranged a Facilitated Workshop to discuss the content and agree the way forward.
Remember to limit your answers to the number of selections requested in each question.
Which 2 individuals should the Facilitator invite to participate in the Workshop?
What action should the Project Manager take regarding the remaining windows?
Answer the following question about how risks will be reduced on the Hoy Hall Hotel project through successful application of the DSDM Principles.
Column 1 lists a selection of project risks identified on the Hoy Hall Hotel project. Column 2 is a list of the DSDM Principles. For each risk in Column 1, select from Column
2 the DSDM Principle which, if applied appropriately, would MOST help to reduce or mitigate that risk.
Each selection from Column 2 can be used once, more than once or not at all.


(Which one of the following actions should Hira take to balance the benefit of agile leadership whilst ensuring alignment of the Project Increment with project objectives?)
(Brinda Vyas has been absent for two weeks, leaving Mira Bachar and the Delivery Teams to make decisions. Recent strategic adjustments haven ' t been communicated to the Delivery Teams causing frustration and risk of rework.
Which 2 statements describe how this risk should be handled within the AgilePM framework?)
As Sprint 5 comes to an end, the Infrastructure Delivery Team is facing delays due to:
. Heavy rainfall affecting the Wellness Garden.
. Local supplier issues causing material delivery delays.
· Dependency on external contractors for hydrotherapy equipment.
The Operations Delivery Team is unable to finalize details of the hydrotherapy treatments without testing them in the
context of the facilities being constructed. The marketing materials cannot be generated until this work is complete.
In addition to the Developers, the teams include:

(It is appropriate that the Delivery Team Leaders attend this Project Sprint Planning Event?)
Brinda Vyas and Mira Bachar have agreed to use content from a marketing brochure to describe guest-centric Product Goals for the Eco-Spa. These goals describe specific treatments that the Spa might offer and will be used to identify prioritizable Product Backlog items that could contribute to that treatment. One such Product Goal is described as:
Hydrotherapy in Mineral-Rich Spring Pools
Immerse yourself in mineral-rich hydrotherapy pools designed to soothe muscies, improve circulation, and promote
deep relaxation. Experience the gentle power of temperature-controlled waters and therapeutic massage jets in a lush
and tranquil tropical garden setting and let nature ' s healing embrace rejuvenate both your body and your mind.
In addition to the Developers, the teams include:

(Which one of the following actions will ensure that Product Backlog items for the Hydrotherapy infrastructure remain aligned with the planned treatment experience throughout development?)
(Wanida Anong, working on some compliance issue in India, has limited availability to work with the Southeast Asia Delivery Teams.
Which 2 statements describe how this risk should be handled within the AgilePM framework?)
During the Foundations phase for Project Increment 4, Sukra Aroon held a meeting with Hira, Mira Bachar, andWanida Anong, to ensure alignment and compliance with EPR company policies, local regulations, and international standards. The meeting also clarified how financial and investment decisions would be made for Project Increment 4, ensuring alignment with EPR business priorities, and how this information will be tracked,
controlled and evidenced.
Wanida Anong, who works across multiple sites worldwide, attended the meeting in person but has limited availability throughout the Project Increment.

(During the meeting, Mira Bachar asked Sukra Aroon which AgilePM project artifacts should use to provide an auditable record of compliance requirements throughout Project Increment 4.
Based on AgilePM guidance, which of the following is an appropriate response?)
(Which 2 statements describe appropriate team behaviour for effective risk management?)
Mira Bachar has spoken with a guest who wanted an aromatherapy scent to remember their holiday. Inspired by this, Mira suggested creating a unique aromatherapy oil for spa treatments and guest sales, which could also serve as a marketing tool.
Brinda Vyas supports exploring the idea, but Sukra Aroon notes that selling products is not in scope and could introduce complexities.

(Which 2 of the following actions align with AgilePM practices for defining and estimating the work of Project Increment 4 during the Foundations phase?)
(At a meeting, Hira reminded all project participants of their role responsibilities.
Which statement does NOT comply with AgilePM?)
If the team cannot agree the system content, which 2 actions should the Workshop Facilitator take?